Res 019-95 2/7/1995RESOLUTION NO. /�?- RESOLUTION TO ACCEPT THE 1994 ALLEY REHABILITATION PROJECT AND AUTHORIZE FINAL PAYMENT TO SELMON ENTERPRISES WHEREAS, the City of Wichita Falls entered a unit price contract with Selman Enterprises with the estimated total cost of $278,877.50 and, WHEREAS, the actual work was completed at a total cost of $268,694.80 of which $232,262.08 has been previously paid to the contractor, leaving an amount due of $36,432.72; and, WHEREAS, the City staff has inspected the work and found it to be acceptable. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The 1994 Alley Rehabilitation Project is hereby accepted and the City Manager is authorized to make final payment to the contractor. PASSED AND APPROVED this the 7th y Februar 95 0 R ATTEST—IN IT_ CLERK