Res 081-2022 Construction Contract to Marrs for WIC Ramp Renovation 07/19/2022 Resolution No. 81-2022
Resolution awarding Construction Services Contract to MARRS
Patriot Construction, LLC for the Health Department, Women, Infants
and Children Ramp Renovation Project for the amount of$104,566.88.
WHEREAS, The City of Wichita Falls wishes to undertake renovation of the
existing WIC accessibility ramp addition located at the Health Department; and,
WHEREAS, the renovation of this area will create a functional accessibility
entrance for not only the exterior WIC entrance but also the Main entrance of the Health
Department; and,
WHEREAS, Marrs Patriot Construction, LLC has submitted a bid for completion of
the project.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
The construction agreement for the amount of $104,566.88.with Marrs Patriot
Construction, LLC for the City of Wichita Falls Health Department WIC ramp renovation
is hereby approved, and the City Manager is authorized to sign the agreement in a form
approved by the City Attorney.
PASSED AND APPROVED this the 19th day of July, 2022.
2
MAYOR
ATTEST:
/6,0 ZiC tlac,; -)
City Clerk
CITY OF WICHITA FALLS
WICHITA FALLS-WICHITA COUNTY PUBLIC HEALTH DISTRICT
ENTRANCE RAMP RENOVATION AGREEMENT
This Agreement("Agreement") is entered into on this day of July, 2022,by and between the City of
Wichita Falls,"Owner,"by and through the Wichita Falls-Wichita County Public Health District,"Owner",
and Mans Patriot Construction,LLC,"Contractor."
Recitals
A. Owner is seeking to renovate the entrance ramp for the Wichita Falls-Wichita County Public Health
District(Project) located at 1700 3rd Street,Wichita Falls, Texas 76301,see Exhibit A; and,
B. Contractor submitted a bid and was awarded the Project by the City of Wichita Falls;and,
C. Contractor is a licensed contractor in the building remodeling business, properly licensed and
bonded, and has the capability to construct the Project in accordance with generally accepted
demolition practices and procedures;and,
D. SLA Architects will oversee the work on behalf of Owner and shall work with Contractor to
complete the Project; and,
E. The parties desire to enter into this Agreement upon the terms and conditions that follow.
Now,therefore,in consideration of$101,013.07 and other good and valuable consideration,the receipt and
sufficiency of which is acknowledged,the parties agree as follows.
ARTICLE 1 GENERAL PROVISIONS
§ 1.1 Basic Definitions
§1.1.1 The Contract Documents.The Contract Documents are enumerated in the Agreement between the
Owner and Contractor (hereinafter the Agreement), and consist of the Agreement, Conditions of the
Contract(General, Supplementary and other Conditions),Drawings, Specifications, Addenda issued prior
to execution of the Contract, attached hereto as Exhibit A, other documents listed in the Agreement and
Modifications issued after execution of the Contract. A Modification is (1) a written amendment to the
Contract signed by both parties, (2) a Change Order, (3) a Construction Change Directive or(4)a written
order for a minor change in the Work issued by the Architect. Unless specifically enumerated in the
Agreement,the Contract Documents do not include the advertisement or invitation to bid, Instructions to
Bidders, sample forms, other information furnished by the Owner in anticipation of receiving bids or
proposals,the Contractor's bid or proposal,or portions of addenda relating to bidding requirements).
§ 1.1.2 The Contract. The Contract Documents form the Contract for Construction. The Contract
represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations,
representations or agreements,either written or oral. The Contract may be amended or modified only by a
Modification. The Contract Documents shall not be construed to create a contractual relationship of any
kind (1)between the Contractor and the Architect or the Architect's consultants, (2)between the Owner
and the Construction Manager or the Construction Manager's consultants, (3)between the Owner and the
1
Architect or the Architect's consultants, (4)between the Contractor and the Construction Manager or the
Construction Manager's consultants,(5)between the Owner and a Subcontractor or Sub-Subcontractor(6)
between the Construction Manager and the Architect, or(7)between any persons or entities other than the
Owner and Contractor.The Construction Manager and Architect shall,however,be entitled to performance
and enforcement of obligations under the Contract intended to facilitate performance of their duties.
§ 1.1.3 The Work. The term "Work" means the construction and services required by the Contract
Documents, whether completed or partially completed, and includes all other labor, materials, equipment
and services provided or to be provided by the Contractor to fulfill the Contractor's obligations. The Work
may constitute the whole or a part of the Project.
§ 1.1.4 The Project. The Project is the total construction of which the Work performed under the Contract
Documents may be the whole or a part and which may include construction by other Multiple Prime
Contractors and by the Owner's own forces, including persons or entities under separate contracts not
administered by the Construction Manager and in general includes work required by City of Wichita Falls
Bid#22-39.
§ 1.1.5 The Drawings. The Drawings are the graphic and pictorial portions of the Contract Documents
showing the design, location and dimensions of the Work, generally including plans, elevations, sections,
details,schedules and diagrams.
§1.1.6 The Specifications. The Specifications are that portion of the Contract Documents consisting of the
written requirements for materials, equipment, systems, standards and workmanship for the Work, and
performance of related services.
§ 1.1.7 Instruments of Service. Instruments of Service are representations, in any medium of expression
now known or later developed, of the tangible and intangible creative work performed by the Architect and
the Architect's consultants under their respective professional services agreements. Instruments of Service
may include, without limitation, studies, surveys, models, sketches, drawings, specifications, and other
similar materials.
§ 1.1.8 Initial Decision Maker. The Initial Decision Maker is the person identified in the Agreement to
render initial decisions on Claims in accordance with Section 15.2 and certify termination of the Agreement
under Section 14.2.2.
§ 1.2 Correlation and Intent of the Contract Documents
§ 1.2.1 The intent of the Contract Documents is to include all items necessary for the proper execution and
completion of the Work by the Contractor. The Contract Documents are complementary, and what is
required by one shall be as binding as if required by all; performance by the Contractor shall be required
only to the extent consistent with the Contract Documents and reasonably inferable from them as being
necessary to produce the indicated results.
§1.2.2 Organization of the Specifications into divisions,sections and articles,and arrangement of Drawings
shall not control the Contractor in dividing the Work among Subcontractors or in establishing the extent of
Work to be performed by any trade.
§ 1.2.3 Unless otherwise stated in the Contract Documents, words that have well-known technical or
construction industry meanings are used in the Contract Documents in accordance with such recognized
meanings.
2
§ 1.3 Capitalization
Terms capitalized in these General Conditions include those that are(1) specifically defined, (2)the titles
of numbered articles or(3)the titles of other documents published by the American Institute of Architects.
§ 1.4 Interpretation
In the interest of brevity,the Contract Documents frequently omit modifying words such as"all"and"any"
and articles such as "the"and"an,"but the fact that a modifier or an article is absent from one statement
and appears in another is not intended to affect the interpretation of either statement.
ARTICLE 2 OWNER
§2.1 General
§2.1.1 The Owner is the person or entity identified as such in the Agreement and is referred to throughout
the Contract Documents as if singular in number.The Owner may designate in writing a representative who
shall have express authority to bind the Owner with respect to all matters requiring the Owner's approval
or authorization. Except as otherwise provided in Article 4,the Construction Manager and the Architect do
not have such authority. The term"Owner"means the Owner or the Owner's authorized representative.
§ 2.1.2 The Owner shall furnish to the Contractor within fifteen days after receipt of a written request,
information necessary and relevant for the Contractor to evaluate,give notice of or enforce mechanic's lien
rights. Such information shall include a correct statement of the record legal title to the property on which
the Project is located,usually referred to as the site,and the Owner's interest therein.
§2.2 Information and Services Required of the Owner
§2.2.1 Prior to commencement of the Work,the Contractor may request in writing that the Owner provide
reasonable evidence that the Owner has made financial arrangements to fulfill the Owner's obligations
under the Contract. Thereafter, the Contractor may only request such evidence if(1) the Owner fails to
make payments to the Contractor as the Contract Documents require; (2) a change in the Work materially
changes the Contract Sum; or (3) the Contractor identifies in writing a reasonable concern regarding the
Owner's ability to make payment when due. The Owner shall furnish such evidence as a condition
precedent to commencement or continuation of the Work or the portion of the Work affected by a material
change. After the Owner furnishes the evidence, the Owner shall not materially vary such financial
arrangements without prior notice to the Contractor.
§ 2.2.2 Except for permits and fees that are the responsibility of the Contractor under the Contract
Documents, including those required under Section 3.7.1, the Owner shall secure and pay for necessary
approvals, easements, assessments and charges required for construction,use or occupancy of permanent
structures or for permanent changes in existing facilities. Unless otherwise provided under the Contract
Documents,the Owner,through the Construction Manager, shall secure and pay for the building permit.
§ 2.2.3 The Owner shall furnish surveys describing physical characteristics, legal limitations and utility
locations for the site of the Project, and a legal description of the site. The Contractor shall be entitled to
rely on the accuracy of information furnished by the Owner but shall exercise proper precautions relating
to the safe performance of the Work.
§2.2.4 The Owner shall furnish information or services required of the Owner by the Contract Documents
with reasonable promptness. The Owner shall also furnish any other information or services under the
Owner's control and relevant to the Contractor's performance of the Work with reasonable promptness
after receiving the Contractor's written request for such information or services.
3
§2.2.5 Unless otherwise provided in the Contract Documents, the Owner shall furnish to the Contractor
one copy of the Contract Documents for purposes of making reproductions pursuant to Section 1.5.2.
§2.2.6 The Owner shall endeavor to forward all communications to the Contractor through the Construction
Manager and shall contemporaneously provide the same communications to the Architect about matters
arising out of or relating to the Contract Documents.
§2.3 Owner's Right to Stop the Work
If the Contractor fails to correct Work that is not in accordance with the requirements of the Contract
Documents as required by Section 12.2 or repeatedly fails to carry out Work in accordance with the Contract
Documents,the Owner may issue a written order to the Contractor to stop the Work,or any portion thereof,
until the cause for such order has been eliminated;however,the right of the Owner to stop the Work shall
not give rise to a duty on the part of the Owner to exercise this right for the benefit of the Contractor or any
other person or entity, except to the extent required by Section 6.1.3.
§2.4 Owner's Right to Carry Out the Work
If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and
fails within a ten-day period after receipt of written notice from the Owner to commence and continue
correction of such default or neglect with diligence and promptness,the Owner may, without prejudice to
other remedies the Owner may have, correct such deficiencies. In such case an appropriate Change Order
shall be issued deducting from payments then or thereafter due the Contractor the reasonable cost of
correcting such deficiencies, including Owner's expenses and compensation for the Construction
Manager's and Architect's and their respective consultants' additional services made necessary by such
default,neglect or failure. Such action by the Owner and amounts charged to the Contractor are both subject
to prior approval of the Architect, after consultation with the Construction Manager. If payments then or
thereafter due the Contractor are not sufficient to cover such amounts, the Contractor shall pay the
difference to the Owner.
ARTICLE 3 CONTRACTOR
§3.1 General
§ 3.1.1 The Contractor is the person or entity identified as such in the Agreement and is referred to
throughout the Contract Documents as if singular in number. The Contractor shall be lawfully licensed,if
required in the jurisdiction where the Project is located. The Contractor shall designate in writing a
representative who shall have express authority to bind the Contractor with respect to all matters under this
Contract if required by Owner.The term"Contractor"means the Contractor or the Contractor's authorized
representative.
§3.1.2 The plural term"Multiple Prime Contractors"refers to persons or entities who perform construction
under contracts with the Owner that are administered by the Construction Manager. The term does not
include the Owner's own forces,including persons or entities under separate contracts not administered by
the Construction Manager.
§3.1.3 The Contractor shall perform the Work in accordance with the Contract Documents.
§ 3.1.4 The Contractor shall not be relieved of obligations to perform the Work in accordance with the
Contract Documents either by activities or duties of the Construction Manager or Architect in their
administration of the Contract, or by tests, inspections or approvals required or performed by persons or
entities other than the Contractor.
4
§3.2 Review of Contract Documents and Field Conditions by Contractor
§3.2.1 Execution of the Contract by the Contractor is a representation that the Contractor has visited the
site, become generally familiar with local conditions under which the Work is to be performed and
correlated personal observations with requirements of the Contract Documents.
§ 3.2.2 Because the Contract Documents are complementary, the Contractor shall, before starting each
portion of the Work, carefully study and compare the various Contract Documents relative to that portion
of the Work, as well as the information furnished by the Owner pursuant to Section 2.2.3, shall take field
measurements of any existing conditions related to that portion of the Work, and shall observe any
conditions at the site affecting it. These obligations are for the purpose of facilitating coordination and
construction by the Contractor and are not for the purpose of discovering errors, omissions, or
inconsistencies in the Contract Documents; however, the Contractor shall promptly report to the
Construction Manager and Architect any errors,inconsistencies or omissions discovered by or made known
to the Contractor as a request for information submitted to the Construction Manager in such form as the
Construction Manager and Architect may require. It is recognized that the Contractor's review is made in
the Contractor's capacity as a contractor and not as a licensed design professional, unless otherwise
specifically provided in the Contract Documents.
§ 3.2.3 The Contractor is not required to ascertain that the Contract Documents are in accordance with
applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities,
but the Contractor shall promptly report to the Construction Manager and Architect any nonconformity
discovered by or made known to the Contractor as a request for information submitted to Construction
Manager in such form as the Construction Manager and Architect may require.
§ 3.2.4 If the Contractor believes that additional cost or time is involved because of clarifications or
instructions the Architect issues in response to the Contractor's notices or requests for information pursuant
to Sections 3.2.2 or 3.2.3,the Contractor shall make Claims as provided in Article 15.If the Contractor fails
to perform the obligations of Sections 3.2.2 or 3.2.3, the Contractor shall pay such costs and damages to
the Owner as would have been avoided if the Contractor had performed such obligations.If the Contractor
performs those obligations, the Contractor shall not be liable to the Owner or Architect for damages
resulting from errors,inconsistencies or omissions in the Contract Documents,for differences between field
measurements or conditions and the Contract Documents, or for nonconformities of the Contract
Documents to applicable laws,statutes,ordinances,codes,rules and regulations,and lawful orders of public
authorities.
§3.3 Supervision and Construction Procedures
§3.3.1 The Contractor shall supervise and direct the Work,using the Contractor's best skill and attention.
The Contractor shall be solely responsible for, and have control over, construction means, methods,
techniques, sequences and procedures and for coordinating all portions of the Work under the Contract,
unless the Contract Documents give other specific instruction concerning these matters. If the Contract
Documents give specific instructions concerning construction means, methods, techniques, sequences or
procedures, the Contractor shall evaluate the jobsite safety thereof and, except as stated below, shall be
fully and solely responsible for the jobsite safety of such means, methods, techniques, sequences or
procedures. If the Contractor determines that such means, methods, techniques, sequences or procedures
may not be safe, the Contractor shall give timely written notice to the Owner, the Construction Manager,
and the Architect and shall not proceed with that portion of the Work without further written instructions
from the Architect,through the Construction Manager. If the Contractor is then instructed to proceed with
the required means,methods,techniques,sequences or procedures without acceptance of changes proposed
by the Contractor,the Owner shall be solely responsible for any loss or damage arising solely from those
Owner-required means,methods,techniques,sequences or procedures.
5
§ 3.3.2 The Contractor shall be responsible to the Owner for acts and omissions of the Contractor's
employees, Subcontractors and their agents and employees, and other persons performing portions of the
Work for,or on behalf of,the Contractor or any of its Subcontractors.
§3.3.3 The Contractor shall be responsible for inspection of portions of the Project already performed to
determine that such portions are in proper condition to receive subsequent Work.
§3.4 Labor and Materials
§ 3.4.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for
labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities,
transportation,and other facilities and services necessary for proper execution and completion of the Work,
whether temporary or permanent and whether or not incorporated or to be incorporated in the Work.
§3.4.2 Except in the case of minor changes in the Work authorized by the Architect in accordance with
Sections 3.12.8 or 7.4, the Contractor may make substitutions only with the consent of the Owner, after
evaluation by the Architect, in consultation with the Construction Manager, and in accordance with a
Change Order or Construction Change Directive.
§3.4.3 The Contractor shall enforce strict discipline and good order among the Contractor's employees and
other persons carrying out the Work. The Contractor shall not permit employment of unfit persons or
persons not properly skilled in tasks assigned to them.
§3.5 Warranty
The Contractor warrants to the Owner,Construction Manager,and Architect that materials and equipment
furnished under the Contract will be of good quality and new unless the Contract Documents require or
permit otherwise. The Contractor further warrants that the Work will conform with the requirements of the
Contract Documents and will be free from defects,except for those inherent in the quality of the Work the
Contract Documents require or permit.Work,materials,or equipment not conforming to these requirements
may be considered defective. The Contractor's warranty excludes remedy for damage or defect caused by
abuse, alterations to the Work not executed by the Contractor, improper or insufficient maintenance,
improper operation,or normal wear and tear and normal usage.If required by the Construction Manager or
Architect, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and
equipment.
§3.6 Taxes
The Contractor shall pay sales, consumer, use and similar taxes for the Work or portions thereof provided
by the Contractor that are legally enacted when bids are received or negotiations concluded,whether or not
yet effective or merely scheduled to go into effect.
