Res 041-2019 Alley Rehab Project Bid to Gary Barker Construction 5/7/2019
Resolution No41-2019
.
Resolution authorizing the City Manager to award bid and contract for
the 2019 Alley Rehabilitation Project to Cage Construction and
Management Co. dba Gary Baker Construction in the amount of
$303,349.00
WHEREAS, the City of Wichita Falls has advertised for bids for the 2019 Alley
Rehabilitation Project; and,
WHEREAS, it is found that the lowest responsible bidder is Gary Baker
Construction who made a unit price bid with an estimated total of $303,349.00.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
The unit price bid for the 2019 Alley Rehabilitation Projectis awarded to Gary
Baker Construction, in an estimated total amount of $303,349.00, and the City Manager
is authorized to execute a contract for the City with said Contractor for the construction of
such project.
th
PASSED AND APPROVED this the 7 day of May, 2019.
______________________________
M A Y O R
ATTEST:
____________________
City Clerk