Loading...
Res 072-2025 PSA with Garver, LLC for Falls Study 07/01/2025 Resolution No. 72-2025 Resolution authorizing the City Manager to execute a professional services agreement with Garver, LLC to perform an overall evaluation of the Falls in the amount of$129,508.00 WHEREAS, the City of Wichita Falls owns, operates, and maintains the City's iconic feature, "The Falls"; and, WHEREAS, it has been determined that a thorough evaluation of the overall structural, mechanical, electrical, and accessibility components of the Falls is needed; and, WHEREAS, it is found, through a qualification-based selection process, that Garver LLC is capable of completing this work. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The City Manager is authorized to execute a professional service agreement, in a form approved by the City Attorney, with Garver, LLC to perform an overall evaluation of the Falls in the amount of $129,508.00. PASSED AND APPROVED this the 1st day of July, 2025. MAYOR ATTEST: City Clerk Professional Services Agreement between the City of Wichita Falls and Carver, LLC for Consulting Services for the The Falls Evaluation 2025 OWNER: .1111. CiL i Wijijia Fa Rs: Alin! DLwkFr of Works,P.O.Box 1431,Wichita Falls,Texas 76307 CONSULTANT: Garver, PRO,IE CT: The Falls Evaluation 2025 TIMETABLE: Time is of material consideration for services pfffortned undin.this t t...)>,Si..LTANT shall complete the soope of work in accordance with the schedule outlined in Appendix A Siioci Sinvices. PAYMENT: 1. Payment for Bask Services.OWNER agrees to pay the follow ing amounts for Basic Services rendered pursuant to this oontract,a total amount of S129,501.00 subject to completion of the following phases of the PROJECT! WORK DESCRIPTION FEE AMOUNT FEE Tv-PE IDEk ' I'roject Manaderient m I DEk 2 Data H.equeEt. Field Assessment and Verifications $22.4 ▪ F.1 I DEk 3 Dralt AllernaliveE Evaluation Memorandum F.:11, ▪ m I ask 4 Conceptual Desin ▪ F.1 I ask 5 Fin.d Alternatives Evaluation Memorandum ▪ F.1 TOTAL FEE S'2 '11. 11 IL:0...11J :MI 2.111;!Iltill'!•''h.'.%:k. SIILII %:11.'.11111:.ILLL J:.!:Airrtimitatitm reasonably I. %%all iL .iiLItlLLitaiiit'!.' dr. I:LT:Jai:An 2,P17. ra file A it ill Well Str%ii . OWNER shall pa y CON SULTAN!'for Additiortat Savion rogoestod and ftmtineti. s: 2.7.7,2,.yrr.2ril.'.."ni ...!!..CONSI...-1..TANTR nal-AtiiiJi [Ilk t "Aui-..-anni- pliJ t;! 2:11d AdditL11111. .11.1tIWILZLd 11', an LILA Li this agreer Rent. 3.TiiINTS 3.1.Ti :.1!:.1"uy111:1111.s--CONSI:TLTANT.i112.11 ..;411!11111 11'•'111111'*•itittUrncrils fur 3usiumn.lAthlio..11..:1:.-,,r,L....iv:m{1:7a].FUT SLV•ILL‘:. I . ill i I : \ is dr. :.!:17111111.2. dILII HILL 11.111111'.,!11[16 ila?irti.T.rits LT1 rusr:INLt t 1..):\51. st.LLIE.LIIN. )!:.!ii (.:0A 1.;.! 1711 1!.11LI . tiIi IiL La Si 3..2. Past-Din -OW:\-..'")% .1.21•:.US tO ply a -:.11:.ive of 0.5% per Tmnali. :rn dr. all aJ interest accordingte rwt FLi..1 dr. invoice, I. ON 1.;\ LILL t Y. rli:1 iii nil LN.r.FISCS. OWNER'S REPRESENTATIVE: Russell Sehreibin,Dimetor :'ulr Ile V..:11.1,A,Cir, :AWL-calla Falk BASIC SERVICES: CONSULTANT shall complete the rtrurLssi:.!ilL1 NI_TviC,CS as 732.‘i... Strieci a ou'Llintql in Appendix A Scope of Sinviees according to the industry standard of tare!Ct:1:',.!.=.1.'7 'IA.VI' II 1.,i urrt an y and all servict...s r-L,i.luiredhin.ein thacrdane with generally aetepted praetiees and apiLitabk Lrii1td Stales Pate I I'I:.'