Res 140-2025 execute change order number two to the Construction Manager at Risk contract with Anthony Inman Construction, Inc. RESOLUTION NO. 140-2025
Resolution authorizing the City Manager to execute change order
number two to the Construction Manager at Risk contract with
Anthony Inman Construction, Inc. in the amount of $552,423.66
WHEREAS, in February of 2024, the Council awarded a Construction Manager at
Risk contract to Anthony Inman Construction for a guaranteed maximum price (GMP) of
$16.3 million for the building renovation of Memorial Auditorium; and,
WHEREAS, contingency funds have been used for some improvements to
Memorial Auditorium that were out of the original scope; and,
WHEREAS, the City has requested modifications to the original scope to
accommodate staff changes over the last 18 months; and,
WHEREAS, funds are available for this change order from the ARPA funds interest
and Venue Tax fund.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
The City Manager is authorized to execute change order number two, in a
form approved by the City Attorney, to the Construction Manager at Risk
contract with Anthony Inman Construction, Inc. in the amount of
$552,423.66.
PASSED AND APPROVED this the 4th day of November, 2025.
MAYOR
ATTEST:
11/(au, Baki-k
City Clerk r