Res 134-93 9/7/1993RESOLUTION NO. / 141-V-5) RESOLUTION TO ACCEPT THE CDBG COUNTRY CLUB RECONSTRUCTION (PHASE I) PROJECT AND AUTHORIZE FINAL PAYMENT TO KEYSTONE CONSTRUCTION COMPANY WHEREAS, the City of Wichita Falls entered a unit price contract with Keystone Construction Company with the estimated total cost of 383, 128. 00 and, WHEREAS, the actual work was completed at a total cost of 388, 942 . 10 of which $381,163.26 has been previously paid to the contractor leaving an amount due of $7,778.84 ; and, WHEREAS, the City staff has inspected the work and found it to be acceptable. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The CDBG Country Club Reconstruction (Phase I ) Project is hereby accepted and the City Manager is authorized to make final payment to the contractor. PASSED AND APPROVED this the 7th day off September 1993. r M A Y O R ATTES 11r7 41W, I( CITY CL RK