..':ssl:.'II I s:l'•I::s IIIJtistiiLs s :...'tll: :.....:ll.. J t: ;..'this ;°..L. L II:.IIL. I'I .FI.IIIL. t111J.i sin:iI .1 ::.'11JIii:.'IIs�.II.1I:.':�I:. Stl:II L.:.irA sr:All:ids .1: II;'L ink IIJ:J L:' 1': 111rIL:J L;' L11: ;'I'lllrlllr I'I_'.:ll::s. II::LI1;'Js. L::11111.I tl:s. :.'I sI.LIIJ�.I Ji Lrt tllc :\:I tlsl:.' Ltl}Itis, Ina :rid pi uJ:11t Stale;pi.'..:ss i;'11r.1 s.rvit:es industry'. GENERA]. C'CI`4I]I']O S: I I1r'C171[L ILL''rt OWNER termin LW_ this ALI. II::n1LIpUT1 km L OIda4s 5LTiLL.rir1.ILi.L LUC ON51-LT ANT'.LItllthe t111J:Isi.uldi ll!'t11r.1 l.II s:l'•I::s1':I IIL' I'.I..;'IIr:J tlnJa t11Is;°5L'ILLiik111 III' 'll ilk. ..1..I._ i...I in <II:II II;ILioe. l.'I':.'11 t:I lriIIL.li:.'11.. '1 I t:? Sl.`:.'I';°5. '1"S II I:L.L J t t) `Sl.':.'I':'S.4 I'sI1.'.II I1.'.'...I.11: ::: ..LGk i upp.rI IlIIIII to cttre.In ilk :'•Lilt t S1. 1;°5 "I sh...11 III'•;.•I:: : :i .'.IIJ I . L•'ll'I'.Ils.'.I..1 •'I :I: LII '.1'•I-..; I•I IpLllti` Ia:l-;'I II.:J tIIIJ:I this;\.L'I:•II.:IIL. _'.nj 1:_'.s;'111l'l::;'sts ill:tll I:J 1'L't :? yfl. : 1''S.4 I .'n;'I 11L.;'I:L t)\s1..: LA.. I &It L}IC turrr:.i11.tLi:.'11 11;'Lice, iII:ILIJIIIL' Ill ttu Lsl.mrlt1LTIL' L1F:1 tIIII'Sid irr•..'i-.'+. . pun terrniTlatLL}TL for cum.•.111.1k.. COX Sr.LTA N C s llatl I allow b 4 p r:' i J.d till all ousts r.. ' I i LI I k. i I I Lr urrCLl Lu bring such sen iees to an ordt`ly oLs s.m Li.Frl. 2, 0-virtu-strip & Maintenance Uf DLUCEIE11tELl --ALL J;':t11r:11ts :.IIJ dL LtaL :II:s prt anJ .Ir atss:ll:hLed by t t:? Sl.`:.'I'.t ti C uTldur this •'.L'r::II: IIF slILll h::;'11_: I.11: I'1;'I':1Ik , rI1: C)ti.L'\:.':t L.ntl ',%I t11;'tIt I:itl IL LI:.•rI:.Irl TLtln. [Is:. I'I:.'.1:1:J 11;'',L:'.:I..Lll. LIIJ 11l tlll•.1.1I,I II"_'1111.11.Jll�.1 I'I;'I':I Lh'.i..'�.Ilk.. 11111:ss I:I;''•I J.J 1'k' sll_'.II I.II: ill 1.11:I'I;'I'.II.L':.'..t t.? S1. :.I;5 I sL1:11 lllaL I. {:I`4 l _ I •'4 I II:. L':;'lllllltl.L;'I':I..;'I II:ILs 1'Lt<ill:«ill I°wk11'.IIt III .ull. t DNS'.':.I ;°5 1slI[41.1IIt t)''•5' :':4 II III:'•:.': 1'1:.II;'ll-:h:111 k1',..I ",.'.1tk-..'I:: tills;'SL'I:.II.III.. I :.'tll: .\F.IIt.II:.''.L:J t111J:1 t 1L.Y : :i slILll J:..':IIJ. i!R:ll:Ili_'k' „.HJ 11;'1;111m111:1:ss .:1 ;°5, 1 .liJ Its itll'...unitlltrAus iLs._'.11J LNTLIKL,..III:1uJlII!'I:....: 1_7.1'1:l.I.L;'III:L's ..::s 111'41IIL':.'LIL;'.. L112.II.2. I.;'.:.'1 I:-tls: :.'_'J:11'•.I.'.I'1.� - Ilk' ;'t11:1 I'1:.'.::I..t)''•5 :.':l s I:-tls: ;'_J;':tlll::lll.s:.'ll:tam:I'I:.'.::Ls '.L II 11':Lt 111: s:.'I I I ilk ;.'.. :?''5 :.':C.L t:?.4`.l, _ 1..•5.4.1. L:rpi:s:.'..' Ilk' LIIJ sLL I :;'nL1ir1:tl L11:1:I11. t :? ..1. I':1'4 I' LLI II ttIaiilll.:.ill I'I..r:::L ILL'Al Js..';:1 three,ti':..Is_'._lLI t}I ..1u:.1I'.'.yir_Luttotheetuu LLL.1 :.IIJ 2.11 :.'tll.l maw,' LuL :I;'<:J Ind pr....idcuupi:s Liu°reoiluO 'fir:r if r4 1Li terl. 3.Conir'oIL'ErtL" ].nr+. -This A I:.ntettisperfitrrrlall: _mil Istobt_';.ticnccs.II''. rII: Irr,L r_ppli:LI'I: iiI ''. i:llil : II.s.Tcxas. SL Le 4'4r141: :.'I .LII .. LI.IrI irrislll!' under this AJT4tILLL11t shall be Lit 'i:IliL I. 1.AssignmeniofC'.ontraci--t t:?\S1. 1 "I s11al[T1uE'LssiLll,subL4l;'1 tl_11Ii.'.I 2.11L'II.2llk1,111 .tirr.unteresliTll.iTl:luJi1IL'. but w Lt Il;'tl t l i l l:.i l_'.Li:.'I I'. I I.Ill:s[Ira a 11:;'Ill:s tl l.1l 2.1: :JUL: t111 s,,t!'I::'rr: "rlE wll}Ittut t}Iu 54TLLLL I I th. .'iI1'.1. l Ill:ss sI'::i..i: II sl l:J t;' t11: :;'lltl l . Ill Lll '•L I ILt.11 :;'lls.11t t;'L11 LssiL'IIIr.r11..r1.e as;wrlrrl nt•.L ill I:I: IisaltlL'. tll: 1ssIL'll;'I ..I:.'ll: Ilk' Jtll.k ;'I I:sIG'IIsiI'ililt' unJ:1 tills;°5L'I:.IIIIF. ;'FlIIIIL' :;'III.LIII.J in this i Li. '1.4.11 sl11L1 prereerlLt t:? ..1.':.'I';°5 "I'..'1;'11_LiI:I'I;'ti•'In :1I:I'I:.'L.