§3.7 Permits,Fees,Notices, and Compliance with Laws
§ 3.7.1 Unless otherwise provided in the Contract Documents, the Owner, through the Construction
Manager,shall secure and pay for the building permit.The Contractor shall secure and pay for other permits,
fees, licenses and inspections by government agencies necessary for proper execution and completion of
the Work that are customarily secured after execution of the Contract and legally required at the time bids
are received or negotiations concluded.
§3.7.2 The Contractor shall comply with and give notices required by applicable laws,statutes,ordinances,
codes,rules and regulations,and lawful orders of public authorities applicable to performance of the Work.
6
§3.7.3 If the Contractor performs Work knowing it to be contrary to applicable laws,statutes,ordinances,
codes,rules and regulations,or lawful orders of public authorities,the Contractor shall assume appropriate
responsibility for such Work and shall bear the costs attributable to correction.
§3.7.4 Concealed or Unknown Conditions.If the Contractor encounters conditions at the site that are(1)
subsurface or otherwise concealed physical conditions that differ materially from those indicated in the
Contract Documents or (2) unknown physical conditions of an unusual nature that differ materially from
those ordinarily found to exist and generally recognized as inherent in construction activities of the
character provided for in the Contract Documents, the Contractor shall promptly provide notice to the
Owner, Construction Manager, and the Architect before conditions are disturbed and in no event later than
21 days after first observance of the conditions. The Architect and Construction Manager will promptly
investigate such conditions and,if the Architect,in consultation with the Construction Manager,determines
that they differ materially and cause an increase or decrease in the Contractor's cost of, or time required
for,performance of any part of the Work,will recommend an equitable adjustment in the Contract Sum or
Contract Time,or both. If the Architect,in consultation with the Construction Manager,determines that the
conditions at the site are not materially different from those indicated in the Contract Documents and that
no change in the teens of the Contract is justified, the Architect shall promptly notify the Owner,
Construction Manager, and Contractor in writing, stating the reasons. If the Owner or Contractor disputes
the Architect's determination or recommendation,either party may proceed as provided in Article 15.
§3.7.5 If,in the course of the Work,the Contractor encounters human remains or recognizes the existence
of burial markers, archaeological sites or wetlands not indicated in the Contract Documents,the Contractor
shall immediately suspend any operations that would affect them and shall notify the Owner, Construction
Manager, and Architect. Upon receipt of such notice,the Owner shall promptly take any action necessary
to obtain governmental authorization required to resume the operations. The Contractor shall continue to
suspend such operations until otherwise instructed by the Owner but shall continue with all other operations
that do not affect those remains or features. Requests for adjustments in the Contract Sum and Contract
Time arising from the existence of such remains or features may be made as provided in Article 15.
§3.8 Allowances
§3.8.1 The Contractor shall include in the Contract Sum all allowances stated in the Contract Documents.
Items covered by allowances shall be supplied for such amounts and by such persons or entities as the
Owner may direct, but the Contractor shall not be required to employ persons or entities to whom the
Contractor has reasonable objection.
§3.8.2 Unless otherwise provided in the Contract Documents:
.1 Allowances shall cover the cost to the Contractor of materials and equipment delivered at the
site and all required taxes,less applicable trade discounts;
.2 Contractor's costs for unloading and handling at the site, labor, installation costs, overhead,
profit and other expenses contemplated for stated allowance amounts shall be included in the
Contract Sum but not in the allowances; and
.3 Whenever costs are more than or less than allowances, the Contract Sum shall be adjusted
accordingly by Change Order.The amount of the Change Order shall reflect(1)the difference
between actual costs and the allowances under Section 3.8.2.1 and(2)changes in Contractor's
costs under Section 3.8.2.2.
§ 3.8.3 Materials and equipment under an allowance shall be selected by the Owner with reasonable
promptness.
7
§3.9 Superintendent
§3.9.1 The Contractor shall employ a competent superintendent and necessary assistants who shall be in
attendance at the Project site during performance of the Work. The superintendent shall represent the
Contractor, and communications given to the superintendent shall be as binding as if given to the
Contractor.
§3.9.2 The Contractor, as soon as practicable after award of the Contract, shall furnish in writing to the
Owner and Architect through the Construction Manager, the name and qualifications of a proposed
superintendent. The Construction Manager may reply within 14 days to the Contractor in writing stating
(1)whether the Owner,the Construction Manager,or the Architect has reasonable objection to the proposed
superintendent or(2)that any of them require additional time to review.
§ 3.9.3 The Contractor shall not employ a proposed superintendent to whom the Owner, Construction
Manager or Architect has made reasonable and timely objection. The Contractor shall not change the
superintendent without the Owner's consent,which shall not unreasonably be withheld or delayed.
§3.10 Contractor's Construction Schedules
§ 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the
Owner's and Architect's information and the Construction Manager's approval a Contractor's construction
schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents,
shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be
related to the entire Project schedule to the extent required by the Contract Documents, and shall provide
for expeditious and practicable execution of the Work.The Contractor shall cooperate with the Construction
Manager in scheduling and performing the Contractor's Work to avoid conflict with, and as to cause no
delay in,the work or activities of other Multiple Prime Contractors or the construction or operations of the
Owner's own forces.
§3.10.2 The Contractor shall prepare a submittal schedule,promptly after being awarded the Contract and
thereafter update it as necessary to maintain a current submittal schedule,and shall submit the schedule(s)
for the Construction Manager's and Architect's approval. The Architect and Construction Manager's
approval shall not unreasonably be delayed or withheld. The submittal schedule shall (1) be coordinated
with the Contractor's construction schedule, and (2) allow the Construction Manager and Architect
reasonable time to review submittals.If the Contractor fails to submit a submittal schedule,the Contractor
shall not be entitled to any increase in Contract Sum or extension of Contract Time based on the time
required for review of submittals.
§3.10.3 The Contractor shall participate with other Contractors,the Construction Manager and Owner in
reviewing and coordinating all schedules for incorporation into the Project schedule that is prepared by the
Construction Manager. The Contractor shall make revisions to the construction schedule and submittal
schedule as deemed necessary by the Construction Manager to conform to the Project schedule.
§ 3.10.4 The Contractor shall perform the Work in general accordance with the most recent schedules
submitted to the Owner, Construction Manager and Architect and incorporated into the approved Project
schedule.
§3.11 Documents and Samples at the Site
The Contractor shall maintain at the site for the Owner one copy of the Drawings, Specifications,Addenda,
Change Orders and other Modifications, in good order and marked currently to indicate field changes and
selections made during construction,and one copy of approved Shop Drawings,Product Data,Samples and
similar required submittals. These documents shall be available to the Architect and delivered to the
8
Construction Manager for submittal to the Owner upon completion of the Work as a record of the Work as
constructed.
§3.12 Shop Drawings,Product Data and Samples
§3.12.1 Shop Drawings are drawings, diagrams, schedules and other data specially prepared for the Work
by the Contractor or a Subcontractor, Sub-Subcontractor,manufacturer, supplier or distributor to illustrate
some portion of the Work.
§ 3.12.2 Product Data are illustrations, standard schedules, performance charts, instructions, brochures,
diagrams and other information furnished by the Contractor to illustrate materials or equipment for some
portion of the Work.
§3.12.3 Samples are physical examples that illustrate materials, equipment or workmanship and establish
standards by which the Work will be judged.
§3.12.4 Shop Drawings,Product Data, Samples and similar submittals are not Contract Documents. Their
purpose is to demonstrate the way by which the Contractor proposes to conform to the information given
and the design concept expressed in the Contract Documents for those portions of the Work for which the
Contract Documents require submittals. Review by the Architect and Construction Manager is subject to
the limitations of Sections 4.2.9 through 4.2.11. Informational submittals upon which the Construction
Manager and Architect are not expected to take responsive action may be so identified in the Contract
Documents. Submittals that are not required by the Contract Documents may be returned by the
Construction Manager or Architect without action.
§3.12.5 The Contractor shall review for compliance with the Contract Documents, approve and submit to
the Construction Manager Shop Drawings, Product Data, Samples and similar submittals required by the
Contract Documents in accordance with the Project submittal schedule approved by the Construction
Manager and Architect, or in the absence of an approved Project submittal schedule, with reasonable
promptness and in such sequence as to cause no delay in the Work or in the activities of other Multiple
Prime Contractors or the Owner's own forces. The Contractor shall cooperate with the Construction
Manager in the coordination of the Contractor's Shop Drawings, Product Data, Samples and similar
submittals with related documents submitted by other Multiple Prime Contractors.
§ 3.12.6 By submitting Shop Drawings, Product Data, Samples and similar submittals, the Contractor
represents to the Owner, Construction Manager, and Architect, that the Contractor has (1) reviewed and
approved them, (2) determined and verified materials, field measurements and field construction criteria
related thereto, or will do so, and (3) checked and coordinated the information contained within such
submittals with the requirements of the Work and of the Contract Documents.
§3.12.7 The Contractor shall perform no portion of the Work for which the Contract Documents require
submittal and review of Shop Drawings, Product Data, Samples or similar submittals until the respective
submittal has been reviewed and approved by the Architect.
§3.12.8 The Work shall be in accordance with approved submittals except that the Contractor shall not be
relieved of responsibility for deviations from requirements of the Contract Documents by the Architect's
approval of Shop Drawings, Product Data, Samples or similar submittals unless the Contractor has
specifically informed the Construction Manager and Architect in writing of such deviation at the time of
submittal and(1)the Architect has given written approval to the specific deviation as a minor change in the
Work,or(2) a Change Order or Construction Change Directive has been issued authorizing the deviation.
The Contractor shall not be relieved of responsibility for errors or omissions in Shop Drawings, Product
Data, Samples or similar submittals by the Architect's approval thereof
9
§3.12.9 The Contractor shall direct specific attention,in writing or on resubmitted Shop Drawings,Product
Data, Samples or similar submittals, to revisions other than those requested by the Construction Manager
and Architect on previous submittals. In the absence of such written notice, the Architect's approval of a
resubmission shall not apply to such revisions.
§3.12.10 The Contractor shall not be required to provide professional services that constitute the practice
of architecture or engineering unless such services are specifically required by the Contract Documents for
a portion of the Work or unless the Contractor needs to provide such services in order to carry out the
Contractor's responsibilities for construction means,methods,techniques, sequences and procedures. The
Contractor shall not be required to provide professional services in violation of applicable law. If
professional design services or certifications by a design professional related to systems, materials or
equipment are specifically required of the Contractor by the Contract Documents, the Owner and the
Architect will specify all performance and design criteria that such services must satisfy. The Contractor
shall cause such services or certifications to be provided by a properly licensed design professional,whose
signature and seal shall appear on all drawings, calculations, specifications,certifications, Shop Drawings
and other submittals prepared by such professional. Shop Drawings and other submittals related to the Work
designed or certified by such professional, if prepared by others, shall bear such professional's written
approval when submitted to the Architect. The Owner and the Architect shall be entitled to rely upon the
adequacy, accuracy and completeness of the services, certifications and approvals performed or provided
by such design professionals, provided the Owner and Architect have specified to the Contractor all
performance and design criteria that such services must satisfy. Pursuant to this Section 3.12.10, the
Architect will review, approve or take other appropriate action on submittals only for the limited purpose
of checking for conformance with information given and the design concept expressed in the Contract
Documents. The Contractor shall not be responsible for the adequacy of the performance and design criteria
specified in the Contract Documents.
§3.13 Use of Site
§3.13.1 The Contractor shall confine operations at the site to areas permitted by applicable laws,statutes,
ordinances,codes,rules and regulations,and lawful orders of public authorities and the Contract Documents
and shall not unreasonably encumber the site with materials or equipment.
§3.13.2 The Contractor shall coordinate the Contractor's operations with, and secure the approval of,the
Construction Manager before using any portion of the site.
§3.14 Cutting and Patching
§3.14.1 The Contractor shall be responsible for cutting,fitting or patching required to complete the Work
or to make its parts fit together properly. All areas requiring cutting,fitting and patching shall be restored
to the condition existing prior to the cutting,fitting and patching,unless otherwise required by the Contract
Documents.
§3.14.2 The Contractor shall not damage or endanger a portion of the Work or fully or partially completed
construction of the Owner's own forces or of other Multiple Prime Contractors by cutting, patching, or
otherwise altering such construction,or by excavation. The Contractor shall not cut or otherwise alter such
construction by the Owner's own forces or by other Multiple Prime Contractors except with written consent
of the Construction Manager, Owner and such other Multiple Prime Contractors; such consent shall not be
unreasonably withheld. The Contractor shall not unreasonably withhold from the other Multiple Prime
Contractors or the Owner the Contractor's consent to cutting or otherwise altering the Work.
10
§3.15 Cleaning Up
§ 3.15.1 The Contractor shall keep the premises and surrounding area free from accumulation of waste
materials or rubbish caused by operations under the Contract. At completion of the Work the Contractor
shall remove waste materials, rubbish, the Contractor's tools, construction equipment, machinery and
surplus materials from and about the Project.
§ 3.15.2 If the Contractor fails to clean up as provided in the Contract Documents, the Owner, or
Construction Manager with the Owner's approval, may do so and the Owner shall be entitled to
reimbursement from the Contractor.
§3.16 Access to Work
The Contractor shall provide the Owner, Construction Manager and Architect access to the Work in
preparation and progress wherever located.
§3.17 Indemnification
§3.17.1 To the fullest extent permitted by law,the Contractor shall indemnify and hold harmless the Owner,
Construction Manager, Architect, Construction Manager's and Architect's consultants, and agents and
employees of any of them from and against claims, damages,losses and expenses,including but not limited
to attorneys' fees, arising out of or resulting from performance of the Work, provided that such claim,
damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or
destruction of tangible property(other than the Work itself)but only to the extent caused by the negligent
acts or omissions of the Contractor, a Subcontractor, anyone directly or indirectly employed by them or
anyone for whose acts they may be liable,regardless of whether or not such claim,damage,loss or expense
is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate,abridge
or reduce other rights or obligations of indemnity that would otherwise exist as to a party or person
described in this Section 3.18.
§3.17.2 In claims against any person or entity indemnified under this Section 3.18 by an employee of the
Contractor, a Subcontractor,anyone directly or indirectly employed by them or anyone for whose acts they
may be liable, the indemnification obligation under Section 3.18 shall not be limited by a limitation on
amount or type of damages, compensation or benefits payable by or for the Contractor or a Subcontractor
under workers' compensation acts, disability benefit acts or other employee benefit acts.
ARTICLE 4 ARCHITECT AND CONSTRUCTION MANAGER
§4.1 General
§4.1.1 The Owner shall retain an architect lawfully licensed to practice architecture or an entity lawfully
practicing architecture in the jurisdiction where the Project is located. That person or entity is identified as
the Architect in the Agreement and is referred to throughout the Contract Documents as if singular in
number.
§ 4.1.2 Architect may act as Owner's Construction Manager. That person or entity is identified as the
Construction Manager in the Agreement and is referred to throughout the Contract Documents as if singular
in number.
§ 4.1.3 Duties,responsibilities and limitations of authority of the Construction Manager and Architect as
set forth in the Contract Documents shall not be restricted, modified or extended without written consent
of the Owner, Construction Manager, Architect and Contractor. Consent shall not be unreasonably
withheld.
11
§4.1.4 If the employment of the Construction Manager or Architect is terminated,the Owner shall employ
a successor construction manager or architect as to whom the Contractor has no reasonable objection and
whose status under the Contract Documents shall be that of the Construction Manager or Architect,
respectively.
§4.2 Administration of the Contract
§4.2.1 The Construction Manager and Architect will provide administration of the Contract as described
in the Contract Documents and will be the Owner's representatives during construction until the date the
Architect issues the final Certificate for Payment. The Construction Manager and Architect will have
authority to act on behalf of the Owner only to the extent provided in the Contract Documents.
§4.2.2 The Architect will visit the site at intervals appropriate to the stage of construction,or as otherwise
agreed with the Owner, to become generally familiar with the progress and quality of the portion of the
Work completed, and to determine in general if the Work observed is being performed in a manner
indicating that the Work, when fully completed, will be in accordance with the Contract Documents.
However,the Architect will not be required to make exhaustive or continuous on-site inspections to check
the quality or quantity of the Work. On the basis of the site visits, the Architect will keep the Owner
reasonably informed about the progress and quality of the portion of the Work completed,and report to the
Owner and Construction Manager(1)known deviations from the Contract Documents and from the most
recent Project schedule prepared by the Construction Manager, and(2) defects and deficiencies observed
in the Work.
§ 4.2.3 The Construction Manager, and Architect will not have control over, or charge of, construction
means, methods, techniques, sequences or procedures, or for the safety precautions and programs in
connection with the Work, since these are solely the Contractor's rights and responsibilities under the
Contract Documents, except as provided in Section 3.3.1, and neither will be responsible for the
Contractor's failure to perform the Work in accordance with the requirements of the Contract Documents.
Neither the Construction Manager nor the Architect will have control over or charge of or be responsible
for acts or omissions of the Contractor,Subcontractors,or their agents or employees,or of any other persons
or entities performing portions of the Work.
