Res 199-90 12/6/1990RESOLUTION NO. /,ff-fa RESOLUTION TO ACCEPT THE 1989-1990 STREET REHABILITATION PROJECT AND AUTHORIZE FINAL PAYMENT TO B. D. HAYNES CONSTRUCTION COMPANY. WHEREAS, the City of Wichita Falls entered into a Unit Price contract with B. D. Haynes Construction Company with the estimated total cost of $397, 133 and, WHEREAS, the actual work was completed at a total cost of 396,498.44 from which $6,240. 00 has been deducted for liquidated damages and the contractor has been previously paid $382, 328.47, leaving amount due of $7,929.97 ; and, WHEREAS, the City staff has inspected the work and found it to be acceptable. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The 1989-1990 Street Rehabilitation Project is hereby accepted and the City Manager is authorized to make final payment to the contractor. PASSED AND APPROVED THIS THE 6TH day of December, 1990. MA Yom• ATTEST: A3-e//4 / , rte CITY C ERK