-:.s LotassLLL it in the,per i;'I Il:cud:il' servii.r.s Ire.wu ldtr. 5.Na Tlr.ird-Part. Iitneliciaries--Nothing htn.ein shall be Oansirued to ui.: Ir* 11 L'Ills or bin.]:_i Ls t;' 1Ik;Inc otht.1 than OWNER anti CONSCITANT. b. Indt pen1L•rLl Contractor--In pertc'111:IIIL' s:l'.i t111J:1 Lids Agreement t-C)Nsr.-:.TAN I.I.k'thL',AL:t1I.I:.'11:._'t11is;°5L'ILLnkl1t ;l1.'11"_'. ill: in::I':nJ:llt :;'lltl :t;'I sl. LLIs ;..'t t: Sl.':.'I';°5 'I'. :.' [Lin: l L t: , .'S III L11:I':I.:1111:_II:::l.L11 is;5!I..ball s11..111': V.'IIsLI LI.J ms 11: lwlll!'L t1 .:.`1;°5 `1 ;'I mllk,__:IIL.s:I.m111 .'1 „JrI'1 "+... _'t 0 Sl.'L.TANT the argent, : Irrtlr lrr nits--t t?�'•�'+I ':..TAT'T vL'I..s ttl isle aL_;c'.iT1dL1 I:I I I..k'.and}RI Li.I 1.11 l:l'`.. . :. '.'.11.'I.. II:I IIJ.11111:ss.:.21IristaT1% arld alit thin]I'.I I', 1.11 .I.i1r s. LYi Ls...11,1 ..41I `Ilk 'I II .1.III •.` I' ',111 III'III .`1 I..I I!'11'1 I'I 'I'.I L4'J II'.SL't FL.sul LT16'CI-tFTHL the tteuliL:.Ill I',.1 'l ll'.'.II..,.•'1 11:.2lI2.III .'"u,.11 I'I,.,11'.I •'l ll'.'.II.... .` 'llli�I. •'lll l.'.:.I. Hu,illa.Irinr, s11.'.1111•'I. I'I'15'L.1 any 1:Iarim to tklt LIE:IILiFL' I'l11su1IIL to C a.Loi.i$l{.iov't Cod, _ 8, Cu%LrnnlLrLC 1F FIlnt`tillrt Cr An panics aur that al is Contract is 4.4T1t wh4r4ir1 C)\i, -R is suleiy performing a gtl :I IIII .III..I 'IIII.Fi.Fn. .\ll [Ail..., . .I'I.ksl', .L'1.. IIL I C'`'.`'• Ls rut: 1p.. 'IIIL' in LIIk If1.,rpli.FLI' .'tIII.FI;lrli. 9.Contractual Damages Limitation Clause Page 2 9.1 All FLILL.sLLI tII.LLN. S LI I L S thILS Cindraet are lint ited by agrement(litho parties,and to t h tLIJLLL ..LILiIorLed unthr Texas Loc,a1 Cloven-1111ml Code Section 271.153. 9.2 Tfl 7'AR-1-')' SI LALLL BE LIABLE TO TEIE OTITF.R :',A.RTY FOR r7A:. :f.XEMPLARY DAMAGES OF ANY SS I."S:f c r70:\ NEC.iL IC-FENCE OF ANY KIND OR CiEARACT:::z. IN L. . Y Ti) co .• is. rs. >,.)0:Z.S: TOT A:. ;V_ OF L ALS:: VION NE(.-FLIL-FENCE OF KIND OR C:LARACTE.11. (-FROSS NEL-FLICiENIC'E).. 9.4 C Sr.:LTANTshallbt 43nlitied L...! .1[1 6quiL.I. !IL is to the&LI'vit:es rt;s Litt ing cvmLi 1 '. .1 ,:': sLLlANrs control. 10.WailderolAiliirrul.'s ues Lion aLl.w or i ILI ILLS ::.ss LrRI Yifl 11:.,4 i Lk k S'.`-..TA:\I k 2" . that ill:. iii .:.11 .1;.1Sir.li...1Li:Ai t .111;.1 OW>. earn Ld Li. 2.1 I LLItiF.i .uid other rm.:m.11a I ' iii 271.; arid all other law. 11. F.\IiiI7iLs The llow Ediihi1s are attached to and made a part of this Agreetntmi. 1 - '..1.1c at s t Agreurrient,adolow Ledges that .ISSLIILJ LIFLII:SLI'.LS LI ILI 111:s that all Exhibits, and agrees that this 1,...g.H.,4_411-u.rii and 17.117.1[11111.1 L-LL 11w 1.1.MILLS pr.1.1%.,is ions,andutlitrr ti:ii: riis tiaiut.LLTILLISS SIIL L_L[1.•.: LLIILLIILL ALl truil is 't-,ateti by an authorized atatt oithe GINNER signing itt tha spaee provided 12, Vuelli.uNtilin. Pate 3 T. : utli;i ir..l ;+..'_i.iall Randall(i.McIntyre do ht'eby depose anti verity the lrutht'ulrress and accuracy ut't}ie ira ill; ;!..'tk sl. l..ii_.iits suhrnilttxl trrr this kcal:tort under the provisions of Subtitle F,Title 10,C.iuternrru nl(7t111e I. II Lill I 227:: n:l tli t rli: .urrtpany named below: 1) Dots nut Ir..% I.l :i .l.urrtrrllk. .' 2) Will not buk:;+tt i :l durirr} lhi Lill .' 