§ 4.2.4 Communications Facilitating Contract Administration. Except as otherwise provided in the
Contract Documents or when direct communications have been specially authorized, the Owner and
Contractor shall endeavor to communicate with each other through the Construction Manager, and shall
contemporaneously provide the same communications to the Architect about matters arising out of or
relating to the Contract Documents. Communications by and with the Architect's consultants shall be
through the Architect. Communications by and with Subcontractors and material suppliers shall be through
the Contractor. Communications by and with other Multiple Prime Contractors shall be through the
Construction Manager and shall be contemporaneously provided to the Architect if those communications
are about matters arising out of or related to the Contract Documents. Communications by and with the
Owner's own forces shall be through the Owner.
§ 4.2.5 The Construction Manager and Architect will review and certify all Applications for Payment by
the Contractor, in accordance with the provisions of Article 9.
§4.2.6 The Architect and Construction Manager have authority to reject Work that does not conform to the
Contract Documents and will notify each other about the rejection. The Construction Manager shall
determine in general whether the Work of the Contractor is being performed in accordance with the
requirements of the Contract Documents and notify the Owner, Contractor and Architect of defects and
deficiencies in the Work. Whenever the Construction Manager considers it necessary or advisable, the
Construction Manager will have authority to require additional inspection or testing of the Work in
12
accordance with Sections 13.5.2 and 13.5.3,upon written authorization of the Owner,whether or not such
Work is fabricated, installed or completed. The foregoing authority of the Construction Manager will be
subject to the provisions of Sections 4.2.16 through 4.2.18 inclusive, with respect to interpretations and
decisions of the Architect. However, neither the Architect's nor the Construction Manager's authority to
act under this Section 4.2.6 nor a decision made by either of them in good faith either to exercise or not to
exercise such authority shall give rise to a duty or responsibility of the Architect or the Construction
Manager to the Contractor, Subcontractors, material and equipment suppliers,their agents or employees,
or other persons performing any of the Work.
§ 4.2.7 The Construction Manager will receive and promptly review for conformance with the submittal
requirements of the Contract Documents, all submittals from the Contractor such as Shop Drawings,
Product Data and Samples. Where there are Multiple Prime Contractors, the Construction Manager will
also check and coordinate the information contained within each submittal received from Contractor and
other Multiple Prime Contractors, and transmit to the Architect those recommended for approval. By
submitting Shop Drawings, Product Data, Samples and similar submittals, the Construction Manager
represents to the Owner and Architect that the Construction Manager has reviewed and recommended them
for approval. The Construction Manager's actions will be taken in accordance with the Project submittal
schedule approved by the Architect or, in the absence of an approved Project submittal schedule, with
reasonable promptness while allowing sufficient time to permit adequate review by the Architect.
§ 4.2.8 The Architect will review and approve or take other appropriate action upon the Contractor's
submittals such as Shop Drawings,Product Data and Samples,but only for the limited purpose of checking
for conformance with information given and the design concept expressed in the Contract Documents. The
Architect's action will be taken in accordance with the submittal schedule approved by the Architect or, in
the absence of an approved submittal schedule,with reasonable promptness while allowing sufficient time
in the Architect's professional judgment to permit adequate review.Upon the Architect's completed review,
the Architect shall transmit its submittal review to the Construction Manager.
§4.2.9 Review of the Contractor's submittals by the Construction Manager and Architect is not conducted
for the purpose of determining the accuracy and completeness of other details such as dimensions and
quantities, or for substantiating instructions for installation or performance of equipment or systems, all of
which remain the responsibility of the Contractor as required by the Contract Documents. The Construction
Manager and Architect's review of the Contractor's submittals shall not relieve the Contractor of the
obligations under Sections 3.3, 3.5 and 3.12. The Construction Manager and Architect's review shall not
constitute approval of safety precautions or, unless otherwise specifically stated by the Construction
Manager and Architect, of any construction means, methods, techniques, sequences or procedures. The
Architect's approval of a specific item shall not indicate approval of an assembly of which the item is a
component.
§4.2.10 The Construction Manager will prepare Change Orders and Construction Change Directives.
§ 4.2.11 The Construction Manager and the Architect will take appropriate action on Change Orders or
Construction Change Directives in accordance with Article 7 and the Architect will have authority to order
minor changes in the Work as provided in Section 7.4. The Architect,in consultation with the Construction
Manager, will investigate and make determinations and recommendations regarding concealed and
unknown conditions as provided in Section 3.7.4.
§ 4.2.12 Utilizing the documents provided by the Contractor, the Construction Manager will maintain at
the site for the Owner one copy of all Contract Documents, approved Shop Drawings, Product Data,
Samples and similar required submittals, in good order and marked currently to record all changes and
13
selections made during construction. These will be available to the Architect and the Contractor, and will
be delivered to the Owner upon completion of the Project.
§ 4.2.13 The Construction Manager will assist the Architect in conducting inspections to determine the
dates of Substantial Completion and the date of final completion; issue Certificates of Substantial
Completion in conjunction with the Architect pursuant to Section 9.8;and receive and forward to the Owner
written warranties and related documents required by the Contract and assembled by the Contractor
pursuant to Section 9.10. The Construction Manager will forward to the Architect a final Application and
Certificate for Payment or final Project Application and Project Certificate for Payment upon the
Contractor's compliance with the requirements of the Contract Documents.
§4.2.14 If the Owner and Architect agree,the Architect will provide one or more project representatives to
assist in carrying out the Architect's responsibilities at the site. The duties,responsibilities and limitations
of authority of such project representatives shall be as set forth in an exhibit to be incorporated in the
Contract Documents.
§4.2.15 The Architect will interpret and decide matters concerning performance under, and requirements
of the Contract Documents on written request of the Construction Manager, Owner or Contractor through
the Construction Manager. The Architect's response to such requests will be made in writing within any
time limits agreed upon or otherwise with reasonable promptness.
§4.2.16 Interpretations and decisions of the Architect will be consistent with the intent of and reasonably
inferable from the Contract Documents and will be in writing or in the form of drawings. When making
such interpretations and decisions, the Architect will endeavor to secure faithful performance by both
Owner and Contractor,will not show partiality to either and will not be liable for results of interpretations
or decisions so rendered in good faith.
§4.2.17 The Architect's decisions on matters relating to aesthetic effect will be final if consistent with the
intent expressed in the Contract Documents.
§4.2.18 The Construction Manager will receive and review requests for information from the Contractor,
and forward each request for information to the Architect, with the Construction Manager's
recommendation.The Architect will review and respond in writing to the Construction Manager to requests
for information about the Contract Documents. The Construction Manager's recommendation and the
Architect's response to each request will be made in writing within any time limits agreed upon or otherwise
with reasonable promptness. If appropriate, the Architect will prepare and issue supplemental Drawings
and Specifications in response to the requests for information.
ARTICLE 5 SUBCONTRACTORS
§5.1 Definitions
§ 5.1.1 A Subcontractor is a person or entity who has a direct contract with the Contractor to perform a
portion of the Work at the site.The term"Subcontractor"is referred to throughout the Contract Documents
as if singular in number and means a Subcontractor or an authorized representative of the Subcontractor.
The term "Subcontractor" does not include other Multiple Prime Contractors or subcontractors of other
Multiple Prime Contractors.
§5.1.2 A Sub-Subcontractor is a person or entity who has a direct or indirect contract with a Subcontractor
to perform a portion of the Work at the site. The term "Sub-Subcontractor" is referred to throughout the
Contract Documents as if singular in number and means a Sub-Subcontractor or an authorized
representative of the Sub-Subcontractor.
14
§5.2 Award of Subcontracts and Other Contracts for Portions of the Work
§5.2.1 Unless otherwise stated in the Contract Documents or the bidding requirements,the Contractor,as
soon as practicable after award of the Contract, shall furnish in writing to the Construction Manager for
review by the Owner, Construction Manager and Architect, the names of persons or entities (including
those who are to furnish materials or equipment fabricated to a special design)proposed for each principal
portion of the Work. The Construction Manager may reply within 14 days to the Contractor in writing
stating(1)whether the Owner, the Construction Manager or the Architect has reasonable objection to any
such proposed person or entity or,(2)that the Construction Manager,Architect or Owner requires additional
time for review.
§5.2.2 The Contractor shall not contract with a proposed person or entity to whom the Owner,Construction
Manager or Architect has made reasonable and timely objection. The Contractor shall not be required to
contract with anyone to whom the Contractor has made reasonable objection.
§ 5.2.3 If the Owner, Construction Manager or Architect has reasonable objection to a person or entity
proposed by the Contractor, the Contractor shall propose another to whom the Owner, Construction
Manager or Architect has no reasonable objection. If the proposed but rejected Subcontractor was
reasonably capable of performing the Work, the Contract Sum and Contract Time shall be increased or
decreased by the difference, if any, occasioned by such change,and an appropriate Change Order shall be
issued before commencement of the substitute Subcontractor's Work.However,no increase in the Contract
Sum or Contract Time shall be allowed for such change unless the Contractor has acted promptly and
responsively in submitting names as required.
§ 5.2.4 The Contractor shall not substitute a Subcontractor, person or entity previously selected if the
Owner, Construction Manager or Architect makes reasonable objection to such substitution.
ARTICLE 6 CONSTRUCTION BY OWNER OR BY OTHER CONTRACTORS
§6.1 Owner's Right to Perform Construction with Own Forces and to Award Other Contracts
§6.1.1 The Owner reserves the right to perform construction or operations related to the Project with the
Owner's own forces, which include persons or entities under separate contracts not administered by the
Construction Manager, and to award other contracts in connection with other portions of the Project or
other construction or operations on the site under Conditions of the Contract identical or substantially
similar to these including those portions related to insurance and waiver of subrogation. If the Contractor
claims that delay or additional cost is involved because of such action by the Owner,the Contractor shall
make such Claim as provided in Article 15.
§ 6.1.2 When the Owner performs construction or operations with the Owner's own forces including
persons or entities under separate contracts not administered by the Construction Manager,the Owner shall
provide for coordination of such forces with the Work of the Contractor,who shall cooperate with them.
§6.1.3 Unless otherwise provided in the Contract Documents, when the Owner performs construction or
operations related to the Project with the Owner's own forces,the Owner shall be deemed to be subject to
the same obligations and to have the same rights that apply to the Contractor under the Conditions of the
Contract,including,without excluding others, those stated in Article 3,this Article 6, and Articles 10, 11,
and 12.
§6.2 Mutual Responsibility
§ 6.2.1 The Contractor shall afford the Owner's own forces, Construction Manager and other Multiple
Prime Contractors reasonable opportunity for introduction and storage of their materials and equipment and
15
performance of their activities, and shall connect and coordinate the Contractor's construction and
operations with theirs as required by the Contract Documents.
§ 6.2.2 If part of the Contractor's Work depends for proper execution or results upon construction or
operations by the Owner's own forces or other Multiple Prime Contractors, the Contractor shall, prior to
proceeding with that portion of the Work, promptly report to the Construction Manager and Architect
apparent discrepancies or defects in such other construction that would render it unsuitable for such proper
execution and results. Failure of the Contractor so to report shall constitute an acknowledgment that the
Owner's own forces or other Multiple Prime Contractors' completed or partially completed construction is
fit and proper to receive the Contractor's Work, except as to defects not then reasonably discoverable.
§ 6.2.3 The Contractor shall reimburse the Owner for costs the Owner incurs, including costs that are
payable to a separate contractor or to other Multiple Prime Contractors because of the Contractor's delays,
improperly timed activities or defective construction. The Owner shall be responsible to the Contractor for
costs the Contractor incurs because of delays,improperly timed activities,damage to the Work or defective
construction by the Owner's own forces or other Multiple Prime Contractors.
§ 6.2.4 The Contractor shall promptly remedy damage the Contractor wrongfully causes to completed or
partially completed construction or to property of the Owner,separate contractors,or other Multiple Prime
Contractors as provided in Section 10.2.5.
§ 6.2.5 The Owner and other Multiple Prime Contractors shall have the same responsibilities for cutting
and patching as are described for the Contractor in Section 3.14.
§6.3 Owner's Right to Clean Up
If a dispute arises among the Contractor, other Multiple Prime Contractors and the Owner as to the
responsibility under their respective contracts for maintaining the premises and surrounding area free from
waste materials and rubbish, the Owner may clean up and the Construction Manager, with notice to the
Architect,will allocate the cost among those responsible.
ARTICLE 7 CHANGES IN THE WORK
§7.1 General
§7.1.1 Changes in the Work may be accomplished after execution of the Contract,and without invalidating
the Contract, by Change Order, Construction Change Directive or order for a minor change in the Work,
subject to the limitations stated in this Article 7 and elsewhere in the Contract Documents.
§7.1.2 A Change Order shall be based upon agreement among the Owner,Construction Manager,Architect
and Contractor;a Construction Change Directive requires agreement by the Owner,Construction Manager
and Architect and may or may not be agreed to by the Contractor;an order for a minor change in the Work
may be issued by the Architect alone.
§7.1.3 Changes in the Work shall be performed under applicable provisions of the Contract Documents,
and the Contractor shall proceed promptly, unless otherwise provided in the Change Order, Construction
Change Directive or order for a minor change in the Work.
§7.2 Change Orders
A Change Order is a written instrument prepared by the Construction Manager and signed by the Owner,
Construction Manager, Architect and Contractor,stating their agreement upon all of the following:
.1 The change in the Work;
.2 The amount of the adjustment,if any, in the Contract Sum; and
16
.3 The extent of the adjustment,if any, in the Contract Time.
§7.3 Construction Change Directives
§ 7.3.1 A Construction Change Directive is a written order prepared by the Construction Manager and
signed by the Owner, Construction Manager and Architect, directing a change in the Work prior to
agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by
Construction Change Directive, without invalidating the Contract, order changes in the Work within the
general scope of the Contract consisting of additions, deletions or other revisions, the Contract Sum and
Contract Time being adjusted accordingly.
§7.3.2 A Construction Change Directive shall be used in the absence of total agreement on the terms of a
Change Order.
§7.3.3 If the Construction Change Directive provides for an adjustment to the Contract Sum,the adjustment
shall be based on one of the following methods:
.1 Mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating
data to permit evaluation;
.2 Unit prices stated in the Contract Documents or subsequently agreed upon;
.3 Cost to be determined in a manner agreed upon by the parties and a mutually acceptable fixed
or percentage fee;or
.4 As provided in Section 7.3.7.
§7.3.4 If unit prices are stated in the Contract Documents or subsequently agreed upon, and if quantities
originally contemplated are materially changed in a proposed Change Order or Construction Change
Directive so that application of such unit prices to quantities of Work proposed will cause substantial
inequity to the Owner or Contractor,the applicable unit prices shall be equitably adjusted.
§7.3.5 Upon receipt of a Construction Change Directive,the Contractor shall promptly proceed with the
change in the Work involved and advise the Construction Manager and Architect of the Contractor's
agreement or disagreement with the method, if any, provided in the Construction Change Directive for
determining the proposed adjustment in the Contract Sum or Contract Time.
§ 7.3.6 A Construction Change Directive signed by the Contractor indicates the Contractor's agreement
therewith, including adjustment in Contract Sum and Contract Time or the method for determining them.
Such agreement shall be effective immediately and shall be recorded as a Change Order.
§ 7.3.7 If the Contractor does not respond promptly or disagrees with the method for adjustment in the
Contract Sum, the Construction Manager shall determine the method and the adjustment on the basis of
reasonable expenditures and savings of those performing the Work attributable to the change,including, in
case of an increase in the Contract Sum, an amount for overhead and profit as set forth in the Agreement,
or if no such amount is set forth in the Agreement,a reasonable amount.In such case,and also under Section
7.3.3.3,the Contractor shall keep and present,in such form as the Construction Manager may prescribe, an
itemized accounting together with appropriate supporting data. Unless otherwise provided in the Contract
Documents, costs for the purposes of this Section 7.3.7 shall be limited to the following:
.1 Costs of labor,including social security,old age and unemployment insurance,fringe benefits
required by agreement or custom,and workers' compensation insurance;
.2 Costs of materials, supplies and equipment, including cost of transportation, whether
incorporated or consumed;
.3 Rental costs of machinery and equipment, exclusive of hand tools, whether rented from the
Contractor or others;
17
.4 Costs of premiums for all bonds and insurance, permit fees, and sales, use or similar taxes
related to the Work;and
.5 Additional costs of supervision and field office personnel directly attributable to the change.
§ 7.3.8 The amount of credit to be allowed by the Contractor to the Owner for a deletion or change that
results in a net decrease in the Contract Sum shall be actual net cost as confirmed by the Construction
Manager and Architect. When both additions and credits covering related Work or substitutions are
involved in a change,the allowance for overhead and profit shall be figured on the basis of net increase,if
any,with respect to that change.
§7.3.9 Pending final determination of the total cost of a Construction Change Directive to the Owner,the
Contractor may request payment for Work completed under the Construction Change Directive in
Applications for Payment.The Construction Manager and Architect will make an interim determination for
purposes of monthly certification for payment for those costs and certify for payment the amount that the
Construction Manager and Architect determine to be reasonably justified.The interim determination of cost
shall adjust the Contract Sum on the same basis as a Change Order, subject to the right of either party to
disagree and assert a Claim in accordance with Article 15.
