Res 073-96 5/21/1996RESOLUTION NO. —13 _G (lJ RESOLUTION TO ACCEPT THE SPUDDER PARK RECREATIONAL COURT (CDBG) PROJECT AND AUTHORIZE FINAL PAYMENT TO M&F LITTEKEN COMPANY WHEREAS, the City of Wichita Falls entered a lump sum contract with M&F Litteken Company with the estimated total cost of $119, 120 . 00 ; and, WHEREAS, the actual work was completed at a total cost of 119, 120 . 00 of which $90, 867 . 15 has been previously paid to the contractor, leaving an amount due of $19, 252 . 85, after appropriate adjustments of $9, 000 . 00 in liquidated damages; and, WHEREAS, the City staff has inspected the work and found it to be acceptable. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The Spudder Park Recreational Court (CDBG) Project is hereby accepted, and the City Manager is authorized to make final payment to the contractor. PASSED AND APPROVED this the 21th day of May, 1996 . Ihkla r A Y ATTEST: L CITY CLERK