Res 120-96 8/6/1996RESOLUTION NO. icz: 6-9C. RESOLUTION TO ACCEPT THE LANDFILL FINAL COVER CELL X AND WET CELL PROJECT AND AUTHORIZE FINAL PAYMENT TO JENNINGS CONSTRUCTION, INC. WHEREAS, the City of Wichita Falls entered a unit price contract with Jennings Construction, Inc . with the estimated total cost of $129, 542 . 10 and, WHEREAS, the actual work was completed at a total cost of 127, 081 . 23 of which $113 , 139 . 61 has been previously paid to the contractor, $1, 800 . 00 was charged to the contractor for repeat material testing and $9, 600 . 00 was deducted for appropriate liquidated damages, leaving an amount due of $2, 541 . 62 . NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The Landfill Final Cover Cell X and Wet Cell Project is hereby accepted, and the City Manager is authorized to make final payment to the contractor. PASSED AND APPROVED this the 6th day of August, 1996 . rte A Y O • ATTEST: i + r /l ; t ! k s C-E• ' -