§7.3.10 When the Owner and Contractor agree with a determination made by the Construction Manager
and Architect concerning the adjustments in the Contract Sum and Contract Time, or otherwise reach
agreement upon the adjustments, such agreement shall be effective immediately and the Construction
Manager shall prepare a Change Order. Change Orders may be issued for all or any part of a Construction
Change Directive.
§7.4 Minor Changes in the Work
The Architect has authority to order minor changes in the Work not involving adjustment in the Contract
Sum or extension of the Contract Time and not inconsistent with the intent of the Contract Documents.
Such changes will be effected by written order issued through the Construction Manager and shall be
binding on the Owner and Contractor.
ARTICLE 8 TIME
§8.1 Definitions
§8.1.1 Unless otherwise provided,Contract Time is 180 days unless amended by written agreement of both
parties.
§8.1.2 The date of commencement of the Work is the date established in the Agreement.
§8.1.3 The date of Substantial Completion is the date certified by the Architect in accordance with Section
9.8.
§ 8.1.4 The term "day" as used in the Contract Documents shall mean calendar day unless otherwise
specifically defined.
§8.2 Progress and Completion
§8.2.1 Time limits stated in the Contract Documents are of the essence of the Contract. By executing the
Agreement,the Contractor confirms that the Contract Time is a reasonable period for performing the Work.
§ 8.2.2 The Contractor shall not knowingly, except by agreement or instruction of the Owner in writing,
prematurely commence operations on the site or elsewhere prior to the effective date of insurance required
18
by Article 11 to be furnished by the Contractor and Owner. The date of commencement of the Work shall
not be changed by the effective date of such insurance.
§ 8.2.3 The Contractor shall proceed expeditiously with adequate forces and shall achieve Substantial
Completion within the Contract Time.
§8.3 Delays and Extensions of Time
§8.3.1 If the Contractor is delayed at any time in the commencement or progress of the Work by an act or
neglect of the Owner, Owner's own forces, Construction Manager, Architect, any of the other Multiple
Prime Contractors or an employee of any of them,or by changes ordered in the Work,or by labor disputes,
fire,unusual delay in deliveries,unavoidable casualties or other causes beyond the Contractor's control,or
by other causes that the Architect,based on the recommendation of the Construction Manager, determines
may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as
the Architect may determine.
§8.3.2 Claims relating to time shall be made in accordance with applicable provisions of Article 15.
§ 8.3.3 This Section 8.3 does not preclude recovery of damages for delay by either party under other
provisions of the Contract Documents.
ARTICLE 9 PAYMENTS AND COMPLETION
§9.1 Contract Sum
The Contract Sum is stated in the Agreement and, including authorized adjustments, is the total amount
payable by the Owner to the Contractor for performance of the Work under the Contract Documents.
§9.2 Schedule of Values
Where the Contract is based on a Stipulated Sum or Guaranteed Maximum Price, the Contractor shall
submit to the Construction Manager, before the first Application for Payment, a schedule of values
allocating the entire Contract Sum to the various portions of the Work and prepared in such form and
supported by such data to substantiate its accuracy as the Construction Manager and Architect may require.
This schedule, unless objected to by the Construction Manager or Architect, shall be used as a basis for
reviewing the Contractor's Applications for Payment.In the event there is one Contractor,the Construction
Manager shall forward to the Architect the Contractor's schedule of values. If there are Multiple Prime
Contractors responsible for performing different portions of the Project, the Construction Manager shall
forward the Multiple Prime Contractors' schedules of values only if requested by the Architect.
§9.3 Applications for Payment
§ 9.3.1 The Contractor shall submit to the Construction Manager an itemized Application for Payment
prepared in accordance with the schedule of values, if required under Section 9.2, for completed portions
of the Work. Such application shall be notarized,if required,and supported by such data substantiating the
Contractor's right to payment as the Owner,Construction Manager or Architect may require,such as copies
of requisitions from Subcontractors and material suppliers,and shall reflect retainage if provided for in the
Contract Documents.
§9.3.1.1 As provided in Section 7.3.9,such applications may include requests for payment on account of
changes in the Work that have been properly authorized by Construction Change Directives,or by interim
determinations of the Construction Manager and Architect,but not yet included in Change Orders.
§ 9.3.1.2 Applications for Payment shall not include requests for payment for portions of the Work for
which the Contractor does not intend to pay a Subcontractor or material supplier unless such Work has been
performed by others whom the Contractor intends to pay.
19
§ 9.3.2 Unless otherwise provided in the Contract Documents, payments shall be made on account of
materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work.
If approved in advance by the Owner,payment may similarly be made for materials and equipment suitably
stored off the site at a location agreed upon in writing. Payment for materials and equipment stored on or
off the site shall be conditioned upon compliance by the Contractor with procedures satisfactory to the
Owner to establish the Owner's title to such materials and equipment or otherwise protect the Owner's
interest, and shall include the costs of applicable insurance, storage and transportation to the site for such
materials and equipment stored off the site.
§9.3.3 The Contractor warrants that title to all Work covered by an Application for Payment will pass to
the Owner no later than the time of payment. The Contractor further warrants that upon submittal of an
Application for Payment all Work for which Certificates for Payment have been previously issued and
payments received from the Owner shall,to the best of the Contractor's knowledge,information and belief,
be free and clear of liens, claims, security interests or encumbrances in favor of the Contractor,
Subcontractors,material suppliers,or other persons or entities making a claim by reason of having provided
labor,materials and equipment relating to the Work.
§9.4 Certificates for Payment
§ 9.4.1 Where there is only one Contractor, the Construction Manager will, within seven days after the
Construction Manager's receipt of the Contractor's Application for Payment, review the Application,
certify the amount the Construction Manager determines is due the Contractor,and forward the Contractor's
Application and Certificate for Payment to the Architect.Within seven days after the Architect receives the
Contractor's Application for Payment from the Construction Manager,the Architect will either issue to the
Owner a Certificate for Payment,with a copy to the Construction Manager,for such amount as the Architect
determines is properly due, or notify the Construction Manager and Owner in writing of the Architect's
reasons for withholding certification in whole or in part as provided in Section 9.5.1. The Construction
Manager will promptly forward to the Contractor the Architect's notice of withholding certification.
§ 9.4.2 Within seven days after the Architect receives the Project Application and Project Certificate for
Payment and the Summary of Contractors' Applications for Payment from the Construction Manager,the
Architect will either issue to the Owner a Project Certificate for Payment, with a copy to the Construction
Manager,for such amount as the Architect determines is properly due,or notify the Construction Manager
and Owner in writing of the Architect's reasons for withholding certification in whole or in part as provided
in Section 9.5.1. The Construction Manager will promptly forward the Architect's notice of withholding
certification to the Contractors.
§9.4.3 The Construction Manager's certification of an Application for Payment or,in the case of Multiple
Prime Contractors,a Project Application and Certificate for Payment shall be based upon the Construction
Manager's evaluation of the Work and the information provided as part of the Application for Payment.
The Construction Manager's certification will constitute a representation that, to the best of the
Construction Manager's knowledge,information and belief,the Work has progressed to the point indicated
and the quality of the Work is in accordance with the Contract Documents. The certification will also
constitute a recommendation to the Architect and Owner that the Contractor be paid the amount certified.
§9.4.4 The Architect's issuance of a Certificate for Payment shall be based upon the Architect's evaluation
of the Work, the recommendation of the Construction Manager, and information provided as part of the
Application for Payment or Project Application for Payment. The Architect's certification will constitute a
representation that, to the best of the Architect's knowledge, information and belief, the Work has
progressed to the point indicated,that the quality of the Work is in accordance with the Contract Documents,
and that the Contractor is entitled to payment in the amount certified.
20
§ 9.4.5 The representations made pursuant to Article 9.4 are subject to an evaluation of the Work for
conformance with the Contract Documents upon Substantial Completion,to results of subsequent tests and
inspections, to correction of minor deviations from the Contract Documents prior to completion and to
specific qualifications expressed by the Construction Manager or Architect.
§9.4.6 The issuance of a separate Certificate for Payment or a Project Certificate for Payment will not be
a representation that the Construction Manager or Architect has (1)made exhaustive or continuous on-site
inspections to check the quality or quantity of the Work,(2)reviewed the Contractor's construction means,
methods, techniques, sequences or procedures, (3) reviewed copies of requisitions received from
Subcontractors and material suppliers and other data requested by the Owner to substantiate the
Contractor's right to payment or(4)made examination to ascertain how or for what purpose the Contractor
has used money previously paid on account of the Contract Sum.
§9.5 Decisions to Withhold Certification
§ 9.5.1 The Construction Manager or Architect may withhold a Certificate for Payment or Project
Certificate for Payment in whole or in part,to the extent reasonably necessary to protect the Owner, if in
the Construction Manager's or Architect's opinion the representations to the Owner required by Section
9.4.4 and 9.4.5 cannot be made. If the Construction Manager or Architect is unable to certify payment in
the amount of the Application,the Construction Manager will notify the Contractor and Owner as provided
in Section 9.4.1 and 9.4.3.If the Contractor, Construction Manager and Architect cannot agree on a revised
amount,the Architect will promptly issue a Certificate for Payment or a Project Certificate for Payment for
the amount for which the Architect is able to make such representations to the Owner. The Construction
Manager or Architect may also withhold a Certificate for Payment or,because of subsequently discovered
evidence or subsequent observations,may nullify the whole or a part of a Certificate for Payment or Project
Certificate for Payment previously issued, to such extent as may be necessary in the Construction
Manager's or Architect's opinion to protect the Owner from loss for which the Contractor is responsible,
including loss resulting from the acts and omissions described in Section 3.3.2 because of:
.1 defective Work not remedied;
.2 third-party claims filed or reasonable evidence indicating probable filing of such claims unless
security acceptable to the Owner is provided by the Contractor;
.3 failure of the Contractor to make payments properly to Subcontractors or for labor,materials
or equipment;
.4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract
Sum;
.5 damage to the Owner or a separate contractor;
.6 reasonable evidence that the Work will not be completed within the Contract Time, and that
the unpaid balance would not be adequate to cover actual or liquidated damages for the
anticipated delay;or
.7 repeated failure to carry out the Work in accordance with the Contract Documents.
§ 9.5.2 When the above reasons for withholding certification are removed, certification will be made for
amounts previously withheld.
§9.5.3 If the Architect or Construction Manager withholds certification for payment under Section 9.5.1,
the Owner may, at its sole option,issue joint checks to the Contractor and to any Subcontractor or material
or equipment suppliers to whom the Contractor failed to make payment for Work properly performed or
material or equipment suitably delivered. If the Owner makes payments by joint check, the Owner shall
notify the Architect and the Construction Manager and both will reflect such payment on the next Certificate
for Payment.
21
§9.6 Progress Payments
§ 9.6.1 After the Architect has issued a Certificate for Payment or Project Certificate for Payment, the
Owner shall make payment in the manner and within the time provided in the Contract Documents, and
shall so notify the Construction Manager and Architect.
§9.6.2 The Contractor shall pay each Subcontractor,no later than seven days after receipt of payment from
the Owner the amount to which the Subcontractor is entitled,reflecting percentages actually retained from
payments to the Contractor on account of the Subcontractor's portion of the Work. The Contractor shall,
by appropriate agreement with each Subcontractor, require each Subcontractor to make payments to Sub-
Subcontractors in a similar manner.
§9.6.3 The Construction Manager will, on request,furnish to a Subcontractor, if practicable, information
regarding percentages of completion or amounts applied for by the Contractor and action taken thereon by
the Owner, Construction Manager and Architect on account of portions of the Work done by such
Subcontractor.
§ 9.6.4 The Owner has the right to request written evidence from the Contractor that the Contractor has
properly paid Subcontractors and material and equipment suppliers amounts paid by the Owner to the
Contractor for subcontracted Work. If the Contractor fails to furnish such evidence within seven days,the
Owner shall have the right to contact Subcontractors to ascertain whether they have been properly paid.
Neither the Owner, Construction Manager nor Architect shall have an obligation to pay or to see to the
payment of money to a Subcontractor except as may otherwise be required by law.
§9.6.5 Contractor payments to material and equipment suppliers shall be treated in a manner similar to that
provided in Sections 9.6.2,9.6.3 and 9.6.4.
§9.6.6 A Certificate for Payment, a progress payment, or partial or entire use or occupancy of the Project
by the Owner shall not constitute acceptance of Work not in accordance with the Contract Documents.
§9.6.7 Unless the Contractor provides the Owner with a payment bond in the full penal sum of the Contract
Sum,payments received by the Contractor for Work properly performed by Subcontractors and suppliers
shall be held by the Contractor for those Subcontractors or suppliers who performed Work or furnished
materials, or both,under contract with the Contractor for which payment was made by the Owner.Nothing
contained herein shall require money to be placed in a separate account and not commingled with money
of the Contractor,shall create any fiduciary liability or tort liability on the part of the Contractor for breach
of trust or shall entitle any person or entity to an award of punitive damages against the Contractor for
breach of the requirements of this provision.
§9.7 Failure of Payment
If the Construction Manager and Architect do not issue a Certificate for Payment or a Project Certificate
for Payment, through no fault of the Contractor, within fourteen days after the Construction Manager's
receipt of the Contractor's Application for Payment, or if the Owner does not pay the Contractor within
seven days after the date established in the Contract Documents the amount certified by the Construction
Manager and Architect or awarded by binding dispute resolution, then the Contractor may, upon seven
additional days' written notice to the Owner, Construction Manager and Architect, stop the Work until
payment of the amount owing has been received. The Contract Time shall be extended appropriately and
the Contract Sum shall be increased by the amount of the Contractor's reasonable costs of shut-down,delay
and start-up,plus interest as provided for in the Contract Documents.
22
§9.8 Substantial Completion
§9.8.1 Substantial Completion is the stage in the progress of the Work when the Work or designated portion
thereof is sufficiently complete in accordance with the Contract Documents so the Owner can occupy or
utilize the Work for its intended use.
§9.8.2 When the Contractor considers that the Work,or a portion thereof which the Owner agrees to accept
separately, is substantially complete, the Contractor shall notify the Construction Manager, and the
Contractor and Construction Manager shall jointly prepare and submit to the Architect a comprehensive list
of items to be completed or corrected prior to final payment. Failure to include an item on such list does
not alter the responsibility of the Contractor to complete all Work in accordance with the Contract
Documents.
§9.8.3 Upon receipt of the list,the Architect,assisted by the Construction Manager,will make an inspection
to determine whether the Work or designated portion thereof is substantially complete. If the Architect's
inspection discloses any item, whether or not included on the list, which is not sufficiently complete in
accordance with the requirements of the Contract Documents so that the Owner can occupy or utilize the
Work or designated portion thereof for its intended use, the Contractor shall, before issuance of the
Certificate of Substantial Completion,complete or correct such item upon notification by the Architect. In
such case,the Contractor shall then submit a request for another inspection by the Architect,assisted by the
Construction Manager,to determine Substantial Completion.
§9.8.4 When the Architect, assisted by the Construction Manager,determines that the Work or designated
portion thereof is substantially complete, the Construction Manager will prepare, and the Construction
Manager and Architect shall execute a Certificate of Substantial Completion that shall establish the date of
Substantial Completion, shall establish responsibilities of the Owner and Contractor for security,
maintenance, heat, utilities, damage to the Work and insurance, and shall fix the time within which the
Contractor shall finish all items on the list accompanying the Certificate. Warranties required by the
Contract Documents shall commence on the date of Substantial Completion of the Work or designated
portion thereof unless otherwise provided in the Certificate of Substantial Completion.
§9.8.5 The Certificate of Substantial Completion shall be submitted to the Owner and Contractor for their
written acceptance of responsibilities assigned to them in such Certificate. Upon such acceptance and
consent of surety,if any,the Owner shall make payment of retainage applying to such Work or designated
portion thereof. Such payment shall be adjusted for Work that is incomplete or not in accordance with the
requirements of the Contract Documents.
§9.9 Partial Occupancy or Use
§ 9.9.1 The Owner may occupy or use any completed or partially completed portion of the Work at any
stage when such portion is designated by separate agreement with the Contractor,provided such occupancy
or use is consented to by the insurer as required under Section 11.3.1.5 and authorized by public authorities
having jurisdiction over the Project. Such partial occupancy or use may commence whether or not the
portion is substantially complete, provided the Owner and Contractor have accepted in writing the
responsibilities assigned to each of them for payments, retainage if any, security, maintenance, heat,
utilities,damage to the Work and insurance,and have agreed in writing concerning the period for correction
of the Work and commencement of warranties required by the Contract Documents. When the Contractor
considers a portion substantially complete,the Contractor and Construction Manager shall jointly prepare
and submit a list to the Architect as provided under Section 9.8.2. Consent of the Contractor to partial
occupancy or use shall not be unreasonably withheld. The stage of the progress of the Work shall be
determined by written agreement between the Owner and Contractor or, if no agreement is reached, by
decision of the Architect after consultation with the Construction Manager.
23
§9.9.2 Immediately prior to such partial occupancy or use,the Owner, Construction Manager, Contractor
and Architect shall jointly inspect the area to be occupied or portion of the Work to be used in order to
determine and record the condition of the Work.
