Loading...
Res 029-97 2/18/1997RESOLUTION NO. --! ~7 RESOLUTION TO ACCEPT THE LANDFILL LINER CELL 12 PROJECT AND AUTHORIZE FINAL PAYMENT TO BIG "D" LINING WHEREAS, the City of Wichita Falls entered a unit price contract with Big "D" Lining with the estimated total cost of $746,589; WHEREAS, the actual work was completed at a total cost of $756,883.90 of which $603,033.71 has been previously paid to the contractor; WHEREAS, ten (10) days of liquidated damages were accumulated which totals $2,400 leaving an amount due of $151,450.19; and, WHEREAS, the City staff has inspected the work and found it to be acceptable. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The Landfill Liner Cell 12 Project is hereby accepted, and the City Manager is authorized to make final payment to the contractor. PASSED AND APPROVED this the 18th day of February, 1997. MAYO ATTEST: 11(0 �"rl " T' ff CL R