'ilk.contract: and Is not currerrtlk Ikt.J ;n the State ; I'. .LLs ('uii l'ii.,11.7's Coraparies that Boycott Israel List located at littr,::" ;+icr'ti;+Ila.i. .. .._. . i•'n.li._:iii" I'iil•li..ii: ii: .lr...III .iii_r li r Garver,LLC Company Name .t.— ,�kr 91tiY.+�'rik':L5n1a11G YASncyw yy I"71,4, n itinuill� $WPdfu Y4 C8fi S I!'ll.1ttll. ;+..';luil1•11,, ,l C� 'i:i�.l Vitae Pr. .J rIl 6.: ..2025 Title utAulhari. I T}i is A}trta!rntirt and ',.id at tachrn{rrts nFaty only be arneniled,supplemtwrrltxl,mtwlitredtrr carrce.ltxl by a duly executed written irrstrunrtirl. EXECC:T[ D,t}iis the tlay ut ,20— OWNER: City.01Wiklrila Falls,Texas CONSULTANT: Carxer,Il_C OabY4 srt�cc C4�aic.11 oR4' aye I 6k6r°s2{t 12 k4242-CC{' Jefery.Jenkins, City Merger Randall G. McIntyre, PE,Vice President {seal) I.seal I ATTEST: ATTEST Marie B,althrop,City Clerk FORM APPROVED: lCinley liegglund,City Attorney Page 4 Attachment 1 (SCOPE OF SERVICES) GENERAL Garver will study existing conditions and provide recommended improvements to the existing Wichita Falls trail and waterfall,located south of Interstate 44, near Broad Street on the south bank of the Wichita River. The study will address the condition of the existing waterfalls infrastructure,clarity of water used in the falls,access/connectivity to the falls. and other user-facing upgrades to make the site more inviting to visitors and accessible for maintenance. 1. Task 1-Project Management and Administration 1.1. Project Kick oil r.1eeting flan and participate in a hybrid project kick off meeting with City of Wichita Falls staff to conlirri project goals. scope, introduce team, define lines of communication. and discuss project schedule.Carver's project manager will attend in person with additional Carver Ieam members attending 'virtually. Carver will prepare a meeting agenda in a presentation lorrlal. lake notes. and create meeting notes. 12. Project Schedule -- generate a project schedule including City review time. 1.3. Project Management and QA•'QC Plan--- Develop a simple Project Management plan(PMP), Quality Control Plan, and project schedule. 2. Task 2-Data Request, Field Assessments and Verifications 2.1. Data Collection arid ke:ic,•: the City of Wichita Falls will provide the following data and information, if available. I he inlorriatiori will be reviewed and incorporated into the overall study project. + As-built plans Iorwater !all improvements including available information about existing pump mechanical systemic. IF4 ecoi,.,od + Any previous master plans. studies or reports. • Maintenance and inspection reports for the existing waterfalls pump system. • Any CAUL)or CIS liles available.for exlsLing utilities. • Additional site Llilily and Facilities archival information as requested • Existing survey Irilorrlalion. Z.Z. Site Visits Conduct one site:visit during this phase to inspect the site and review the proposed project requirements. City o1 '.Wichita Falls personnel. arid permitting errtibe.; a,`; necessary. I he site visit will include process.riechanical engineer. electricat'instrumontatiorrcontrols engineer.structural engineer.site civil elir,lllieer.°irid landscape architect.The city will dcvator the waterfalls prior to site visit to allot,'_access Ior_assessment of the waterfalls and rockwork. 