§9.9.3 Unless otherwise agreed upon, partial occupancy or use of a portion or portions of the Work shall
not constitute acceptance of Work not complying with the requirements of the Contract Documents.
§9.10 Final Completion and Final Payment
§9.10.1 Upon completion of the Work,the Contractor shall forward to the Construction Manager a written
notice that the Work is ready for final inspection and acceptance and shall also forward to the Construction
Manager a final Contractor's Application for Payment. Upon receipt, the Construction Manager will
evaluate the completion of Work of the Contractor and then forward the notice and Application,with the
Construction Manager's recommendations,to the Architect who will promptly make such inspection.When
the Architect,finds the Work acceptable under the Contract Documents and the Contract fully performed,
the Construction Manager and Architect will promptly issue a final Certificate for Payment or Project
Certificate for Payment stating that to the best of their knowledge, information and belief,and on the basis
of their on-site visits and inspections,the Work has been completed in accordance with terms and conditions
of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final
Certificate is due and payable. The Construction Manager's and Architect's final Certificate for Payment
or Project Certificate for Payment will constitute a further representation that conditions listed in Section
9.10.2 as precedent to the Contractor's being entitled to final payment have been fulfilled.
§9.10.2 Neither fmal payment nor any remaining retained percentage shall become due until the Contractor
submits to the Architect through the Construction Manager(1)an affidavit that payrolls,bills for materials
and equipment, and other indebtedness connected with the Work for which the Owner or the Owner's
property might be responsible or encumbered (less amounts withheld by Owner) have been paid or
otherwise satisfied,(2)a certificate evidencing that insurance required by the Contract Documents to remain
in force after final payment is currently in effect and will not be canceled or allowed to expire until at least
30 days'prior written notice has been given to the Owner,(3)a written statement that the Contractor knows
of no substantial reason that the insurance will not be renewable to cover the period required by the Contract
Documents, (4) consent of surety, if any, to final payment and (5), if required by the Owner, other data
establishing payment or satisfaction of obligations, such as receipts, releases and waivers of liens, claims,
security interests or encumbrances arising out of the Contract, to the extent and in such form as may be
designated by the Owner. If a Subcontractor refuses to furnish a release or waiver required by the Owner,
the Contractor may furnish a bond satisfactory to the Owner to indemnify the Owner against such lien. If
such lien remains unsatisfied after payments are made,the Contractor shall refund to the Owner all money
that the Owner may be compelled to pay in discharging such lien, including all costs and reasonable
attorneys'fees.
§9.10.3 If,after Substantial Completion of the Work,fmal completion thereof is materially delayed through
no fault of the Contractor or by issuance of Change Orders affecting final completion,and the Construction
Manager and Architect so confirm, the Owner shall,upon application by the Contractor and certification
by the Construction Manager and Architect, and without terminating the Contract, make payment of the
balance due for that portion of the Work fully completed and accepted.If the remaining balance for Work
not fully completed or corrected is less than retainage stipulated in the Contract Documents, and if bonds
have been furnished, the written consent of surety to payment of the balance due for that portion of the
Work fully completed and accepted shall be submitted by the Contractor to the Architect through the
Construction Manager prior to certification of such payment. Such payment shall be made under terms and
conditions governing fmal payment, except that it shall not constitute a waiver of Claims.
24
§9.10.4 The making of final payment shall constitute a waiver of Claims by the Owner except those arising
from
.1 liens,Claims,security interests or encumbrances arising out of the Contract and unsettled;
.2 failure of the Work to comply with the requirements of the Contract Documents;or
.3 terms of special warranties required by the Contract Documents.
§9.10.5 Acceptance of final payment by the Contractor,a Subcontractor or material supplier shall constitute
a waiver of claims by that payee except those previously made in writing and identified by that payee as
unsettled at the time of final Application for Payment.
ARTICLE 10 PROTECTION OF PERSONS AND PROPERTY
§ 10.1 Safety Precautions and Programs
The Contractor shall be responsible for initiating,maintaining and supervising all safety precautions and
programs in connection with the performance of the Contract.The Contractor shall submit the Contractor's
safety program to the Construction Manager for review and coordination with the safety programs of other
Contractors. The Construction Manager's responsibilities for review and coordination of safety programs
shall not extend to direct control over or charge of the acts or omissions of the Contractors, Subcontractors,
agents or employees of the Contractors or Subcontractors, or any other persons performing portions of the
Work and not directly employed by the Construction Manager.
§ 10.2 Safety of Persons and Property
§ 10.2.1 The Contractor shall take reasonable precautions for safety of, and shall provide reasonable
protection to prevent damage, injury or loss to:
.1 employees on the Work and other persons who may be affected thereby;
.2 the Work, materials and equipment to be incorporated therein, whether in storage on or off
the site, under care, custody or control of the Contractor or the Contractor's Subcontractors
or Sub-Subcontractors;
.3 other property at the site or adjacent thereto, such as trees, shrubs, lawns,walks,pavements,
roadways,structures and utilities not designated for removal,relocation or replacement in the
course of construction; and
.4 construction or operations by the Owner or other Contractors.
§ 10.2.2 The Contractor shall comply with and give notices required by applicable laws, statutes,
ordinances,codes,rules and regulations and lawful orders of public authorities bearing on safety of persons
or property or their protection from damage,injury or loss.
§10.2.3 The Contractor shall erect and maintain,as required by existing conditions and performance of the
Contract, reasonable safeguards for safety and protection, including posting danger signs and other
warnings against hazards,promulgating safety regulations and notifying owners and users of adjacent sites
and utilities.
§ 10.2.4 When use or storage of explosives or other hazardous materials or equipment or unusual methods
are necessary for execution of the Work, the Contractor shall exercise utmost care and carry on such
activities under supervision of properly qualified personnel.
§ 10.2.5 The Contractor shall promptly remedy damage and loss (other than damage or loss insured under
property insurance required by the Contract Documents) to property referred to in Sections 10.2.1.2,
10.2.1.3 and 10.2.1.4 caused in whole or in part by the Contractor, a Subcontractor, a Sub-Subcontractor,
or anyone directly or indirectly employed by any of them, or by anyone for whose acts they may be liable
and for which the Contractor is responsible under Sections 10.2.1.2, 10.2.1.3 and 10.2.1.4,except damage
25
or loss attributable to acts or omissions of the Owner,Construction Manager or Architect or anyone directly
or indirectly employed by any of them, or by anyone for whose acts any of them may be liable, and not
attributable to the fault or negligence of the Contractor. The foregoing obligations of the Contractor are in
addition to the Contractor's obligations under Section 3.18.
§ 10.2.6 The Contractor shall designate a responsible member of the Contractor's organization at the site
whose duty shall be the prevention of accidents. This person shall be the Contractor's superintendent unless
otherwise designated by the Contractor in writing to the Owner, Construction Manager and Architect.
§ 10.2.7 The Contractor shall not permit any part of the construction or site to be loaded so as to cause
damage or create an unsafe condition.
§ 10.2.8 Injury or Damage to Person or Property
If either party suffers injury or damage to person or property because of an act or omission of the other
party,or of others for whose acts such party is legally responsible,written notice of such injury or damage,
whether or not insured, shall be given to the other party within a reasonable time not exceeding 21 days
after discovery. The notice shall provide sufficient detail to enable the other party to investigate the matter.
§ 10.3 Hazardous Materials
§ 10.3.1 The Contractor is responsible for compliance with any requirements included in the Contract
Documents regarding hazardous materials.If the Contractor encounters a hazardous material or substance
not addressed in the Contract Documents and if reasonable precautions will be inadequate to prevent
foreseeable bodily injury or death to persons resulting from a material or substance, including but not
limited to, asbestos or polychlorinated biphenyl (PCB),encountered on the site by the Contractor, the
Contractor shall,upon recognizing the condition,immediately stop Work in the affected area and report the
condition to the Owner, Construction Manager and Architect in writing.
§ 10.3.2 Upon receipt of the Contractor's written notice,the Owner shall obtain the services of a licensed
laboratory to verify a presence or absence of the material or substance reported by the Contractor and, in
the event such material or substance is found to be present, to cause it to be rendered harmless. Unless
otherwise required by the Contract Documents, the Owner shall furnish in writing to the Contractor,
Construction Manager and Architect the names and qualifications of persons or entities who are to perform
tests verifying the presence or absence of such material or substance or who are to perform the task of
removal or safe containment of such material or substance. The Contractor,the Construction Manager and
the Architect will promptly reply to the Owner in writing stating whether or not any of them has reasonable
objection to the persons or entities proposed by the Owner. If the Contractor, Construction Manager or
Architect has an objection to a person or entity proposed by the Owner,the Owner shall propose another to
whom the Contractor,the Construction Manager and the Architect have no reasonable objection. When the
material or substance has been rendered harmless, Work in the affected area shall resume upon written
agreement of the Owner and Contractor. By Change Order, the Contract Time shall be extended
appropriately and the Contract Sum shall be increased in the amount of the Contractor's reasonable
additional costs of shut-down,delay and start-up.
§10.3.3 To the fullest extent permitted by law,the Owner shall indemnify and hold harmless the Contractor,
Subcontractors, Construction Manager, Architect, their consultants, and agents and employees of any of
them from and against claims, damages, losses and expenses, including but not limited to attorneys' fees,
arising out of or resulting from performance of the Work in the affected area if in fact the material or
substance presents the risk of bodily injury or death as described in Section 10.3.1 and has not been rendered
harmless, provided that such claim, damage, loss or expense is attributable to bodily injury, sickness,
disease or death, or to injury to or destruction of tangible property(other than the Work itself), except to
the extent that such damage,loss or expense is due to the fault or negligence of the party seeking indemnity.
26
§ 10.3.4 The Owner shall not be responsible under this Section 10.3 for materials or substances the
Contractor brings to the site unless such materials or substances are required by the Contract Documents.
The Owner shall be responsible for materials or substances required by the Contract Documents,except to
the extent of the Contractor's fault or negligence in the use and handling of such materials or substances.
§ 10.3.5 The Contractor shall indemnify the Owner for the cost and expense the Owner incurs (1) for
remediation of a material or substance the Contractor brings to the site and negligently handles,or(2)where
the Contractor fails to perform its obligations under Section 10.3.1, except to the extent that the cost and
expense are due to the Owner's fault or negligence.
§ 10.3.6 If,without negligence on the part of the Contractor,the Contractor is held liable by a government
agency for the cost of remediation of a hazardous material or substance solely by reason of performing
Work as required by the Contract Documents, the Owner shall indemnify the Contractor for all cost and
expense thereby incurred.
§ 10.4 Emergencies
In an emergency affecting safety of persons or property, the Contractor shall act, at the Contractor's
discretion, to prevent threatened damage, injury or loss. Additional compensation or extension of time
claimed by the Contractor on account of an emergency shall be determined as provided in Article 15 and
Article 7.
ARTICLE 11 INSURANCE AND BONDS
§ 11.1 Contractor's Liability Insurance
§ 11.1.1 The Contractor shall purchase from and maintain in a company or companies lawfully authorized
to do business in the jurisdiction in which the Project is located such insurance as will protect the Contractor
from claims set forth below which may arise out of or result from the Contractor's operations and completed
operations under the Contract and for which the Contractor may be legally liable,whether such operations
be by the Contractor or by a Subcontractor or by anyone directly or indirectly employed by any of them,or
by anyone for whose acts any of them may be liable:
.1 Claims under workers' compensation, disability benefit and other similar employee benefit
acts which are applicable to the Work to be performed;
.2 Claims for damages because of bodily injury,occupational sickness or disease,or death of the
Contractor's employees;
.3 Claims for damages because of bodily injury,sickness or disease,or death of any person other
than the Contractor's employees;
.4 Claims for damages insured by usual personal injury liability coverage;
.5 Claims for damages, other than to the Work itself, because of injury to or destruction of
tangible property,including loss of use resulting therefrom;
.6 Claims for damages because of bodily injury, death of a person or property damage arising
out of ownership,maintenance or use of a motor vehicle;and
.7 Claims for bodily injury or property damage arising out of completed operations; and
.8 Claims involving contractual liability insurance applicable to the Contractor's obligations
under Section 3.18.
Insurance will be required in the following amounts:
• Commercial General Liability
o $1,000,000 aggregate or
o $600,000 per occurrence
• Automobile Liability
27
o $600,000 aggregate or
o $500,000 for personal injury and
o S100,000 for property damage
• Workers Compensation
o Statutory Limits
§ 11.1.2 The insurance required by Section 11.1.1 shall be written for not less than limits of liability
specified in the Contract Documents or required by law,whichever coverage is greater.Coverages,whether
written on an occurrence or claims-made basis, shall be maintained without interruption from the date of
commencement of the Work until the date of fmal payment and termination of any coverage required to be
maintained after final payment and, with respect to the Contractor's completed operations coverage, until
the expiration of the period for correction of Work or for such other period for maintenance of completed
operations coverage as specified in the Contract Documents.
§ 11.1.3 Certificates of insurance acceptable to the Owner shall be submitted to the Construction Manager
for transmittal to the Owner with a copy to the Architect prior to commencement of the Work and thereafter
upon renewal or replacement of each required policy of insurance. These certificates and the insurance
policies required by this Section 11.1 shall contain a provision that coverages afforded under the policies
will not be canceled or allowed to expire until at least 30 days' prior written notice has been given to the
Owner. An additional certificate evidencing continuation of liability coverage, including coverage for
completed operations, shall be submitted with the final Application for Payment as required by Section
9.10.2 and thereafter upon renewal or replacement of such coverage until the expiration of the time required
by Section 11.1.2.Information concerning reduction of coverage shall be furnished by the Contractor with
reasonable promptness.
§ 11.1.4 The Contractor shall cause the commercial liability coverage required by the Contract Documents
to include(1)the Construction Manager,the Construction Manager's consultants,the Owner,the Architect,
and the Architect's consultants as additional insureds for claims caused in whole or in part by the
Contractor's negligent acts or omissions during the Contractor's operations; and (2) the Owner as an
additional insured for claims caused in whole or in part by the Contractor's negligent acts or omissions
during the Contractor's completed operations.
§ 11.2 Owner's Liability Insurance
The Owner is a self-insured home-rule municipality and will maintain insurance requirements as such.
§ 11.3 Property Insurance
§ 11.3.1 Unless otherwise provided, the Owner may, at the Owner's option, purchase and maintain, in a
company or companies lawfully authorized to do business in the jurisdiction in which the Project is located,
property insurance written on a builder's risk"all risk"or equivalent policy form in the amount of the initial
Contract Sum, plus value of subsequent Contract modifications and cost of materials supplied or installed
by others, comprising total value for the entire Project at the site on a replacement cost basis without
optional deductibles. Such property insurance will be maintained,unless otherwise provided in the Contract
Documents or otherwise agreed in writing by all persons and entities who are beneficiaries of such
insurance,until final payment has been made as provided in Section 9.10 or until no person or entity other
than the Owner has an insurable interest in the property required by this Section 11.3 to be covered,
whichever is later.
§ 11.3.1.1 Property insurance, if Owner chooses to provide, shall be on an"all-risk"or equivalent policy
form and shall include,without limitation,insurance against the perils of fire(with extended coverage)and
physical loss or damage including,without duplication of coverage, theft,vandalism, malicious mischief,
28
collapse, earthquake, flood, windstorm, falsework, testing and startup, temporary buildings and debris
removal including demolition occasioned by enforcement of any applicable legal requirements, and shall
cover reasonable compensation for the Architect's,Contractor's,and Construction Manager's services and
expenses required as a result of such insured loss.
§ 11.3.1.2 If the Owner does not intend to purchase such property insurance required by the Contract and
with all of the coverages in the amount described above,the Owner shall so inform the Contractor in writing
prior to commencement of the Work. The Contractor may then effect insurance that will protect the interests
of the Contractor, Subcontractors and Sub-Subcontractors in the Work, and by appropriate Change Order
the cost thereof shall be charged to the Owner.
§ 11.3.1.3 If the property insurance requires deductibles,the Owner shall pay costs not covered because of
such deductibles.
§ 11.3.1.4 This property insurance shall cover portions of the Work stored off the site,and also portions of
the Work in transit.
§ 11.3.1.5 Partial occupancy or use in accordance with Section 9.9 shall not commence until the insurance
company or companies providing property insurance have consented to such partial occupancy or use by
endorsement or otherwise. The Owner and the Contractor shall take reasonable steps to obtain consent of
the insurance company or companies and shall,without mutual written consent,take no action with respect
to partial occupancy or use that would cause cancellation, lapse or reduction of insurance.
§ 11.3.2 Boiler and Machinery Insurance. The Contractor shall purchase and maintain boiler and
machinery insurance required by the Contract Documents or by law, which shall specifically cover such
insured objects during installation and until final acceptance by the Owner; this insurance shall include
interests of the Owner, Construction Manager, Contractor, Subcontractors and Sub-Subcontractors in the
Work,and the Owner and Contractor shall be named insureds.
§ 11.3.3 Loss of Use Insurance. The Owner, at the Owner's option, may purchase and maintain such
insurance as will insure the Owner against loss of use of the Owner's property due to fire or other hazards,
however caused.The Owner waives all rights of action against the Contractor for loss of use of the Owner's
property,including consequential losses due to fire or other hazards however caused.
