RESOLUTION NO. _31-2012_
Resolution Approving Change Order No. 1 To The Transfer Station
Tipping Floor Replacement Project (CWF12-530-12) In The Amount
Of $116,276.00
WHEREAS, the City of Wichita Falls entered into a unit price contract with
Scale Concrete Construction Co. for the Transfer Station Tipping Floor Replacement
Project (CWF12-530-12), with the estimated total cost of $548,541.00;
WHEREAS, Change Order No. 1 will increase the contract $116,276.00 for a
revised cost of $664,817.00; and
WHEREAS, City staff has reviewed all aspects of this change order and
believes that it is in the City’s best interest to approve.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF WICHITA FALLS, TEXAS, THAT:
Change Order No. 1
The attached to the Transfer Station Tipping Floor
Replacement Project (CWF12-530-12) is approved, in the amount of $116,276.00, and
the City Manager is authorized to execute said change order.
PASSED AND APPROVED this the 3rd day of April, 2012.