3.. Task 3-DrattAltematives Evaluation Memorandum 3.1. Review of Existing Conditions--Garver w ill describe t he condition and criticality of the existing facilities identified during the site isit and review effectiveness of current facilities in a technical memorandum (T'A+I.. 3.2. Establish design parameters establish design flow requirements for waterfalls, load ratings for in alriteriance vehicles that might need access to pump equipment,percent blend of potable water. recirculating water.and'or groundwater to improve water clarity, high water level of the 1 Version 1 Wichita Falls.Trail& ':Valerlall Upgrade Study Garver Project No.2 500 542 Wichita River to aid in addressing intake location for recirculated water and the elevation of possible replacement trail bridges,desired parking location(s)and quantity,standards for new site furnishings and lighting, and design direction for rebuilt waterfalls rockwark. High water level will be based on available flood insurance study(FIS)elevations (10-year,50-year, and 100-year elevations). 3.3. Pump System Evaluation-Assess existing water pump system and make recommendations for a new replacement pump system, including possibility of higher flaw pump and replacement of water intake. Garver will also review the location of pump equipment and accessibility needs by City maintenance staff. 3.4. Electrical, Instrumentation and Controls Assessment Garver will assess the condition and capacity of existing electrical, instrumentation,.and controls systems. Garver will recommend upgrades. and/or replacement based on age, availability of replacement'repair parts, and condition. 3.5. Structural Assessment (W terfalls' Carer will re:icw the condition of existing concrete foundation located under rock work. including visible signs of degradation or failure. The assessment will also include recommendations for structural repairs or replacement as necessary. 3.6. Water Clarity Improvement Evaluation ASSOSErleiliWlii consider options to address turbidity in river water and hail.,the conddron degrades a.aterl_all_aesthetics after storm events. Based on design criteria identified in task 32,Garver,.ill evaluate costs of the following water quality improvement alternatives: 3.6.1.Recirculation al lower turbidity river water pulled from pool at higher elevation. 3.6.2.Blending pubble water dh ri:era._ater. 3.6.3.Blending groundwater with river water. 3.7. Maintenance .Access Assessment (Trail Bridge) - Garver will assess four alternatives for maintenance=acce:;`;. i.'.Carver will _access the condition of the trail bridge and abutments at the waterfalls, including 3 review of load rating information and the bridge's.ability to serve as.an access point I°r maintenance of pump equipment. 3.7.2.Acccss to cite oa.ned property i a.a new bridge from the north bank of the river_ (.3.?'access via crane equipment from Riverside Cemetery Property. r'.4.Access via trail widening from public works sanitation yard to the waterfalls. 3.8. Parking and Trail Enhancements Carver will consider talc locations for additional visitor parking near the waterfalls. Locations will locus on city owned lard.including those properties on the north bank of the river and city owned Land east ol the Riverside Cemetery Property. The assessment will also include options for potential enhancements oh trail connections to new parking,a new river crossing,and other changes necessary to making the fall area more accessible to visitors_ 3.9. Site Lighting Enhancements-Garver will review existing lighting on the waterfalls andexisting trail lighting. Review will include recommendations for security and aesthetic lighting enhancements to the refurbished waterfalls and along the trail tolfrom waterfalls parking. 