Res 054-95 4/18/1995RESOLUTION NO. -5-A E- RESOLUTION TO ACCEPT THE BARNA ROAD RECONSTRUCTION PROJECT AND AUTHORIZE FINAL PAYMENT TO MCGRATH BROTHERS CONCRETE WHEREAS, the City of Wichita Falls entered a unit price contract with McGrath Brothers Concrete with the estimated total cost of $60,391.75 and, WHEREAS, the actual work was completed at a total cost of $61,229.15 of which $55,394.53 has been previously paid to the contractor, leaving an amount due of $5,834.62; and, WHEREAS, the City staff has inspected the work and found it to be acceptable. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The Barna Road Reconstruction Project is hereby accepted, and the City Manager is authorized to make final payment to the contractor. PASSED AND APPROVED this the 18th day of April, 1995. M A Y O R ATTEST: v ' 0"CITY CLERK