Res 065-2025 Change Order for Memorial Aud. Contract with Anthony Inman Construction 06/17/2025 Resolution No. 65-2025
Resolution authorizing the City Manager to execute a change order to
the Construction Manager at Risk contract with Anthony Inman
Construction, Inc. in the amount of$388,654
WHEREAS, in February of 2024, the Council awarded a Construction Manager at
Risk contract to Anthony Inman Construction for a guaranteed maximum price (GMP) of
$16.3 million for the building renovation of Memorial Auditorium; and
WHEREAS, contingency funds have been used for some improvements to
Memorial Auditorium that were out of the original scope; and
WHEREAS, these additions are sensible due to their convenience factor, and they
must be completed for the proposed Performance Hall remodel; and
WHEREAS, funds are available for this change order from the ARPA funds interest
and Venue Tax fund.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
The City Manager is authorized to execute a change order, in a form
approved by the City Attorney, to the Construction Manager at Risk contract
with Anthony Inman Construction, Inc. in the amount of $388,654.
PASSED AND APPROVED this the 17th day of June, 2025.
MAYOR
ATTEST:
City Clerk
# ANTHONY INMAN
r 1. coNSTRUCTION, INC.
May 1,2025
Mr.Steve Wood,AIA
BYSP Architects
1005 Ninth Street,Suite 200
Wichita Falls,TX 76301
Re: Memorial Auditorium Building Renovations
Subj: Construction Cost—Proposed Change Order to the Project
Mr.Wood,
We present the following items for review and possible approval for Change Order 001 to the project
cost.
1. PC0_008 Hydronic Piping Revisions to the Project $ 78,580
2_ PC0_010 Replace underfloor DWV on the First Floor $ 47,384
3_ PC0_015R1 Add Fire Alarm Devices to the Auditorium $ 20,000
4_ PC0_022 Stage Lighting Electrical Revisions $ 19,278
5_ PC0_024 Upsize the Fire Pump for future Auditorium Fire Sprinklers $ 22,225
6_ PC0_026R1 Replace slab on 2nd floor west area $ 23,925
7_ PC0_027 Sheetrock lid on 4th floor Return Air plenum $ 25,522
8_ PC0_040 Move and Replace ONCOR Transformer and Feed $ 79,080
9_ PC0_047 Overhead Structural Support for Single Gla2ed High Wall $ 49,270
Subtotal Construction Cost for Change Order 001 $365,264
Builders Risk Insurance to the Project IP 1% $ 3,653
PURE/Insurance to the Project IP_85% $ 3,105
Construction Manager Fee @ 3.5% $ 12,784
Total Cost with Insurance and CM Fee $384,806
Payment and Performance Bond Cost $ 3,848
Total Proposed Cost for Change Order 001 $388,654
Do not hesitate to reach out to our team for additional information or questions about the PCO's listed
above.
Respectfully submitted,
Anthony Inman Construction