2 Version I Wichita Falls Trail&Waterfall Upgrade Study Garver Project Na.,2500542 (WRIER 3.10.Waterfall and Area trihancements Carver 's.ill review' the condition and layout of the waterfall, including How rates. layout of walerlall pools and drops. and rock work and make recommendations for potential enhancements to the,:atcrlall experience I or:'IS rtors. Uar:'ar will also review existing site design and aCCece and make recommendations for potential enhancements to site lurnishinas. plantings.irrigation. and signage. 3.11.Technic.al Evaluation of Alternatives Carver will provide conceptual alternatives for access. water pumping,and site design improvements.provide conceptual design opinion al probable construction cost(AACE Clas :'.,:tti anticipated to i'viva" accuracy range of expected construction cost, and assess their technical Ieasibility. Carver will recommend up to two(2) alternatives of each.Garver will assess pump options and make recommendations. 3.12.Draft Alternatives Evaluation Memorandum—Garver will document the findings from all items in this task in a Draft Alternatives Evaluation Memorandum_The Memorandum will include: 3.12.1_ Class 5 opinion of probable construction cost(OPCC)for evaluated alternatives.. 3.12.2. Site condition summary 3.12.3. Design parameters. 3.12.4_ Draft alternatives evaluation including DPCC of each will include: 3.12.4.1.Rehabilitation of existing waterfalls with no additional improvements.This"base" alternative will include recommended electricaltinstrumentatiorucontrols rehabilitation,and structural rehabilitation. 3.12.4.2.Three water clarity improvement alternatives (recirculation from higher pool, blending potable water,blending groundwater). 3.12.4.3.Four alternatives for maintenance access as outlined in task 3.7. 3.12.4.4.Two parking and trail enhancement alternatives as outlined in task 3.8. 3.12.4.5.Site lighting enhancements. 3.12.4.6.Waterfall and area enhancements such as site furnishings, plantings,irrigation,. and signage. 3.13_ Draft Alternatives Evaluation Memorandum Workshop — Garver will conduct an in-person workshop with City of Wichita Falls staff to review the findings,,receive comments from city staff,and identify the preferred alternative. 3.14_ Selected Alternative—Garver will prepare up to three(3)color site plans, perspectives, and other graphics to convey design intent of the selected alternative_ 4. Task 4•Conceptual Design 4.1. Conceptual Design Based on the preferred alternatives identified during task 3.13— Draft Alternatives Evaluation '.Vorkstaop. Carer will provide a conceptual design of the preferred alternative for site. v,alerlall. and water pump improvements at the waterfalls site. The conceptual design documents will become an appendix to the Alternatives Evaluation F.1em orandum.conceptual design will include: 4.1.1.Conceplu_al Ul'UC: (AACE Class 4) with anticipated -30%to +SO% accuracy range of expected construction cost. 4.12.Conceplu_al drawings (up to five drawings) to include site layout and site plans. conceptual design will include: 4.1.2.".Pump systom recommendations including preferred water clarity improvement alternative.. 4.1.22.Maintenance access improvement 4.12.3.Parking and trail enhancement 3 Version 1 Wichita Falls.Trail&Waterfall Upgrade Study Garver Project No.2500542 GARV ER 4.