Res 110-89 7/18/1989RESOLUTION NO. //G'- ff
RESOLUTION TO ACCEPT THE BERT-SOUTHMOOR
DRAINAGE PROJECT AND AUTHORIZE FINAL PAYMENT
TO THE CONTRACTOR
WHEREAS, the City of Wichita Falls entered a unit price
contract with Terry Edwards Construction Company, Inc. with the
estimated total cost of $189,730. 00 and,
WHEREAS, the actual work was completed at a total cost of
194, 135.30 of which $182, 861. 04 has been previously paid to the
Contractor, leaving amount due of $11,274.26; and
WHEREAS, the City staff has inspected the work and found it
to be acceptable.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF WICHITA FALLS, TEXAS, THAT:
The Bert-Southmoor Drainage Project is hereby accepted and
the City Manager is authorized to make final payment to the
Contractor.
PASSED AND APPROVED THIS THE 18TH DAY OF JULY, 1989.
M A Y O R
ATTEST:
CITY CLERK