§ 11.3.4 If the Contractor requests in writing that insurance for risks other than those described herein or
other special causes of loss be included in the property insurance policy,the Owner shall,if possible,include
such insurance, and the cost thereof shall be charged to the Contractor by appropriate Change Order.
§ 11.3.5 If during the Project construction period the Owner insures properties, real or personal or both,
adjoining or adjacent to the site by property insurance under policies separate from those insuring the
Project, or if after final payment property insurance is to be provided on the completed Project through a
policy or policies other than those insuring the Project during the construction period,the Owner shall waive
all rights in accordance with the terms of Section 11.3.7 for damages caused by fire or other causes of loss
covered by this separate property insurance. All separate policies shall provide this waiver of subrogation
by endorsement or otherwise.
§ 11.3.6 Before an exposure to loss may occur, the Owner shall file with the Contractor a copy of each
policy that includes insurance coverages required by this Section 11.3. Each policy shall contain all
generally applicable conditions, definitions, exclusions and endorsements related to this Project. Each
policy shall contain a provision that the policy will not be canceled or allowed to expire, and that its limits
will not be reduced,until at least 30 days'prior written notice has been given to the Contractor.
29
§ 11.4 Performance Bond and Payment Bond
§ 11.4.1 The Owner shall require the Contractor to furnish bonds covering faithful performance of the
Contract and payment of obligations arising thereunder as stipulated in bidding requirements or specifically
required in the Contract Documents on the date of execution of the Contract.
§ 11.4.2 Upon the request of any person or entity appearing to be a potential beneficiary of bonds covering
payment of obligations arising under the Contract,the Contractor shall promptly furnish a copy of the bonds
or shall authorize a copy to be furnished.
ARTICLE 12 UNCOVERING AND CORRECTION OF WORK
§ 12.1 Uncovering of Work
§ 12.1.1 If a portion of the Work is covered contrary to the Construction Manager's or Architect's request
or to requirements specifically expressed in the Contract Documents, it must, if requested in writing by
either, be uncovered for their observation and be replaced at the Contractor's expense without change in
the Contract Time.
§ 12.1.2 If a portion of the Work has been covered which the Construction Manager or Architect has not
specifically requested to observe prior to its being covered, the Construction Manager or Architect may
request to see such Work and it shall be uncovered by the Contractor. If such Work is in accordance with
the Contract Documents, costs of uncovering and replacement shall, by appropriate Change Order, be at
the Owner's expense. If such Work is not in accordance with the Contract Documents, such costs and the
cost of correction shall be at the Contractor's expense unless the condition was caused by the Owner or one
of the other Contractors in which event the Owner shall be responsible for payment of such costs.
§ 12.2 Correction of Work
§ 12.2.1 Before or After Substantial Completion
The Contractor shall promptly correct Work rejected by the Construction Manager or Architect or failing
to conform to the requirements of the Contract Documents,whether discovered before or after Substantial
Completion and whether or not fabricated,installed or completed. Costs of correcting such rejected Work,
including additional testing and inspections,the cost of uncovering and replacement,and compensation for
the Construction Manager's and Architect's services and expenses made necessary thereby, shall be at the
Contractor's expense.
§ 12.2.2 After Substantial Completion
§ 12.2.2.1 In addition to the Contractor's obligations under Section 3.5,if,within one year after the date of
Substantial Completion of the Work or designated portion thereof, or after the date for commencement of
warranties established under Section 9.9.1, or by terms of an applicable special warranty required by the
Contract Documents,any of the Work is found to be not in accordance with the requirements of the Contract
Documents,the Contractor shall correct it promptly after receipt of written notice from the Owner to do so,
unless the Owner has previously given the Contractor a written acceptance of such condition. The Owner
shall give such notice promptly after discovery of the condition.During the one-year period for correction
of Work, if the Owner fails to notify the Contractor and give the Contractor an opportunity to make the
correction, the Owner waives the rights to require correction by the Contractor and to make a claim for
breach of warranty.If the Contractor fails to correct nonconforming Work within a reasonable time during
that period after receipt of notice from the Owner or Architect,the Owner may correct it in accordance with
Section 2.4.
30
§ 12.2.2.2 The one-year period shall be extended with respect to portions of Work first performed after
Substantial Completion by the period of time between Substantial Completion and the actual completion
of that portion of the Work.
§12.2.2.3 The one-year period for correction of Work shall not be extended by corrective Work performed
by the Contractor pursuant to this Section 12.2.
§12.2.3 The Contractor shall remove from the site portions of the Work that are not in accordance with the
requirements of the Contract Documents and are neither corrected by the Contractor nor accepted by the
Owner.
§ 12.2.4 The Contractor shall bear the cost of correcting destroyed or damaged construction, whether
completed or partially completed, of the Owner or separate contractors or other Multiple Prime Contractors
caused by the Contractor's correction or removal of Work that is not in accordance with the requirements
of the Contract Documents.
§ 12.2.5 Nothing contained in this Section 12.2 shall be construed to establish a period of limitation with
respect to other obligations the Contractor has under the Contract Documents. Establishment of the one-
year period for correction of Work as described in Section 12.2.2 relates only to the specific obligation of
the Contractor to correct the Work,and has no relationship to the time within which the obligation to comply
with the Contract Documents may be sought to be enforced,nor to the time within which proceedings may
be commenced to establish the Contractor's liability with respect to the Contractor's obligations other than
specifically to correct the Work.
§ 12.3 Acceptance of Nonconforming Work
If the Owner prefers to accept Work that is not in accordance with the requirements of the Contract
Documents,the Owner may do so instead of requiring its removal and correction,in which case the Contract
Sum will be reduced as appropriate and equitable. Such adjustment shall be effected whether or not fmal
payment has been made.
ARTICLE 13 MISCELLANEOUS PROVISIONS
§ 13.1 Governing Law
The Contract shall be governed by the laws of the State of Texas with exclusive jurisdiction in Wichita
County.
§ 13.2 Successors and Assigns
§ 13.2.1 The Owner and Contractor respectively bind themselves, their partners, successors, assigns and
legal representatives to covenants, agreements and obligations contained in the Contract Documents.
Except as provided in Section 13.2.2, neither party to the Contract shall assign the Contract as a whole
without written consent of the other. If either party attempts to make such an assignment without such
consent,that party shall nevertheless remain legally responsible for all obligations under the Contract.
§ 13.2.2 The Owner may, without consent of the Contractor, assign the Contract to a lender providing
construction financing for the Project, if the lender assumes the Owner's rights and obligations under the
Contract Documents. The Contractor shall execute all consents reasonably required to facilitate such
assignment.
§ 13.3 Written Notice
Written notice shall be deemed to have been duly served if delivered in person to the individual,to a member
of the firm or entity or to an officer of the corporation for which it was intended; or if delivered at or sent
31
by registered or certified mail or by courier service providing proof of delivery to,the last business address
known to the party giving notice.
§ 13.4 Rights and Remedies
§ 13.4.1 Duties and obligations imposed by the Contract Documents and rights and remedies available
thereunder shall be in addition to and not a limitation of duties, obligations,rights and remedies otherwise
imposed or available by law.
§ 13.4.2 No action or failure to act by the Owner, Construction Manager, Architect or Contractor shall
constitute a waiver of a right or duty afforded them under the Contract, nor shall such action or failure to
act constitute approval of or acquiescence in a breach thereunder, except as may be specifically agreed in
writing.
§ 13.5 Tests and Inspections
§13.5.1 Tests,inspections and approvals of portions of the Work shall be made as required by the Contract
Documents and by applicable laws, statutes, ordinances, codes, rules and regulations or lawful orders of
public authorities. Unless otherwise provided, the Contractor shall make arrangements for such tests,
inspections and approvals with an independent testing laboratory or entity acceptable to the Owner,or with
the appropriate public authority, and shall bear all related costs of tests, inspections and approvals. The
Contractor shall give the Construction Manager and Architect timely notice of when and where tests and
inspections are to be made so that the Construction Manager and Architect may be present for such
procedures. The Owner shall bear costs of (1) tests, inspections or approvals that do not become
requirements until after bids are received or negotiations concluded,and(2)tests,inspections or approvals
where building codes or applicable laws or regulations prohibit the Owner from delegating its cost to the
Contractor.
§ 13.5.2 If the Construction Manager,Architect,Owner or public authorities having jurisdiction determine
that portions of the Work require additional testing, inspection or approval not included under Section
13.5.1,the Construction Manager and Architect will,upon written authorization from the Owner, instruct
the Contractor to make arrangements for such additional testing, inspection or approval by an entity
acceptable to the Owner, and the Contractor shall give timely notice to the Construction Manager and
Architect of when and where tests and inspections are to be made so that the Construction Manager and
Architect may be present for such procedures. Such costs,except as provided in Section 13.5.3, shall be at
the Owner's expense.
§ 13.5.3 If such procedures for testing, inspection or approval under Sections 13.5.1 and 13.5.2 reveal
failure of the portions of the Work to comply with requirements established by the Contract Documents,all
costs made necessary by such failure including those of repeated procedures and compensation for the
Construction Manager's and Architect's services and expenses shall be at the Contractor's expense.
§ 13.5.4 Required certificates of testing, inspection or approval shall, unless otherwise required by the
Contract Documents,be secured by the Contractor and promptly delivered to the Construction Manager for
transmittal to the Architect.
§ 13.5.5 If the Construction Manager or Architect is to observe tests,inspections or approvals required by
the Contract Documents,the Construction Manager or Architect will do so promptly and,where practicable,
at the normal place of testing.
§ 13.5.6 Tests or inspections conducted pursuant to the Contract Documents shall be made promptly to
avoid unreasonable delay in the Work.
32
§ 13.6 Interest
Payments due and unpaid under the Contract Documents shall bear interest from the date payment is due
at such rate as the parties may agree upon in writing or, in the absence thereof, at the legal rate prevailing
from time to time at the place where the Project is located.
§ 13.7 Time Limits on Claims
The Owner and the Contractor shall commence all claims and causes of action,whether in contract, tort,
breach of warranty or otherwise, against the other arising out of or related to the Contract in accordance
with the requirements of the final dispute resolution method selected in the Agreement within the time
period specified by applicable law, but in any case not more than 10 years after the date of Substantial
Completion of the Work. The Owner and the Contractor waive all claims and causes of action not
commenced in accordance with this Section 13.7.
ARTICLE 14 TERMINATION OR SUSPENSION OF THE CONTRACT
§ 14.1 Termination by the Contractor
§ 14.1.1 The Contractor may terminate the Contract if the Work is stopped for a period of 30 consecutive
days through no act or fault of the Contractor or a Subcontractor, Sub-Subcontractor or their agents or
employees or any other persons or entities performing portions of the Work under direct or indirect contract
with the Contractor,for any of the following reasons:
.1 Issuance of an order of a court or other public authority having jurisdiction that requires all
Work to be stopped;
.2 An act of government, such as a declaration of national emergency that requires all Work to
be stopped;
.3 Because the Construction Manager has not certified or the Architect has not issued a
Certificate for Payment and has not notified the Contractor of the reason for withholding
certification as provided in Section 9.4, or because the Owner has not made payment on a
Certificate for Payment within the time stated in the Contract Documents;or
.4 The Owner has failed to furnish to the Contractor promptly, upon the Contractor's request,
reasonable evidence as required by Section 2.2.1.
§ 14.1.2 The Contractor may terminate the Contract if, through no act or fault of the Contractor or a
Subcontractor, Sub-Subcontractor or their agents or employees or any other persons or entities performing
portions of the Work under direct or indirect contract with the Contractor,repeated suspensions, delays or
interruptions of the entire Work by the Owner as described in Section 14.3 constitute in the aggregate more
than 100 percent of the total number of days scheduled for completion, or 120 days in any 365-day period,
whichever is less.
§ 14.1.3 If one of the reasons described in Section 14.1.1 or 14.1.2 exists,the Contractor may,upon seven
days'written notice to the Owner,Construction Manager and Architect,terminate the Contract and recover
from the Owner payment for Work executed, including reasonable overhead and profit, costs incurred by
reason of such termination,and damages.
§14.1.4 If the Work is stopped for a period of 60 consecutive days through no act or fault of the Contractor
or a Subcontractor or their agents or employees or any other persons performing portions of the Work under
contract with the Contractor because the Owner has repeatedly failed to fulfill the Owner's obligations
under the Contract Documents with respect to matters important to the progress of the Work,the Contractor
may, upon seven additional days' written notice to the Owner, Construction Manager and Architect,
terminate the Contract and recover from the Owner as provided in Section 14.1.3.
33
§ 14.2 Termination by the Owner for Cause
§ 14.2.1 The Owner may terminate the Contract if the Contractor:
.1 repeatedly refuses or fails to supply enough properly skilled workers, proper equipment, or
proper materials;
.2 fails to make payment to Subcontractors for materials or labor in accordance with the
respective agreements between the Contractor and the Subcontractors;
.3 repeatedly disregards applicable laws, statutes, ordinances, codes, rules and regulations, or
lawful orders of a public authority;
.4 substantial evidence that Contractor has abandoned the work or discontinued the performance
of the work and failure to resume performance within a reasonable time after notice to do;
.5 substantial evidence that the Contractor has become insolvent or bankrupt, or otherwise
financially unable to carry on the work;
.6 failure of the Contractor to promptly make good any defects in materials or workmanship, or
any defects of any nature,the correction of which has been directed in writing by the Owner;
.7 repeated and flagrant violations of safe working procedures;
.8 the filing by Contractor of litigation against the Owner prior to final completion of the work;
or
.9 otherwise is guilty of substantial breach of a provision of the Contract Documents.
§14.2.2 When any of the above reasons exist,the Owner,after consultation with the Construction Manager,
and upon certification by the Initial Decision Maker that sufficient cause exists to justify such action,may
without prejudice to any other rights or remedies of the Owner and after giving the Contractor and the
Contractor's surety, if any, seven days' written notice, terminate employment of the Contractor and may,
subject to any prior rights of the surety:
.1 exclude the Contractor from the site and take possession of all materials, equipment, tools,
and construction equipment and machinery thereon owned by the Contractor;
.2 accept assignment of subcontracts pursuant to Section 5.4;and
.3 finish the Work by whatever reasonable method the Owner may deem expedient. Upon
written request of the Contractor, the Owner shall furnish to the Contractor a detailed
accounting of the costs incurred by the Owner in finishing the Work.
§ 14.2.3 When the Owner terminates the Contract for one of the reasons stated in Section 14.2.1, the
Contractor shall not be entitled to receive further payment until the Work is fmished.
§ 14.2.4 If the unpaid balance of the Contract Sum exceeds costs of finishing the Work, including
compensation for the Construction Manager's and Architect's services and expenses made necessary
thereby, and other damages incurred by the Owner and not expressly waived, such excess shall be paid to
the Contractor.If such costs and damages exceed the unpaid balance,the Contractor shall pay the difference
to the Owner.The amount to be paid to the Contractor or Owner,as the case may be,shall,upon application,
be certified by the Initial Decision Maker after consultation with the Construction Manager, and this
obligation for payment shall survive termination of the Contract.
§ 14.3 Suspension by the Owner for Convenience
§ 14.3.1 The Owner may,without cause, order the Contractor in writing to suspend, delay or interrupt the
Work in whole or in part for such period of time as the Owner may determine.
§14.3.2 The Contract Sum and the Contract Time shall be adjusted for increases in the cost and time caused
by suspension, delay or interruption as described in Section 14.3.1. Adjustment of the Contract Sum shall
include profit.No adjustment shall be made to the extent:
.1 that performance is,was or would have been so suspended,delayed or interrupted by another
cause for which the Contractor is responsible;or
34
.2 that an equitable adjustment is made or denied under another provision of this Contract.
§ 14.4 Termination by the Owner for Convenience
§ 14.4.1 The Owner may, at any time, terminate the Contract for the Owner's convenience and without
cause.
§ 14.4.2 Upon receipt of written notice from the Owner of such termination for the Owner's convenience,
the Contractor shall:
.1 cease operations as directed by the Owner in the notice;
.2 take actions necessary, or that the Owner may direct, for the protection and preservation of
the Work; and
.3 except for Work directed to be performed prior to the effective date of termination stated in
the notice, terminate all existing subcontracts and purchase orders and enter into no further
subcontracts and purchase orders.
§14.4.3 In case of such termination for the Owner's convenience,the Contractor shall be entitled to receive
payment for Work executed, and costs incurred by reason of such termination, along with reasonable
overhead and profit on the Work not executed.
ARTICLE 15 CLAIMS AND DISPUTES
§ 15.1 Claims
§ 15.1.1 Definition. A Claim is a demand or assertion by one of the parties seeking, as a matter of right,
payment of money,or other relief with respect to the terms of the Contract.The term"Claim"also includes
other disputes and matters in question between the Owner and Contractor arising out of or relating to the
Contract The responsibility to substantiate Claims shall rest with the party making the Claim.
§ 15.1.2 Notice of Claims. Claims by either the Owner or Contractor must be initiated by written notice to
the other party and to the Initial Decision Maker with a copy sent to the Construction Manager and
Architect,if the Construction Manager and or Architect is not serving as the Initial Decision Maker.Claims
by either party must be initiated within 21 days after occurrence of the event giving rise to such Claim or
within 21 days after the claimant first recognizes the condition giving rise to the Claim,whichever is later.
