Res 123-99 10/19/1999RESOLUTION NO.
RESOLUTION TO ACCEPT THE JASPER WATER TREATMENT PLANT
EXTERIOR PAINT PROJECT AND AUTHORIZE FINAL PAYMENT TO
JIM MARSHALL CONSTRUCTION; DETERMINING THAT THE
MEETING AT WHICH THIS RESOLUTION WAS PASSED WAS OPEN
TO THE PUBLIC AS REQUIRED BY LAW.
WHEREAS, the City of Wichita Falls entered a unit price contract with Jim
Marshall Construction with the estimated total cost of $75,669.50; and
WHEREAS, the actual work was completed at a total cost of $75,669.50 of which
$58,824.41 has been previously paid to the contractor, leaving an amount due of
$16,845.09; and
WHEREAS, the City staff has inspected the work and found it to be acceptable.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
SECTION 1. The Jasper Water Treatment Plant Exterior Paint Project is hereby
accepted, and the City Manager is authorized to make final payment to the contractor.
SECTION 2. It is hereby officially found and determined that the meeting at
which this resolution was passed was open to the public as required by law.
PASSED AND APPROVED this the 19th day of October 1999.
ATTEST:
C', , ( UA1,6,)
ity Clerk