Loading...
Res 119-2020 Change Order 1 2020 Alley Rehab Project 12/15/2020Resolution No. 119-2020 Resolution authorizing the City Manager to award bid and contract for the 2020 Alley Rehabilitation Project to Freeman Paving, LLC in the amount of $29,440.00 WHEREAS, the City of Wichita Falls entered a unit price contract with Freeman Paving, LLC for the 2020 Alley Rehabilitation Project with the estimated total cost of $274,455.00; and, WHEREAS, the City of Wichita Falls has negotiated Change Order No. 1 for an addition of $29,440.00 for a final contract amount of $303,895.00. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The City Manager is authorized to execute Change Order No. 1 for the 2020 Alley Rehabilitation Project in the amount of $29,440.00. PASSED AND APPROVED this the 15t" day of December, 2020. ATTEST: c� B City Clerk CITY OF WICHITA FALLS, TEXAS CHANGE ORDER NO.: 1 CONTRACT CHANGE ORDER FORM DATE: 11/30/2020 AMOUNT OF CHANGE: $ 29,440.00 PROJECT/CONTRACT: 2C20 ALLEY REHABILITATION PROJECT, CWF20-530-05 TO: Freeman Paving, LLC , this Change Order, after approval by the Owner, will be your (Contractor) authority to make the following changes in the work under your contract: Decrease Increase Total Change Description of Changes in Contract in Contract in Contract (This Change Order will add items needed to repair pavement inside the City Transfer Station on Lawrence Rd) 1. Bid Item 203.3-RP - Remove Exisitng Internal Transfer Station Pavement $ - $ 5,120.00 $ 5,120.00 Add 128 SY @ $40,001SY for a revised total of 128 SY 2. Bid Item 301.2-FB - 6" TxnOT Grade 3 Flex Base $ - $ 7,680.00 $ 7,680.00 Add 256 SY @ $30/SY for a revised total of 256 SY 3. Bid Item 303.1 - Install 10" Reinforced Concrete Pavement $ - $ 16,640.00 $ 16,640.00 Add 128 SY @ 5130.001SY for a revised total of 128 SY TOTAL $ - $ 29,440.00 $ 29,440.00 AMOUNT OF ORIGINAL CONTRACT: $ 274,455.00 TOTAL AMOUNT OF THIS CHANGE ORDER: $ 29,440.00 TOTAL AMOUNT OF PREVIOUS CHANGE ORDERS: $ - CONTRACT AMOUNT TO DATE: $ 303,895.00 The completion time under your contract will be extended by fourteen (14) days because of this change order making the revised completion date February 19, 2021. Approved By Owner: Accepted By Contractor: Recommended By Arch/Eng: (if applicable) By: By; _ - —tm By: r"0 ? .1'4 Title:_City Manager Title: v bJ i)Q (- Title:_City Engineer Date: Date: a i a Date: /-�-3- Z0