§ 15.1.3 Continuing Contract Performance. Pending final resolution of a Claim, except as otherwise
agreed in writing or as provided in Section 9.7 and Article 14,the Contractor shall proceed diligently with
performance of the Contract and the Owner shall continue to make payments in accordance with the
Contract Documents.The Construction Manager will prepare Change Orders and the Architect will issue a
Certificate for Payment or Project Certificate for Payment in accordance with the decisions of the Initial
Decision Maker.
§ 15.1.4 Claims for Additional Cost. If the Contractor wishes to make a Claim for an increase in the
Contract Sum,written notice as provided herein shall be given before proceeding to execute the Work.Prior
notice is not required for Claims relating to an emergency endangering life or property arising under Section
10.3.
§ 15.1.5 Claims for Additional Time
§ 15.1.5.1 If the Contractor wishes to make a Claim for an increase in the Contract Time,written notice as
provided herein shall be given. The Contractor's Claim shall include an estimate of cost and of probable
effect of delay on progress of the Work.In the case of a continuing delay only one Claim is necessary.
35
§ 15.1.5.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be
documented by data substantiating that weather conditions were abnormal for the period of time,could not
have been reasonably anticipated and had an adverse effect on the scheduled construction.
§ 15.1.6 Claims for Consequential and Exemplary Damages. The Contractor and Owner waive Claims
against each other for consequential damages arising out of or relating to this Contract. This mutual waiver
includes:
.1 damages incurred by the Owner for rental expenses, for losses of use, income, profit,
financing, business and reputation, and for loss of management or employee productivity or
of the services of such persons; and
.2 damages incurred by the Contractor for principal office expenses including the compensation
of personnel stationed there, for losses of fmancing,business and reputation, and for loss of
profit except anticipated profit arising directly from the Work.
This mutual waiver is applicable, without limitation, to all consequential damages due to either patty's
termination in accordance with Article 14. Nothing contained in this Section 15.1.6 shall be deemed to
preclude an award of liquidated damages, when applicable, in accordance with the requirements of the
Contract Documents.
§ 15.1.7 Liquidated Damages for Failure to Complete on Time. The time of completion is the essence
of this Contract. For each day that any work shall remain uncompleted after the time specified in the
Contract Documents, or the increased time granted by the Owner, shall be deducted from the money due
the Contractor at a rate of$240 per day.
The sum of money thus deducted for such delay, failure or non-completion is not to be considered as a
penalty but shall be deemed,taken and treated as reasonable liquidated damages,per day that the Contractor
shall be in default after the time stipulated in the Contractor for completing the work. The said amount is
fixed and agreed upon by and between Owner and Contractor because of the impracticability and extreme
difficulty of fixing and ascertaining the actual damages the Owner would sustain and which shall be retained
from the money due, or that may become due,to the Contractor under this Contract; and if such money be
insufficient to cover the amount owing,then the Contractor or its surety shall pay any additional amounts
due.
In the event actual damages incurred by the Owner exceed the amount of liquidated damages, Owner shall
be entitled to recover its actual damages.
§15.1.8 Waiver of Attorneys' Fees.If any action at law or in equity is necessary to enforce this agreement,
each party agrees to pay its own attorneys' fees and will not seek to recover its own attorneys' fees from
the other party. Contractor understands that Texas Local Government Code subchapter I, § 271.153(a)(3)
provides that the total amount of money awarded in an adjudication brought against a governmental entity
for breach of a contract includes attorneys' fees. Both Contractor and the Owner expressly waive all
statutory and other rights to recover attorneys'fees pursuant to in §271.153(a)(3)and all other law.
§ 15.1.9 Waiver of Additional Damages. Contractor acknowledges that Texas Local Government Code
subchapter I, § 271.153(a)(1)provides that the total amount of money awarded in an adjudication brought
against a governmental entity for breach of a contract brought under subchapter I includes any amount owed
as compensation for the increased cost to perform the work as a direct result of Owner-caused delays or
acceleration. Contractor expressly waives its statutory rights as outlined by§271.153(a)(1)and agrees that
it will not seek to recover from Owner any amount owed as compensation for the increased cost to perform
the work as a direct result of Owner-caused delays or acceleration
36
§ 15.2 Initial Decision
§ 15.2.1 Claims, excluding those arising under Sections 10.3, 10.4, 11.3.9,and 11.3.10,shall be referred to
the Initial Decision Maker for initial decision. The Architect will serve as the Initial Decision Maker,unless
otherwise indicated in the Agreement. Except for those Claims excluded by this Section 15.2.1, an initial
decision shall be required as a condition precedent to mediation of any Claim arising prior to the date final
payment is due,unless 30 days have passed after the Claim has been referred to the Initial Decision Maker
with no decision having been rendered.Unless the Initial Decision Maker and all affected parties agree,the
Initial Decision Maker will not decide disputes between the Contractor and persons or entities other than
the Owner.
§ 15.2.2 The Initial Decision Maker will review Claims and within ten days of the receipt of a Claim take
one or more of the following actions:(1)request additional supporting data from the claimant or a response
with supporting data from the other party, (2)reject the Claim in whole or in part, (3) approve the Claim,
(4)suggest a compromise,or(5) advise the parties that the Initial Decision Maker is unable to resolve the
Claim if the Initial Decision Maker lacks sufficient information to evaluate the merits of the Claim or if the
Initial Decision Maker concludes that, in the Initial Decision Maker's sole discretion, it would be
inappropriate for the Initial Decision Maker to resolve the Claim.
§ 15.2.3 In evaluating Claims, the Initial Decision Maker may, but shall not be obligated to, consult with
or seek information from either party or from persons with special knowledge or expertise who may assist
the Initial Decision Maker in rendering a decision. The Initial Decision Maker may request the Owner to
authorize retention of such persons at the Owner's expense.
§ 15.2.4 If the Initial Decision Maker requests a party to provide a response to a Claim or to furnish
additional supporting data, such party shall respond,within ten days after receipt of such request,and shall
either(1)provide a response on the requested supporting data, (2) advise the Initial Decision Maker when
the response or supporting data will be furnished or(3)advise the Initial Decision Maker that no supporting
data will be furnished. Upon receipt of the response or supporting data, if any, the Initial Decision Maker
will either reject or approve the Claim in whole or in part.
§ 15.2.5 The Initial Decision Maker will render an initial decision approving or rejecting the Claim, or
indicating that the Initial Decision Maker is unable to resolve the Claim. This initial decision shall (1)be
in writing; (2) state the reasons therefor; and (3) notify the parties and the Architect and Construction
Manager, if the Architect or Construction Manager is not serving as the Initial Decision Maker, of any
change in the Contract Sum or Contract Time or both. The initial decision shall be final and binding on the
parties but subject to mediation and,if the parties fail to resolve their dispute through mediation,to binding
dispute resolution.
ARTICLE 16 ANTI-BOYCOTT CONTRACT VERIFICATION
§ 16.1 Pursuant to Texas Government Code Chapter 2270, a company providing a good or service
must state by written verification from the company that it: (1)does not boycott Israel; and (2)will
not boycott Israel during the term of the contract.
Verification.
"I, , being over the age of eighteen years and in my official capacity
representing an entity that is a party to this contract with the City of Wichita Falls,hereby swear
and verify under oath:
37
(1) Entity does not boycott Israel; and
(2) Entity will not boycott Israel during the term of this contract."
Signature
38
IN WITNESS WHEREOF,the parties have executed this agreement on the dates indicated below.
City of Wichita Falls Marrs Patriot Construction,LLC
Darron J. Leiker Signature
Printed name
Attest:
City Clerk
Approved as to form:
City Attorney
39
Exhibit A
40
L„.'.'• •'''„‘•„,-% `.1 !
Z
§
g
0
LU▪ Pifli'e n• ! !! ! 14!
''-•-
.e t.
P,', f', .,•':!::.'h!!.5.'
0 1--
z
. . C.}
= >
I__ , 0 ......0..,...., a ff.
_I k....) 0 n
z
LIJ I— i---
0
„ . . • z
LLJ (7) ,
o CC Q6 5
0
t, i'lt; co 0_ 0 <1`4‘1,5 •:'1,-" , '6J
l'
i , Z
. ., .
'-, • i . D
• 0
- 0
4‘,'.', A'14'„:'• '' ' ii. <
i - U • t
I-
-
1
, p
1
. „.
. , .
C.0
_II
/' <
<
„
I—
i,v,6v1iik . =
gWviAnualt; . 0
..,—
v.,
,
i< u
,_.
...I
ltriorsrgr :� xlslid n
.e ' 133als PE DOLL, > >
N
1
4, �� _ N Z O s
oo Q o SEcs+ £_=Q r z4 I uas ;'.I.' NOIlVAONdd dVV
�y Y z� a zF., JZW
al'- , N ps lOR1S10 H11V3H onend o yg i. ° �
', td z o
''7vvuM A1NlOOVIIHOIM-Sl1VJ V.IHOIM V Q ` ,% g L'J> i -Q =
i"9 a u
. -. f
I
W - {.V =
CO W £
V ~
Z Z •:- S o
W o
COI nI w �f'$'w's`
n < W S�Qk�0- p.�
z 0
ix
I
LF
z - `E
o
Eg
m m
a a eb % - 4
e e f - 8 s Vow E � _ I .
1 1 11 1 41 '''''':-.:! '2'1 ..;1 '-' C 4 i.E),1_,,,il ' : ' .1 IT
fa r4 , -a
,
a e
$ u W n5 E. e eE -
I �� o 5 w 'x L d6 � 4 d
E h i. 4aa'�9;a`:m .w Eo4„da dk'4 1E "dgg dL
W G.. _ G1 t4 HME5 4M da'n'sas ES.E3 Ei3y 6 tl 6E 3
_ ., ddd., _ .. 3d PHI/sassn aa'E's E'EMEEEE -,ELSE.»a»a
:1 22d24333.2dd ..-nsanaaW `___,..ua� - F s14a Yhaakaap rc,.a&sndassssssass ..AA9s E#raaffiasi:i&a
< e a r . F n -
W iR
o aY_r �' 3 ;
�,=9 a b z : c 4 L 4
A. ;` . •U� . Sas — " 3 5a 5E5 "5EE g -E ; 1'5 " F "c5- 5 I5 a a 5 4ga E_
V Y ; ZO =.ed a .0 4 R E pp a.Q R 33 I-gmg'S '3 E8 13ses I, I'V 1,tE , e ,' EEa 5E45Eg
a mmxes5 5,555; .5e�,a IEE Iw Pk sa I. Li 15, s a'a 555 Ease'E
H �E's$sa =gyp® ., a ®E iaak,.a. :�:,i: is's2 I$ :.. L<� ,. .._ .-3@.�
Q ssEEEE . .55.5.5.wu E5.1. zze1'so EEEEEE5i@ uk 1 k�33g_ i 55ss 555E5;., oa EEMEEEEE '.8.
> .. ....0 _ .., uuu ..uu uuu ... .. _ .,o��Gd.SL .R444RR� 4£ _mz`z4 -.Y .3Y4 .3y _�.g»> ..,�..
W
m R
m cd h, e40'''ms�rs_ z a14 Q Fe e s 47q
( � d1b1Z 1bi € p9a em a�' git9 9 .a1 s
P 1R k c e 3-sd$.R 2E; w o"0Ea _ s
8
a
q s R q - i asee e ]sF ,e „,� is8 U'm'. I. a =a ri ss? Rx ., IyCY € I �
.a
srneru 0 a,= ..... .1, Ev , dEdEdellEae 2%2 LEEEEE38E 6E24E d8d EE 338 399E, 3 eB dw 1O .... .. .`ee.m.; E.W.k m ;ri.-•: 3am= :m .m _ ai,*E:caacce488aE$ aa6ad4:;rg evo ,:' i;;a . www.a Y
6.'
s
X.L STIVd Vl£.L1H3IM
I '= .LD !of............77.......s.rat. .5 i
.LLI.LS POW.-
<
Q
Tle -..3 I:':''''2'..- 41
t —1 LI
A.. NOLIVAON32:1 dArald ,E1-::,-...3 LI 14 45, 5 8 OIHISICI HI1VRH 011arld
(/)'' ' :. : '' '4
-S11VJ VIIHOIM
'mwvok.;.A—=•• ,u_Nnoa.VilHOIM
—
..j
VaV-SEN rEcune A1111EIISSOOV
- iJ• ,,,:,,
I 0
11 ,
-
11 /A
144..i. '1.* ' il
_i ...', t t, .- .ir• 1' ,,.
,,, ,.,
—t
i
t I
tr.
K!5; ::.-317 e-' eE' "- 'E''!, . 'z''7 '•"; - '.1i..2 L_ .:...L,,, F. , 1 . ,,,' ,i. iPoli..1, ....
tti :Itt.ttPitt.
...,E,. .,.,..- _ .....
, t I _,
, .. 5N.! 5, ;6 - -4-
U. 1 4 'E':
—71 3
i.V. i if - ' .:10,-.;: i a F., -, zi tL ,.„ T. .i. li !.: -„,,. 1--g 2 • - 1. 1 1.
31:- ?; it -- ''. 1:It; 1 t.7; 1-• p :. t 2":.; 't.. 'Yt. :It t t ''' ' -, I. it:', "-,'. f . 1 t.1.:,„
g7.• :'7''' 7.1,11, 1:;::2 !4 '-.5 : 55 'LL t ',- 5 --,. g .:=, 5:, , -55 . ,---.... -'' 2' 'i'it ': ,
ii.' i ‘,U • .t.. .7,- = 3...i.iti 7, .;,, : E" ! it g ; 1 ...v: 2 F- 4".„: !,..:. t-7-L-,ELt
''' 4ii .-1 If-4. ! '''.2 .'-vz a 7 '''',J 9 i '' !.'.'-''' ': F•i;.. 7_2E, .6,'-,'' -,it'7't !,i.2 . '—' .— ']",=ti-'-'7,:',' ', 'it
----
tt6flii1
2,1 7tt
E:.e.' tPlre
E '
tty_.... -.! , ... E a
.,: 1 , i ,..,,t: :i ,.=.. • 1:,:;
• =%t 7 t Ititt
IL: -1Fit. i',E ..1, e
I I,
'
4:
. , , ____ ,
',
- Et
md h.: 71
, i , .._. : .1, 1. .,
, „,, 5 ,
.D.,::.
- . . , -. ,-, _ , ,...,..., - - • = ,-. .. „. _ .„,,_ -, - .;-, ,, , _, . .. , _ _ „-
,
ell
ii 4'
0 E . , AA , L.• i° .g ,, .,.:,, 1 1
- 0 E 1 t il. 2
28 ; I VI i
III
,2„:5 , 1 -. Jel. j ., 7 =.,1 .
,, 7. E “.e4 7'" I '
E ..:., p, ! .-0" ,i 1„LAI I 'I•i .,,i: 1 1
, ., 3-
' ' '11.4 , '.
... . ;:;. . ,... -
-fi.,5 : ` „ , , .., , ,, E _ i, , „,,„ .7: n•
,..e
"i 1 I i 2
E-=, ,
, -7f,t t:v:,l ':€:...,:€ ,:!,;., ,:,+7..! . .,:q€,:e' g33
.:,, :---, .. ,I,-,,2, ,;;;,,,,i,, , , _L
1 0 0
-----_, Xi STIVJVIIHOIM
I
40.16 MN/4N—t:
133H_LSPJ£OOLL
u— P,
e'9 Id,
u,
%k EL(:1 zt
LIt
%, ,,,,g,(4%•97.P 6'00,,=• 1N0O1U1LSVIGA-0HO1.LN1-Y3 36H doVnA IaVnd
.2
.
=
0
mNno3V11- MSl1iVIH3IN 5'2.''.4tt•ii67'..-t e,,t,',F,,,' 3--',:, ,1'.. Lil.'" g (..) ;
vg,y-1— ,g..E.-7-4 E----,..gg c, •-,8 3.2 '3-,.7/ LY,'''•-•""-'15V --, g Er.,•:g, ,`,"' '---
, •-fir.-- — '4 " <4 '.4'
ttt7t.t.,==.==.7,:7,7ZititttEtipt:m....z t
Jawepsu .F._
VCIV-sam-Hainokiniaissoov
1111
i il &II ; 1 i A W I'A ''.:: •,I,, g 1-E ' MEM
d
.WIMII./1 . 111e4
Niro 1 • , . .._ ; 4-, 2 .7,.6.. i N:.;: 3 i 73 l' q ;
z i IN .'.F ..! 7,-- h ,-, ! ! •:-,-,,, ,.E4 i 1 E,..§.A Emil , I ..ti .; i ;it .1. , t ”i i h• 1 .; AI
1 i.-0 t 7:[_ ,I ..- - • ,qi 'i.:=, ; „u:,.. A '3.--PE um - • 2 2 EP F't' tE A. t.; - t.. ' F:. ttt t 9t. I ; EF A
1.0
1 INHENI1.,
., . ..',;,7,: _.•:,,t :.i .'i,, i 7..v.., .4!, E... ;.: :1.• '' :',?.1-F-: ;
', ; .il '. ...;.; Ti .1i' -2', i,':.t; .:%•].:11i i... 21 i ;:li-.!I ii
'': '71 11 E'Eit-'• E12' rIl EN ;22112T '4i '4''' 4 45',33i
i 15JF;
i „,..,E7:t. _. . , , ;; ;,, i 2 7.2 3; 1 i; 1:3T3! ; 2 3:,7', 2',-; .32.• 3. ,, '3', '.,,,, 3 E 1 i i I.4 '''' 'f.3';
E. P33;2- 3
..t.k i. !,....2E
tt .0
:3-,. 4:-! 131.i
2 1:-E:3,4 1'3-73:, i;11!:' ';',:._ i'3Th3 131 i33.T AZ .'-. i.•'7.41',.,41. 'ii. -3 ''.1,3- 3: t . .-.. .:13! -;34:' t::
..=:. .,',,g `-.,, 4E,..,i:V?
