Res 009-95 1/17/1995RESOLUTION NO. CA - (-05-
RESOLUTION TO ACCEPT RIVER ROAD WASTEWATER
TREATMENT PLANT ADDITIONS AND MODIFICATIONS
PROJECT AS COMPLETE AND AUTHORIZE FINAL
PAYMENT TO CONTRACTOR
WHEREAS, the City has a contract with Craig, Sheffield and
Austin, Inc. for the construction of certain modifications and
additions at the River Road Wastewater Treatment Plant;
WHEREAS, the original amount of the contract of $19,572,000
was changed by approved change orders during the progress of the
work to an adjusted contract price of $19,523,327.21;
WHEREAS, the actual amount of work accomplished was
$19,520,327.21, and the City previously has paid the contractor
an amount of $19,510,327.21, leaving an amount due to the
contractor of $10,000.00;
WHEREAS, the Contractor owes $2,642.09 in back taxes,
penalty and interest included, and this amount will be withheld
for payment to the Wichita County Tax Assessor unless the
Contractor will have paid the taxes in full, in which case the
full $10,000 payment will be made to the Contractor; and,
WHEREAS, the project has been certified by the design
engineer to be complete and to have been constructed in
accordance with the plans and specifications, and the staff has
recommended that Council accept the project as complete and
authorize a final payment to the contractor.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF WICHITA FALLS, TEXAS, THAT:
The River Road Wastewater Treatment Plant Modifications and
Additions Project is hereby accepted as complete, and the City
Manager is authorized to make a final payment of $10,000.00 to
the contractor, withholding $2,642.09 as necessary to make
payment of taxes, interest and penalty to the Wichita County Tax
Assessor.
PASSED AND APPROVED this the 17th day of January, 1995.