`.2.4.Site li:il liiigenhancements .".2... ';'alorIall and site enhancements 4."• .. clo_i:iii and construction schedule to include time for internal OAIQC and cost estirialin ii services to bo completed for transmittal with other deliverables. Project schedule ,:ill include .tales for transmittal of design review comment responses at the mid-point between receipt of design revive,'comments and next design deliverable. 4.".4.r:onceptual ':.rkshop Jar:orwill conduct an in-person workshop with City of ficFii1a halls stall to review the conceptual design and receive comments from city staff. 5. Task 5-Final Alternatives Evaluation Memorandum Upon completion e1 I a_k:4. ,:2ar-or,:ill incorporate comments from the alternatives workshop and the conceptual design workshop in a Final Alternatives Evaluation Memorandum. DELIVERABLES I.11 each submittal Carver'will submit electronic files in PDF file format. Garver will also submit at each submittal hard copies.,,five(5) copies of the final Alternatives Evaluation Memorandum and supporting plans,and OPCC.Hard copies will be bound_ EXTRA WORK The following items are not included under this agreement but will be considered as extra work: W for quality testing. 2. Pilot testing of equipment. 3. Detailed design ar development of construction documents. 4. Bidding phase:services. 5., Construction please services. 6. Boundary. property, or topographic surveysr or preparation and acquisition of easement documents. 7. Submittals or deliverables in addition to those listed herein. 8. Site visits or workshops in addition to those listed herein. 9., Redesign and'or additional evaluation Ior the Owner's convenience or due to changed conditions after previous alternate direction and,or approval. 1U. Preparation of a Storm';'dater Pollution Prevention Plan(SWPPP). 11. Environmental permitting and?or regulatory acquisitions. 12. Environrnenbl handling and Documentation. including wetlands identification or mitigation plans or other work related to en:'Iranrientally or historic_411y(culturally)sign'rficant items. 13. Cultural site review and I exas historical CammisEion review or study. 14. Coordination with I-EMA and preparation/submittal of a CLOMR and/or LOMR. 15., Geotechnical Investigation. Extra Work will be as directed by the Cityof Wichita Falls in writing for an additional fee as agreed upon by the City of Wichita Falls and Garver_ SCHEDULE Garver shall begin work under this Agreement within ten(10)days of a Notice to Proceed and shall endeavor to complete the work in accordance with the estimated schedule below: 4 Version 1 Wichita Falls Trail&Waterfall Upgrade Study Garver Project No..2500542 GARVER Task Description Estimated Calendar Days Task 1 -Project Kickoff Meeting r'd_3vs Iron receipt of =11._1 Task Site Visit '4 days from kickon meeting Dnd per city schedule to drain vv_3tcrlaIIs Task 3-Draft Alternatives.Evaluation 60 days from establishment of design Me ma rand um parameters Task 3-Draft Alternatives.Evaluation 14 days from deliver of Draft Alternatives Workshop Evaluation Memorandum Task 3-Graphics of Selected Alternative 30 days from approval of selected alternative Task 4 Conceptual Design 60 days fram approval of selected alternative Task 4-Conceptual Design Workshop 14 days from deliver of conceptual design Task 5-Final Alternatives Evaluation 30 days from receipt of comments Memorandum 5 Version 1 Wichita Falls Trail&Waterfall Upgrade Study Garver Project No.2500542