'' .' '' '''':': +'E''jR1-- •:''': .:'''l l'r.'4'.2!2'' ',Ai; EE El at EIPIEt Et E .qt.B,-222.22 ,2„22,._2.; 2 ,„,_ „ittuk.622E2r22E,E5; 222, ., 2; . E
Ai
><<El .,m
ts ,.;
',IIMEP:
3 ?r3 2 01 .3 f ., 21 Ii '-;i• ., : 4.,7!. L. ;Ii. '
SdU 3 .33' 1!,. iE •
'L2'1' i .e'' '3.0 '1 _•,_
I. 4 g: ;,-ill i ! „ !II i A Ag •Ai E .11... 2'.„il 1 ti- ;i -;; ; ,A,A '' ,
,,,— ,i.,Zt t .t. 7,t Mit 1 t ' t ' .11 I. i D 1.: tItti. t',0%,,t V, Pi -.€ Ft - 3.s.;22i ...3;ii3,,Attz,3 3r•NE3
07 i , tr,'; .-nt] I id, E 2 AS I, 3 .2 .3; ;, 1.,3_ ..71:33 U Li ..N . 33 3:3 3`27,!.“3,3•L,a33P!3,zi: 4.i.:,:3,
12 ;OA/ A 31. E; s, p tff .,... .5 :t. ,., .ttt.E;2 t,ItPhv Tj, t•,,;
FA 33, FaiEtiK3203,11;s33,...,,A,
—,, A n iin, Dgl •:: I--k , ----
c•-
Ez,2
,i 1 e 11
7 gl'
E 3 3 3.,-,: 3 33 : i 3E 3 i ti
G, E
tf. 4 .3333.= = 3 3g 3 1',E.
7 E LE
8tt. .2 • I .;.i
t tt 'EA ,,, ," .2 = E-2 =3 '- 7 t3
•,1,3 Le 3E' il .0 E, ,. .;, I, 4,, ,_ ,. ..q , 1;1: 27 7: ,;.: J i
313 1."'.1
!Iy°
`" 0
4 g::1 ,.! "z' i'li:', ji :!:•; 1.,,A',; ,' 'irg'I
'5.11; 4 itil D
2 . ,
filt r\ .,.1 ;..... =',t,,, 1 „ '.,, E3 '33 .;;L; '13. 3 ,33 3.,,,33,-. T.,•:,!. 7..- tt-, i 4, ES t3S., 1t El E2g'
E .1 L
eij:iC 2,0 gt 4 2411 r..' „., . :.,.,, :::3,i':;±',: .''''-' 1 l'!,,k,;,•.:41 tt!:;;.,1'.j,,, .1'' .0, i 'i'LL'' •%1 ii i., .;:'' `.2.i;.1 l'i- L 1 'Nil
8 'l ii 41 41...1i WITA-2., :,,:Alr !,=•.` i .=.' .'..'- :.: ,,.. =..; .-_, ii-;:;h1..,4:: -.2,-,.E.;. 1:.;1_, .:,..i ..,.,L. 3,i 7; fl ,;,,=_,.,. .,,,, r. n,,,,
. ;1 -0 lw. ,7., 1,,,l.:--,..a ,.. .r.;.t.:.; ,. -3i k.,z ,i:-:1!,,,3Cn:=1.1 g'li,;", . .,..,. . ',,,,•,:, t;•i 77,; E.; --': .,'', '34;'::., ii: T.,31 :;-:,
4.4,',,fi3' ii ;.3..11 ,...y. 1,iii2=0 :•;•: ._:,:- .f - :',.'s 3', .2,,;rl.:1. ilgjil,.;:. ;0'4', r-,'J -.-1i ''" '-'-':: !,:11 .-';', ::;E', '.,.; ;T:i; ..'..-:ii
..0-g;;;;; T; p2i ,,1 :::,,;;-'711. 2-iii:,i,-.7 2. ii'F':;. '24.,; EF.22n2,-,t;;;;PI;i4V .2;;21.1 ,i'; ',: 4.2 i'2...; :t 2,•22 22 2;.;',;E 2,; 2., 2 ;
2,
°
.1'
( .1
xi.ST1VA VIIHOIM
',.'3! .L`t'• g iTi‘. 0 '1'
179ii_LS PJE DOLL-
4,:c17/......
rpLiyi- NO
LvAO
N ?=1 d AJV
.-,.- 5•,','_ !,
131MiSlaH„,3H0rand fl;11-E,,ii,,g' 8
-.. —, AiNnooV11H3IA-STVA Vimam (/)7 : ' ,' i.tz iii..;r,..Tsi.c
rl I.
=
r- . ..
.. 1
., IIT .
k11119ISS300V
'.- ';,' gav-'-sr,n-Raino
ift
.ii:
r': 01
t1: i •L 'eql t5. 6", '''', ',i .:•;' T110,1 1; z.- 1 : i.::2 =t1',-; '. ':,!'i iM±.., ;P:=',::,H gV7i i'?. .';',irlkii .t.Y1„,---"
•7 H'%,,,3 ._.:;.: :q. '; ':' '14M'H=',:.':', 7,':: , .!-_:-zi ',7,1;!4.2,q,1 L7T., ,..
ai
' 4 E
'\ 11- - 7.'
A1
T.,...L., i ,;;; .t.. 1 !,t. f.i
I—I'-11• lap /,: 1_1) i H ' .-. . i
1-1"04 'i'''''' Hi! :-r-4-. ,'. 2 ..il
., . ( J.,
.7:
1
''''-" ;I• =', i 9, -'::. 5.3,. ;,...,i'l ':::',:%:.!, ;Ti,, '. .!
f j f: i;ni..,: , ! i 3,,'] Vj.--.1: .3, :.'i... 7,4" "i':: 0 t: •-• .', ;_:.:11; '',! ; pEti.; :;:'::.]= ', ;;ii ,;' 2,s, i,.. 0'-
1
.:•.•:. ;,-
'•'' ''''
.= -T `,. 7' 1 _ .—LJ : •i — / .-ii 7.: ,, 1 T4 --lif
1 .. . f..7. . .71
,
11 i F i ''.; -:.• 1 rWi - 'ILL: „ ',i--,;; tr. -ii 7: i r•NT;17,, L"•••.i "-; ,..,.:,
!LIM .. i ; f,:t I - t-= :,•i,-! r, 1 F.- ,,,t,.., .,..q-Li ;:.:.::] i..,..''.. . '' : ':,!i .:', ..' .'', " Hi !..1
il omm - I. .,•; i I i '..1 itii il, i fP'.: ..z.-;',1, 1;2_ ',-Li.,', ''';', :E. ',', ', ,' if,.,,i4-! ::,i., :--:;',
,, i. 1.i• 't * -.!;1 ",;:',.'- li, EL ,.;;,;_i',L,',' '' .':; i' i:. ,''..' :'-.Z.'-T., ''E'.7,.3;ii L.,: '4 ';.. .,`,''"''' ' —
T. t 11 .!.! li P. i i 1 t •— ! ,..ii
I g , , . '.. : , - .'- ,-, 9 ; '.9. :. 9 i7 ;`! i •:, :'- i i .; tit
i
., 11 ,-, - I. •
,N ' -15E12
1. iM P 11 .r] . ''. I' ; A : v
•a 2 !. i -,:: .i': :.i ,...'.. , I L ..,.',i , -7 ...,1,:-; ',.: 'i. ''_,H ! EA 5 ; 7 I i ilit q 7. 1. 4 '1 '! '
, -!3: i i ii 1 I il i' tht”; P i i
.,:'.; i i ] ".,i : ::. i: ''lt, 7,,, ' L.. H.0 Hi i I .f. il i ilq if II rt Ul I,. !: . 11 I
3 P -. ! '''''': ' 'Jl i I ; ! '''i.- -.7 I : ''':;-;
' ,' ,'S 'ef . , T. T''... ;7 ''.
1 Pil .1:'':..! ii] .1 1 i T.; .' ,.''', ,;• 2..'1::-.ci .• PH il '1 i '6, 1! ViniNt ."' M U " h
g
‹ 0 'i;i1 ::.',F.i tA 1 i i 2: .,;•;;fq. ":,:=. ::1 '%0 0.; ?..i, - - -
...,---g.,EN -:,4t: ;:y,.•]:, :i i'i -.4' :, k, :''''''
E
CO oI o' Kisry\!� mN� N
vE� dweI < 4• g u i� w— axi dsd pbioHoouinn
St,
NOIIVAO `` s °n a A' u , a 3 4, dvn. a A1N1l0OoIZtlliSi1H0oHMri tlS3lHiOtlIilBtlfiJdHoM
II A�JawejDSIc
t ` T
6 I
VAu IdSdO3
ri
). a
9t % l Y - E _6s s r4I 3 � ms- S• E b E E F i .e
iiii
t '
�8a = >�PF �2.. .. �.. 26B B 9.kw' � �S�t �..- �.�::
b
g x � E — l�ll .� H.
bi b E5
ace s e LH
11 s g
s
} €a`m yby u5 ® Egg
$ ag P FE "� A�
71 c�� as g 3 X 2 H i 3;;
n� m`5kE.¢ SR 5� ca 5. �S '.3 � � �c=xru$E -. _..-w_.._ _.,._" ; �;...-
z 105, �' a ■ S 8 "gas
qg
h b - x 8 E G e s 8
E 7.i E E—JII�11� g $
ti
1 a - gs
k -
•
:_ -- , 5mg A - 7
4 P EN _gtg m�.F ,t . :' �: $ a s . .sg g. i «K �n.e,_"LLS F C - .
a0miplit ® mE o" . e e " hiliM a s L E E a is•-w i y`N € b c € ! Ei -
Laic , ._,',. 4 4..-%.
'Ili
� s me '" g
p.
a ,4ii ,-, .,] 00
�x $g %sa
.. ... FoL 2 a .VI s a & s $E laMil!! ] _ t
��§ 8z ,. 3 B , _ � r .aa W mN
g°SIlHH tl11HOIM
I 3r °
0 m otN rsrn2+f^ aLei G Noildnov�bdw � Q S -Ad ,,_I - 6 o -A a y a hX1l3a1SPEEOPGL
fzi
3H Orland VJ. :, ya V1--1 ldLSIaH1lt1S d1I- IM '1:i 72iiw.a ,..�,..W „.,, awepsid ,� a AlNfOaV1IH�IM,�mvIO
vav-S]NIl]aIfJ kLI1I8ISS303H
F LA
z=
= yfIIIII
a
x' ¢
- ak _ z€
iiti
in
8S 5$ ap �EasrC a Y _ _4a r ,s a . ta` _s _ a ^ _� i . _ sts R ter s„ a: E _12 _ 3Ea a gE
TT
. .,, :..:,..: E..; -. 173, 3 : ; 3tt333 ' - 3.-3'. 3 . 33333
e 4 g€ $.
t ' '' -' 411 , 6 ,5 „ ._ t . ,.:
gil
N
t .
Rg 4" - 33 Le�441:17-
I 5 "
'a a -i� w n� zs - s
rn cage } �,ese=€esAiiitgli ,� e.sa ^"st,. w a s.= si a$,
of U I I IQ ¥ ' x Ti ®11 n , �� 5 &
V G ff"
Q °6 �& ,.1,n E ,� y (.I 3 - b
o: § I� E - z 4 = a
o
E E a m o k
Q
oa
Q
oa 2
�_
N., _"., pb_ .�5 .e. .... r.s=., _.e _ _ _. _ ,.,m e,�an m �. .: .,. .
La
m
0 Dior*/ 47. xi'STI'd VlIH'JIM CD
o?5 133d15 PP£()DLL O
CP ea ^ S
NOIld/10N3J dWdb QuR3 av5 1\J
3' �Z A�� N _R z N c� v a
°yi_ * rg 101?11SI4 H11V3H 0119f1d a g� . LL 0 ° w`g w. ff W
s'nvvtn AINf1OO tl1IHOIM-S11Vd VIIHDIM V"Q ', °E. `a „„, ,T,
a -
u
� P e
I a
a
•
bl
„
° R
Z
J J
cc 5
w CO
=H
(7 Z Z
ZW 4
P� a
ma cx wa rLIJ n
w
m
1874,470- X1 S11V3 VII HOIM I y z
133b1S P.[E COL II.
z O
I a, d
Is NOIIVAON3b dWF1 Q V w r o —
o2
L � �Z � ` � Z N LLD z V
'i_ lORLLSI4 H1ltl3H 0119v ld ' ^ E„M1 6 g w g , y N
snhdvsw, AiNfO3 V1IHOIM-Slltlg tllIHOIM �f f Q °n W
' _ 6 G : 5
- . a G _ E 6 FA -.Gs 3
c '4
8 e 2
y 1 ' = s
rO ,.',P..
,, s.. �s € ? 5 aI t
r = r r . o s_t s _; p
LU w - cc _1
z , L�� ;IL .. a = .• , _ t7 - -- 'Al a lase I I !—I
in
I_
a � �� II
b
w , 85 Er €
% I I_ ' ' € §'r II s ` iTI I 1 . , 1-14I I
l� ^ [I TIC
III 6 G _ .
iII lo . i F
ti
z f 3 z 5 , � j I III II II'r
w a� Y _ s 11=1
w �' 0 as x sE r I, ��'tll l
UF,5 Ls Es a
ll L111
I I ., III I —IIL
I 1 I=IIE
Z II I1 I
Z, I ; I FoII i I lIeI
fig€ € w
n ' w _ '! 0z�r:s oa 6R WIR
I I
3 1 7.az" — I I
v r
'
ae\ : {
r
ir
I ,Y
I
\r �� - H' Z I F. I O
LL
ri
o � i 2 o
\\\ L o .a LL s \ z, \ ❑z
a
,..004DfS ,T ate+ Xi'SI�HL 71IHSIM x N =
_ 1 �2315 PEE DOLL I O
w d o
u N011b/�ON32i dWHZI <( E6 .: °0 o
�- J gP' .n W Z v
ai.s _ .LaI iSI0 H1ltl3H OI19fld r^1 = sR° w"g w a
na3a AlNf OO tl11HOIM•Slltld tllIHJIM V / >r = 1.4R .a N w y ti Q §
1.
'- " 3w'LL a
Z 51
E 4 v Q 4 L'- r
s 4 a '
1 i h'r., ',6' h! "2 .;', 0
— v =
\m g�
1 IIII11I 1 1 1.. § j
ZO Jlllll J __j z
W II II 1 ,: LL 11
r.n �I II Z ! �� 1 11 J
11-11_ a p a e III '�_ Ze
— w 1 H ~
m _I 11
'I a' 11 J i , ,I I „a `,Ii _ = O
01— , ', 5:=1 _II J 'H
�� r> -, Z O 3 TEE
W
a • W _ 1 _f a s m
p uj
Lu
V, Z i C[ m a - a m
e s a. w 3 I w s5 i - Z;
DF
s.a /i i9 i mom e 3 0 �J /D
L
rc
O
` JNDRIdd ;I jDNIONtld �—JJ . a
I I gON zs
O$ 53 E I3 Q
m
02
V
U. w
J
. fIgv aLL m
'Y 8g 5 ,10 F€11 V
¢@ape
Kd �(s Xl S-17HHV11HOI M '
q— z
_aEd15 we ooc Os
NOI AON32i d11V
OlalSl❑Hlltl3H O19nd <� _
_E
� t g 4� '
-1.6"1 A1NlO9Y11H3IM-S1V.YIIHOIM V,/¢ 44- i?;„ dg w„ o
N `a - Q
§.1 a �' six g EeE. _ "3 !.0, •
wag LLi w o awo oca,F3P., .10?
\• W C eCo 5 8 g.
_� Sg to
" co
\' b Z m
Z " _ N � „me
` -_` OU
o ' Z
r + a
m ¢P _ °
oho OF. g LI— I. — a r"
LI
., s
t
as - '- ., ,
L B di N
o w, 2` La �`
'I a
' w
K g
, J
m II
vN_, z, 47,:Eta,:11 d s 3 aPs'
,„s,z08.,„,11.
ff T, N EN a` f
_N_-- s€o aLL =
x
w
a� = w E ,re
o �. wr LL� ig Z �. E'�U6 at
ag Z e g*3 .. .5 .,. 7") s, @�E 2.2. 5
am
WI
/ ' Uq Ct6 ,. IX
, r zo
I I m I