Res 047-2012 6/1/2012
RESOLUTION NO. _47-2012_
Resolution Awarding Bid and Contract for the 2012 Kemp Boulevard
Drainage Project (CWF12-552-10) to A&M Construction and Utilities,
Inc. In An Estimated Total Amount of $714,494.00
WHEREAS, the City of Wichita Falls has advertised for bids for the Third &
Fourth Street Pavement Improvement Project (CWF12-552-10); and
WHEREAS, it is found that the lowest responsible bidder is A&M Construction &
Utilities, Inc., which made a unit price bid with an estimated total of $714,494.00.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
The Kemp Boulevard Drainage Project (CWF12-552-10) is awarded to A&M
Construction & Utilities, Inc., in an estimated total amount of $714,494.00, and the City
Manager is authorized to execute a contract for the City with said Contractor for the
construction of such project.
th
PASSED AND APPROVED this the 5 day of June, 2012.