Res 147-99 12/7/1999RESOLUTION NO. VA-1-1-Al-1
RESOLUTION TO ACCEPT THE LAKE WICHITA BOAT RAMP AND
PIER PROJECT (TPW) AND AUTHORIZE FINAL PAYMENT TO
SCALES CONCRETE; DETERMINING THAT THE MEETING AT WHICH
THIS RESOLUTION WAS PASSED WAS OPEN TO THE PUBLIC AS
REQUIRED BY LAW.
WHEREAS, the City of Wichita Falls entered a unit price contract with Scales
Concrete with the estimated total cost of $64,407.00; and
WHEREAS, a previously approved change order increased the estimated total
cost to $65,433.00; and
WHEREAS, the actual work was completed at a total cost of $65,980.20 of which
$64,660.60 has been previously paid to the contractor, leaving an amount due of
$1,319.60; and
WHEREAS, the City staff has inspected the work and found it to be acceptable.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
SECTION 1. The Lake Wichita Boat Ramp and Pier Project is hereby accepted,
and the City Manager is authorized to make final payment to the contractor.
SECTION 2. It is hereby officially found and determined that the meeting at
which this resolution was passed was open to the public as required by law.
PASSED AND APPROVED this the 7th day of December 1999.