4A Wichita Falls Economic Development Minutes - 02/06/2018MINUTES OF THE
WICHITA FALLS ECONOMIC DEVELOPMENT CORPORATION
February 6, 2018
PRESENT:
Dick Bundy, President § WFEDC Members
Reno Gustafson, Vice President/Secretary-Treasurer §
Leo Lane §
Darron Leiker §
David Toogood §
Stephen Santellana, Mayor
Jim Dockery, Deputy City Manager/CFO
R. Kinley Hegglund, Jr., City Attorney
Karen Montgomery -Gagne, Planning Administrator
Linda Merrill, Recording Secretary
Henry Florsheim, CEO
Kevin Pearson, V.P., Economic Development
Travis Haggard, V.P., BR&E
Adrene Wike, Research Associate
Brian Havins, Marketing
Sarah Harpole, Administrative Assistant
Kathy Jordan, Deputy Commander, Mission Support Group
Keith Maxwell, Resident Engineer
Roderick Edwards, 82d Contracting Squadron
Timothy Fast, Comptroller
Richard Pfeffer, FMA-AF Budget
Christian Erneston, 1 Lt.
Jackie Jastrzeloski, Sheppard Public Affairs
John Ingle, Sheppard Public Affairs
M. Brent Boydston, Sheppard AFB JAG
Mark Mc Burnett, Base Civil Engineer
1. Call to Order
Dick Bundy called the meeting to order at 3:35 p.m.
2. Approval of Minutes (1/18/18)
Mayor and Council
City Staff
§ CCI
§ USAF
DoD
Reno Gustafson moved for approval of the minutes. Seconded by Leo Lane, the motion
carried 4-0. (Mr. Leiker was not present when the vote was taken.)
3. Discussion and possible amendment of Sheppard AFB main gate project agreement
Lt. Col. Kathy Jordan said the Sheppard AFB main gate project is divided into two projects.
The federal government, city and state have rules and limitations on the distribution of funds, and
they do not have a solution. She knows of two options: (1) a gift of money to the Air Force (a
lengthy process), or (2) the city can hire a contractor to execute the Defense Economic Adjustment
Assistance Grant (DEAAG)/4A monies.
Mr. Lane asked why this project is different. Mr. Dockery said the last project was a City
project on City -owned land. This project is on base. DEAAG funding is administered on a
reimbursement basis. Funding from the 4A Board is typically provided on a reimbursement basis,
but that will not work with this project. The military needs all of the funds in their system, or the
City will become the administrator of the $3 million companion project (DEAAG/4A grants) and
the Air Force's $2.7 million project.
Mr. Bundy said the 4A Board has a commitment now of $1.5 million, and the question
before the Board is whether to loan or gift another $1.5 million to the project and be reimbursed
by DEAAG. Mr. Hegglund said the City would submit paperwork to the state on a quarterly basis,
showing the amount of the project completed, and request reimbursement. It would take 12-18
months to receive total reimbursement for the additional $1.5 million. Karen Montgomery-Gagnd
said the City would not be reimbursed until the December 2018 quarter, with the last
reimbursement made by July 2019.
Mr. Bundy asked when the money would have to be committed. Ms. Gagnd said the City
would be solely responsible for all grant obligations, and the funds have to be spent by August 31,
2019. Mr. Bundy asked what happens if the funds do not get spent. Ms. Gagnd said there are
potential scenarios; any remaining funds may not get reimbursed; the City might be fined; or may
have to pay the state back for grant funds already reimbursed.
Mr. Hegglund asked Mark Mc Burnett if it would be satisfactory if the 4A gave Sheppard
$3 million, and obtained reimbursement of $1.5 million through DEAAG funds. Mr. Mc Burnett
said the Corps of Engineers would need the $3 million appropriated to them before they could start
the project. They have federally appropriated $2.7 million to address anti -terrorism force
protection issues, so the City would not be responsible for oversight of the entire $5.7 million
project, but only for the $3 million portion. Mr. Hegglund said DEAAG grant application is a $5.7
million project. The City is responsible for the entire project according to the Governor's office.
Ms. Gagne said SAFB cannot relinquish oversight of the $2.7 million portion of the project, and
cannot mix those funds with the DEAAG/4A funds. It is her understanding that these projects must
be separate/companion projects, not one effort.
Mr. Bundy asked if the money could be provided as an interest -free loan. Lt. Col. Jordan
said they cannot accept a loan. It can be a gift, or a contract with the Corps.
Mr. Leiker said the WFEDC is tying up $1.5 million for a year and a half. Mr. Dockery
said this has to be worked out administratively, as no one wants to oversee a $3 million contract
on base property. Lt. Col. Jordan said that although the Air Force would not own the contract, they
could oversee the day-to-day completion of the project.
Mr. Mc Burnett said the $2.7 million project can be awarded to the Corps, and the other
project can go to the Corps' contractor. They can be accomplished simultaneously, but legally,
they stand alone. Mr. Dockery said DEAAG requires quarterly documents in order to draw down
funds to reimburse 4A for its $1.5 million.
Mr. Hegglund asked if the 4A Board is willing to act as a general contractor or to hire one.
Mr. Bundy said he did not think so. Mr. Hegglund said the other option is to front the money and
hope there would be enough time to finish. Ms. Gagnd said they would not utilize DEAAG money
until the fall of 2018. Lt. Col. Jordan said they cannot even start on the design until they have all
the money. Mr. Dockery said there is a risk in not timely completing the project.
Engineer Keith Maxwell said the Corps' construction oversight, Title II Services, will be
on site for the federal project. Mr. Hegglund asked if they would check both projects, and
Mr. Maxwell replied, conceivably. Mr. Hegglund asked what is encompassed in the City's portion
of the project. Mr. Mc Burnett said they are non -security issues, including storm water
infrastructure, fencing, additional lighting, and mounding/landscaping areas.
4. Executive Session
Mr. Bundy adjourned the meeting into executive session at 4:07 p.m. pursuant to Texas
Government Code §551.087. He announced the meeting back into regular session at 5:42 p.m. The
subjects posted in the Notice of Meeting were deliberated, and no votes or further action was taken
on these items in executive session.
5. Motions
Nexstar
Mr. Leiker moved to approve an incentive agreement of up to $7 000 per job for 25 jobs
based upon retention of those jobs for at least six months. Seconded by Mr. Bundy, the motion
failed 3-2.
Mr. Lane moved to offer Nexstar an incentive agreement of up to $4,000 per job for 25
welding positions so long as these positions are filled in 2018 based upon job retention of at least
six months; further, he moved to offer an additional $3,000 per job for those employees brought
in from outside Wichita County, who establish residency in Wichita County, and remain employed
by Nexstar for at least six months.
SAFB Main Gate Project
Mr. Leiker moved to appropriate an additional $1.5 million for the SAFB Main Gate
Project with the understanding that the WFEDC would keep the reimbursement from the State
DEAAG Grant and enter into ppropriate legal and contractual agreements with all necessary
agencies Seconded by Mr. Gustafson the motion carried 4-1, with Mr. Toogood in opposition.
Amfuel
Mr. Lane moved to accept the offer from Amfuel of $90 000 for the purchase of the
autoclave Seconded by Mr. Leiker, the motion carried 4-0, with Mr. Gustafson abstaining from
Voting.
6. Adjourn
Mr. Leiker moved to adjourn the meeting. The meeting adjourned at 5:46 p.m.
V
Di k Bundy, resident