Res 078-2023 Change Order & Final 2021 Taft Blvd Street Improvement 07/18/2023 Resolution No. 78-2023 Resolution authorizing the City Manager to Approve Change Order No. 1 and Final for the 2021 Taft Blvd Street Improvement Project for a deduct in the amount of$371,747.26 WHEREAS, the City of Wichita Falls entered a unit price contract with Scales Construction Co., Inc. with the estimated total cost of $5,566,124.00; and WHEREAS, Change Order No. 1 and Final will decrease the contract by $371 ,747.26 for a revised cost of$5,194,376.74; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The City Manager is authorized to execute Change Order No. 1 and Final for the 2021 Taft Blvd Street Improvement Project for a deduct in the amount of $371 ,747.26. PASSED AND APPROVED this the 18th day of July 2023. MAYOR ATTEST: City Clerk CITY OF WICHITA FALLS,TEXAS CHANGE ORDER NO.:;s: 1 &FINAL CONTRACT CHANGE ORDER FORM DATE: 6/12/2023 AMOUNT OF CHANGE _ $ (371,747.26) PROJECT/CONTRACT: 2021 Taft Blvd Street Improvement Project,CWF19-100-11 TO: Scales Construction Co.,this Change Order,after approval by the Owner,will be your (Contractor) authority to make the following changes in the work under your contract: Becrease • rl nc s�ti"ti ''Av t:a161Wkielie Description of Changes , , in Contract , „ tin Contract'. in Contract.,o This change order will modify plan quantities to final in-place quantities. Item 5,Remove 8 Dispose of Pavements $ 420.A5 $ - $ (420.45) Decreased 28.03 SY at$15.00 per SY for a final total of 13139.97 SY Item 6,Remove&Replace Street Signs $ 12,000.00 $ - $ (12,000.00) Decreased 15 EA at$800.00 per EA for a final total of 13 EA Item 7,Remove&Dispose of Pipe Bollards $ 35.00 $ - $ (35.00) Decreased 1 EA at$35.00 per EA for a final total of 9 EA. Item 11,Remove Mailboxes&Replace with Standard USPS Mailboxes $ 800.00 $ - $ (800.00) Decreased 1 EA at$800.00 per EA for a final total of 7 EA. Item 12,Remove&Dispose of Concrete Curb&Gutter $ - $ 465.00 $ 465.00 Increased 155 LF at$3.00 per LF for a final total of 905'LE. Item 13,Remove&Dispose of Concrete Curb&Gutter Along Drainageway $ - $ 1,035.00 $ 1,035.00 Increased 69 LF at$15.00 per LF for a final total of 104 LF. Item 14,Remove&Dispose of Concrete Sidewalks $ - $ 1,849.50 $ 1,849.50 Increased 123.30 SY at$15.00 per SY fora final total of 316.30 SY. Item 15,Remove&Dispose of Concrete Driveways $ - $ 4,746.60 $ 4,746.60 Increased 316.44 SY at$15.00 per SY for a final total of 2337.44 SY. Item 16,Remove&Dispose of Concrete Rip Rap $ - $ 829.60 $ 829.60 Increased 48,80 SY at$17.00 per SY for a final total of 155.80 SY. Item 17,Remove and Dispose of Existing Concrete Drainage Flume $ 51.00 $ - $ (51.00) Decreased 3 SY at$17.00 per SY for a final total of 0 SY. Item 19,Remove&Dispose of 12"Reinforced Concrete Storm Pipe $ 525.00 $ - $ (525.00) Decreased 25 LF at$21.00 per LF for a final total of 75 LF. Item 20,Remove&Dispose of 15"Reinforced Concrete Storm Pipe $ - $ 3.719.10 $ 3,719,10 Increased 161.70 LF at$23.00 per LF for a final total of 208.70 LF. Item 22,Remove&Dispose of 30"Reinforced Concrete Storm Pipe $ 344.00 $ - $ (344,00) Decreased 8 LF at$43.00 per LF for a final total of 114 LF. Item 26,Remove&Dispose of 24"Corrugated Metal Storm Pipe $ - $ 368.00 $ 368.00 Increased 16 LF at$23.00 per LF for a final total of 81 LF. Item 28,Remove&Dispose of 6"PVC Drainage Pipe $ 21.00 $ - $ (21.00) Decreased 1 LF at$21.00 per LF for a final total of 4 LF. Item 30,Remove&Dispose of 15"HOPE Drainage Pipe $ 26.00 $ - $ (26.00) Decreased 1 LF at$26.00 per LF for a final total of 4 LF. Item 31,Remove&Dispose of 3'X 1'Reinforced Concrete Box Culvert $ - $ 632.04 $ 632.04 Increased 13.74 LF at$46.00 per LF for a final total of 73.74 LF. — Item 35,Remove&Dispose of Metal Beam Guardrail $ 3,750.00 $ - $ (3,750.00) Decreased 250 LF at$15.00 per LF for a final total of 500 LF Item 36,Remove Existing 6"Water Line $ 6,474.00 $ - $ (6,474.00) Decreased 166 LF at$39.00 per IF for a final total of 18 LE. Item 37,Remove Existing 2"Water Line $ 8,510.00 $ - $ (8,510.00) Decreased 230 LF at$37.00.per LF for a final total of 0 LF. — Item 46,Installation of 6"Pressure Class 150 C-900 PVC DR 18 Water Pipe $ 8,600.00 $ - $ (8,600.00) Decreased 172 LF at$50.00 per LF fora final total of 801 LF. Item 47.Installation of 8"Pressure Class 150 C-900 PVC DR 18 Water Pipe $ 248.08 $ - $ (248,08) Decreased 4.43 LF'at$56.00 per LF for a final total of 1171.57 LF. Item 49,Installation of 6"Gate Valve&Box $ 2,100.00 $ - $ (2,100.00) Decreased 2 EA at$1050.00 per EA far a final total of 4 EA. Item 50,Installation of 8"Gate Valve&Box $ 2,800.00 $ - $ (2,800.00) Decreased 2 EA at$1400,00 per EA for a final total of 4 EA. Item 51,Relocate Water Meters $ 7,200.00 $ - $ (7,200.00) Decreased 9 EA at$800 per EA for a final total of 6 EA. Item 52,Relocate Water Valves&Boxes $ 300.00 $ - $ (300.00) Decreased 1 EA at$300 per EA for a final total of B EA. Item 54,Adjust Sanitary Sewer Cleanout Height $ 700.00 $ - $ (700.00) Decreased 1 EA at$700.00 per EA for a final total of 0 EA. Item 56,Adjust Sanitary Sewer Manhole Height $ 3,780.00 $ - $ (3,780.00) Decreased 12 EA at$315.00 per EA for a final total of 11 EA. _ Item 58,5'X 2'Precast Reinforced Concrete Box Culvert $ 11,550.00 $ - $ (11,550.00) Decreased 22 LF at$525.00 per LF for a final total of 82 IF. Item 66,18"Reinforced Concrete Pipe Class Ill $ 21,483.00 $ - $ (21,483,00) Decreased 93 LF at$231.00 per LF for a final total of 1059 LF. Item 71,24"Reinforced Concrete Pipe Class III $ - $ 20,411.34 $ 20,411,34 Increased 93.63 LF at$218.00 per LF for a final total of 424.83 LF. Item 72,Remove&Replace Street Signs $ 822.00 $ - $ (622.00) Decreased 2 LF at$31 T.00 per LF for a final total of 40 LF item 74,Concrete Safety End Treatments with Wingwalls for 42"Reinforced $ - $ 29,100.00 $ 29.100.00 Concrete Pipe Class III Increased 3 EA at$9,700.00 per EA for a final total of 4 EA. Item 82,6"Monolithic Curb&Gutter $ 78,058.00 $ - $ (78,058.00) Decreased 2518 LF at$31.00 per LF for a final total of 9868 LF. Item 83,8"Thick Lime Stabilized Subgrade $ 84,159.00 $ - $ (84,159.00) Decreased 3117 SY at$27.00 per SY for a final total of 22949 SY. Item 84,8"Concrete Pavement $ 223,618.71 $ - $ (223,618.71) Decreased 3063.27 SY at$73.00 per SY for a final total of 21196.73 SY, Item 85,6"Concrete Commercial Drive Approaches $ 52.80 $ - $ (52,80) Decreased 0.8 SY at$66.00 per SY for a final total of 147.20 SY. Item 66, 6"Concrete Alley Drive Approaches $ 5,742.00 $ - $ (5,742.00) Decreased 87 SY at$68.00 per SY for a final total of 229.00 SY. Item 87,8"Concrete Residential Drive Approaches $ - $ 8,842.60 $ 8,842.60 increased 136.04 SY at$65.00 per SY fora final total of 1248.04 EA. Item 88,4"Thick by 6'Wide Concrete Sidewalk $ 19,159.25 $ - $ (19,159.25) Decreased 348.35 SY at$55.00 per SY for a final total of 3056.65 SY. Item 89,New Concrete Retaining Wall Less Than 4'-0" $ 12,975.00 $ - $ (12,975.00) Decreased 25 LF at$519.00 per LF for a final total of 0 LF. Item 90,New Concrete Retaining Wall 4'-0"Tall or Greater $ 17,920.00 $ - $ (17,920.00) Decreased 35 LF at$512.00 per LF for a final total of 0 LF. Item 91,10'Concrete Channel $ - $ 2,249.00 $ 2,249.00 Increased 17.30 SY at$130.00 per SY for a final total of 518.30 SY. Item 92,Construct 6"Tall Curb Along Offslte Drainage Channel $ - $ 18,328.75 $ 18,328.75 Increased 591.25 LF at$31.00 per LF for a final total of 781.25 LF. • Item 93,Construct Curb-Transition Height from 6"to 2'-0"Offsite $ - $ 10,660.00 $ 10,560.00 Drainage Channel Increased 120 LF at$88.00 per LF for a final total of 220 LF. Item 94,Transition Height From 2'-0"Curb to 3'-0"Wall Offsite Drainage Channel $ - $ 2,205.00 $ 2,205.00 Increased 15 LF at$147.00 per LF for a final total of 65 IF. Item 95,Construct 3'-0"Tat Wall Along Offslte Drainage Channel $ - $ 2,761.86 $ 2,761.86 Increased 11.46 IF at$241.00 per LF for a final total of 36.46 LF. _ Item 96,Transition Height From 3'-0"to 5'-0"Wall Offsite Drainage Channel $ - $ 3,214.53 $ 3,214.53 Increased 17.19 LF at$187.00 per LF for a final total of 67.19 LF Item 97,Construct 5'-0"Tall Wall Along Offsite Drainage Channel $ - $ 3,323.40 $ 3,323.40 Increased 19.10 LF at$174.00 per LF for a final total of 119.10 LF. Item 98,Construct 18"Tall Curb Along Offsite Drainage Channel $ - $ 7,320.00 $ 7,320.00 Increased 122 LF at$60.00.per LF for a final total of 322 LF. Item 99,Curb-Transition Height from 6"to 18"Offsite Drainage Channel $ - $ 1,905.00 $ 1,905.00 Increased 15 IF at$127.00 per LF for a final total of 55 LF. Item 100,Transition Height from 5'-0"Wall to Tie-In to Concrete Pilot Channel $ - $ 6,144.71 $ 6,144.71 Increased 42.97 LF at$143.00 per LF for a final total of 95.97 LF. Item 101,Transition Height from Concrete Pilot Channel to 18"Tall Curb $ - $ 17,044.50 $ 17,044,50 Increased 227.26 LF at$75.00 per LF for a final total of 300.26 LF. Item 103,Type A Sidewalk Handicap Ramp $ - $ 3,000.00 $ 3,000.00 Increased 3 EA at$1000.00 per EA for a final total of 24 EA. 'Item 106,Furnish&Install 9"-12"Nominal Rock Rip Rap $ - $ 13,621 50 $ 13,621.50 Increased 100.91 SY at$135 per SY for a final total of 236.90 SY Item 107,Furnish&Install Pedestrian Rail $ - $ 6,000.00 $ 6 000 00 Increased 30 LF at$200 per LF for a final total of 45 LF. Item 120,White Crosswalk Striping Blocks $ 400.00 $ - $ (400.00) Decreased 1 EA at$400.00 per EA for a final total of 12 EA. Item 121,Remove&Replace Existing Mailbox $ 7,000.00 $ - $ (7,000.00) Decreased 7 EA at$1000.00 per EA for a final total of 0 EA. TOTAL $ 541,424.29 $ 169,677.03 $ (371.747.26) AMOUNT OF ORIGINAL CONTRACT: $ 5,566,124.00 TOTAL AMOUNT OF THIS CHANGE ORDER: $ (371,747.20) TOTAL AMOUNT OF PREVIOUS CHANGE ORDERS. $ - CONTRACT AMOUNT TO DATE: $ 5,194,376.74 The completion time under your contract will be extended by zero(0)days because of this change order making the revised completion date March 12,2023. Recomm de By Pro' ct ngineer By: Titte:_Project Engineer Date: 0 0-r cepted By Contractor Recommended By Arch/Eng: Approved By Owner: (if applicable) B : By: ",""~/Ae6 By. Till Pr es i i enl Title:_City Engineer Title:_City Manager Date: es?p 7/A Oo1? Date: C.' —a3 Date: