Res 077-2013 7/16/2013RESOLUTION NO. 77 -2013 Resolution To Approve Change Order No. 8 For The Phase I Parking LoVEntry Road Project At Wichita Falls Municipal Airport, Which Will Increase The Amount Of The Contract By $131,353.94 WHEREAS, the City of Wichita Falls entered a contract with Anthony Inman Construction with an estimated total cost of $4,526,254.80; WHEREAS, the City of Wichita Falls entered into seven previous change order agreements with Anthony Inman Construction, reducing the total amount of the project by $230,866.64, due to various utility related work and scope reductions on Phase I; WHEREAS, Change Order No. 8 will add $131,353.94 to the contract for a revised cost of $4,426.742.10; WHEREAS, the FAA will pay for 90% of the cost of the change order or $118,218.55 and the City of Wichita Falls will pay for the remaining 10% or $13,135.39; and WHEREAS, the City staff has reviewed all aspects of this change order and feels that it is in the City's best interest to approve. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The attached Change Order No. 8 to the Phase I Entry Road /Parking Lot Project at Wichita Falls Municipal Airport (AIP No. 3 -48- 0346 -14) is hereby approved and the City Manager is authorized to execute said change order, with changes thereto in a form approved by the City Attorney, in an estimated amount of $131,353.94. PASSED AND APPROVED this the 16`" day of July, 2013. MAYOR ATTEST: Acting City Clerk GE'OE5ffi"NO =- 8 CITY OF WICHITA FALLS, TEXAS CHAI I- D CONTRACT CHANGE ORDER FORM DAj* 16- Jul -13 AMOUN1pOFCiANGE;�d: $ 131,353.94 PROJECT %CONT�ACTz; Phase I Terminal Area Project: Entry Road/Parking Lot TO: Anthony Inman Construction this Change Order, after approval by the Owner, will be your (Cwhictoo authority to make the following changes In the work under your contract: r_�� U WIN, . x'� Desaf oMw n;~ <yg: w nC9 n= Cflntfa .Qort Carry Over from Change Order #6 ": $ $ -: :4,272,542.72 . 7. Construction of temporary asphalt exit for new parking lot. $ 22,845.44 8. Parking gates, revenue collection for parking, installation of $ - $ 131,353.94 $ 131,353.94 parking equipment, canopies over the equipment, and additional electrical and communication wiring for equipment 9. $ - $ - $ - 10. $ - $ - $ - 11. $ - $ - $ - 12. $ - $ $ - TOTAL $ - $ 154,199.38 $ 4,403,896.66 4,526,254.80 1 94 ,5. IO�AL AIiAOUNT OF'PRENIOU8,CIIAI�IGE 0�20ERS �s c;. s;r... `.'r:�"„f"`�': "�.; x.:X x��,v��u r�c�, b��`•�. �";t�.� -�✓r� , .�.r,: $ 230.866.64 CONfitAHM0IJNT ° $ 4.426.742.10 The completion time under your oontrect will be extended by 0 days because of this change order making the revised completion date November 5.2013 . Approved By Owner: Accepted By Contractor: Recommended By ArchtEng: (if applicable) By: By By: Title: Title: Title: Date: Date: Date: CHANGE ORDER AIP NO: 3 -48- 0227 -013 DATE OF ISSUANCE: 07/02/13 CHANGE ORDER NO: 8 AIRPORT: Wichita Falls Municipal Airport PROJECT: New Terminal Project. Phase 1 SPONSOR: City of Wichita Falls ADDRESS: 4000 Armstrong Drive, Suite 8 Wichita Falls, TX 76305 CONTRACTOR: Anthony Inman Construction ADDRESS: 3000 Buchanan Wichita Falls. TX 76308 The following changes are hereby made to the Contract Documents: PCO -017 Install Pay Stations, Gates and Shelters Justification / Reason: To provide revenue control into Long Term Parkins; Attachments: (List documents supporting change): PCO -017 Page l of 4 CHANGE IN CONTRACT PRICE: Original Contract Price: $4,526,254.80 Previous Change Orders: ($230,866.64) Contract Price prior to this Change Order: $4,295,388.16 Net increase / (decrease) of this Change Order: $131,353.94 New Contract Price with all approved Change Orders: $4,426,742.10 Percent change from original contract: 3.61% CHANGE IN CONTRACT TIME: Original Contract Time: 365 calendar days Net change from previous Change Orders: 35 calendar days Contract Time prior to this Change Orders: 400 calendar days Net increase / decrease of this Change Orders: 0 calendar days Contract Time with all approved Change Orders: 400 calendar days CONDITIONS OF APPROVAL: Contractor agrees that execution of this Change Order settles any and all claims related to the items addressed herein. The aforementioned change, and work affected thereby, is subject to all contract stipulations and covenants. Page 2 of 4 ATTACHMENT A TO CHANGE ORDER NO.8 Indicate below any new pay items or revisions to original contract pay items resulting from this Change Order. CONTRACT QUANTITY AND PRICE CHANGES: Total: $131,353.94 Page 3 of 4 Contract Quantity Item No. Description Unit Unit Cost Change +, Price Change 111 Pay Station Gates LS $131,353.94 1 $131,353.94 Nextgen — Equipment $90,810.00 Scales — Concrete Bases and Labor $4,956.00 Occhsner - Electrical $10,695.62 AIC — Raceway/Bollard/PM $5,5000.00 Insumnee $1,764.74 Overhead — 5% $5,686.31 Profit— 100/0 $11,941.27 Total: $131,353.94 Page 3 of 4 Prepared by URS Corporation: Qr Name Accepted by Contractor: Signature Accepted by Sponsor: Signature Pr 4- 07/o ti Title Date Title Date City Manager Title Date Page 4 of 4